Financier | Commitments |
---|---|
Borrower/Recipient | 12.00 |
ICELAND: Icelandic International Development Authority | 3.50 |
Strategic Climate Fund Grant | 24.50 |
IDA Credit | 29.43 |
IDA recommitted as a Credit | 149.07 |
P133613
Closed
Kenta Usui , Abdulhakim Abdisubhan
Government of Ethiopia
September 27, 2013
(as of board presentation)
May 29, 2014
August 5, 2014
US$ 218.50 million
Ethiopian Electric Power
2014
US$ 206.50 million
A
March 14, 2024
December 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 12.00 |
ICELAND: Icelandic International Development Authority | 3.50 |
Strategic Climate Fund Grant | 24.50 |
IDA Credit | 29.43 |
IDA recommitted as a Credit | 149.07 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 178.50 |
IBRD + IDA Commitment | 178.50 |
Lending Instrument | |
---|---|
Grant Amount | 28.00 |
Total Project Cost** | 218.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 16, 2024 | IDA-54680 | Loan Disb | 382,429.70 |
Mar 1, 2024 | IDA-54680 | Loan Disb | 215,707.05 |
May 29, 2014 | IDA-54680 | Loan Commitment | 178,500,000.00 |
May 19, 2023 | IDA-54680 | Loan Disb | 2,767,211.50 |
Nov 30, 2023 | IDA-54680 | Loan Cancel | 22,630,000.00 |
Dec 5, 2023 | IDA-54680 | Loan Disb | 2,391,749.50 |
Jan 12, 2024 | IDA-54680 | Loan Disb | 126,141.82 |
Jan 18, 2024 | IDA-54680 | Loan Disb | 2,291,543.00 |
Nov 20, 2023 | IDA-54680 | Loan Disb | 688,950.40 |
Feb 1, 2016 | IDA-54680 | Int Charges | 75.74 |
Feb 1, 2016 | IDA-54680 | Int Charges | 75.74 |
Feb 1, 2016 | IDA-54680 | Int Charges | 29,904.22 |
Feb 1, 2016 | IDA-54680 | Int Charges | 29,904.22 |
Aug 1, 2018 | IDA-54680 | Int Charges | 31,860.61 |
Aug 1, 2018 | IDA-54680 | Int Charges | 31,860.61 |
Feb 1, 2019 | IDA-54680 | Int Charges | 337.81 |
Feb 1, 2019 | IDA-54680 | Int Charges | 337.81 |
Feb 1, 2019 | IDA-54680 | Int Charges | 31,071.62 |
Feb 1, 2019 | IDA-54680 | Int Charges | 31,071.62 |
Oct 31, 2017 | IDA-54680 | Loan Disb | 352,680.28 |
Aug 1, 2017 | IDA-54680 | Int Charges | 217.80 |
Aug 1, 2017 | IDA-54680 | Int Charges | 217.80 |
Aug 1, 2017 | IDA-54680 | Int Charges | 30,136.63 |
Aug 1, 2017 | IDA-54680 | Int Charges | 30,136.63 |
Feb 1, 2017 | IDA-54680 | Int Charges | 30.12 |
Feb 1, 2017 | IDA-54680 | Int Charges | 30.12 |
Feb 1, 2017 | IDA-54680 | Int Charges | 29,426.16 |
Feb 1, 2017 | IDA-54680 | Int Charges | 29,426.16 |
Aug 3, 2016 | IDA-54680 | Int Charges | 86.57 |
Aug 3, 2016 | IDA-54680 | Int Charges | 30,503.00 |
Aug 3, 2016 | IDA-54680 | Int Charges | 30,503.00 |
Aug 3, 2016 | IDA-54680 | Int Charges | 86.57 |
Aug 1, 2015 | IDA-54680 | Int Charges | 16,788.19 |
Aug 1, 2015 | IDA-54680 | Int Charges | 16,788.19 |
Apr 21, 2015 | IDA-54680 | Loan Disb | 8,000,000.00 |
Mar 19, 2020 | IDA-54680 | Loan Disb | 9,251,850.00 |
Feb 1, 2020 | IDA-54680 | Int Charges | 7,220.49 |
Feb 1, 2020 | IDA-54680 | Int Charges | 7,220.49 |
Feb 1, 2020 | IDA-54680 | Int Charges | 83,683.02 |
Feb 1, 2020 | IDA-54680 | Int Charges | 83,683.02 |
May 26, 2020 | IDA-54680 | Loan Cancel | 50,000,000.00 |
May 21, 2020 | IDA-54680 | Loan Disb | 2,600,829.50 |
Sep 15, 2020 | IDA-54680 | Loan Disb | 8,881,430.00 |
Apr 25, 2019 | IDA-54680 | Loan Disb | 5,534,423.00 |
Jun 13, 2019 | IDA-54680 | Loan Disb | 571,250.44 |
Jun 13, 2019 | IDA-54680 | Loan Disb | 2,048,718.60 |
Jun 11, 2019 | IDA-54680 | Loan Disb | 3,731,672.20 |
Jun 13, 2019 | IDA-54680 | Loan Disb | 1,005,620.30 |
Aug 1, 2019 | IDA-54680 | Int Charges | 338.48 |
Aug 1, 2019 | IDA-54680 | Int Charges | 338.48 |
Aug 1, 2019 | IDA-54680 | Int Charges | 42,328.63 |
Aug 1, 2019 | IDA-54680 | Int Charges | 42,328.63 |
Nov 15, 2019 | IDA-54680 | Loan Disb | 945,399.50 |
Nov 22, 2019 | IDA-54680 | Loan Disb | 2,123,166.50 |
Feb 1, 2018 | IDA-54680 | Int Charges | 613.27 |
Feb 1, 2018 | IDA-54680 | Int Charges | 613.27 |
Feb 1, 2018 | IDA-54680 | Int Charges | 31,537.09 |
Feb 1, 2018 | IDA-54680 | Int Charges | 31,537.09 |
Aug 1, 2018 | IDA-54680 | Int Charges | 805.51 |
Aug 1, 2018 | IDA-54680 | Int Charges | 805.51 |
Mar 16, 2022 | IDA-54680 | Loan Disb | 5,987,572.00 |
Apr 8, 2022 | IDA-54680 | Loan Disb | 1,745,783.10 |
May 10, 2022 | IDA-54680 | Loan Disb | 3,395,136.00 |
Jun 9, 2021 | IDA-54680 | Loan Disb | 6,203,933.00 |
Aug 1, 2021 | IDA-54680 | Int Charges | 1,101.91 |
Aug 1, 2021 | IDA-54680 | Int Charges | 1,101.91 |
Aug 1, 2021 | IDA-54680 | Int Charges | 211,719.00 |
Aug 1, 2021 | IDA-54680 | Int Charges | 211,719.00 |
Aug 1, 2020 | IDA-54680 | Int Charges | 275.20 |
Aug 1, 2020 | IDA-54680 | Int Charges | 275.20 |
Aug 1, 2020 | IDA-54680 | Int Charges | 120,227.88 |
Aug 1, 2020 | IDA-54680 | Int Charges | 120,227.88 |
Feb 10, 2021 | IDA-54680 | Loan Disb | 2,404,632.00 |
Feb 10, 2021 | IDA-54680 | Loan Disb | 7,345,420.00 |
Feb 1, 2021 | IDA-54680 | Int Charges | 3,740.69 |
Feb 1, 2021 | IDA-54680 | Int Charges | 3,740.69 |
Feb 1, 2021 | IDA-54680 | Int Charges | 166,704.10 |
Feb 1, 2021 | IDA-54680 | Int Charges | 166,704.10 |
Feb 1, 2023 | IDA-54680 | Int Charges | 5,360.38 |
Aug 3, 2022 | IDA-54680 | Int Charges | 251,629.81 |
Aug 3, 2022 | IDA-54680 | Int Charges | 251,629.81 |
Aug 3, 2022 | IDA-54680 | Int Charges | 190.43 |
Aug 3, 2022 | IDA-54680 | Int Charges | 190.43 |
Feb 2, 2022 | IDA-54680 | Int Charges | 4,172.34 |
Feb 2, 2022 | IDA-54680 | Int Charges | 4,172.34 |
Feb 2, 2022 | IDA-54680 | Int Charges | 229,356.33 |
Feb 2, 2022 | IDA-54680 | Int Charges | 229,356.33 |
Feb 25, 2022 | IDA-54680 | Loan Disb | 3,057,660.20 |
Aug 7, 2023 | IDA-54680 | Int Charges | 6,156.78 |
Aug 7, 2023 | IDA-54680 | Int Charges | 6,156.78 |
Aug 7, 2023 | IDA-54680 | Int Charges | 273,612.22 |
Aug 7, 2023 | IDA-54680 | Int Charges | 273,612.22 |
Feb 1, 2023 | IDA-54680 | Int Charges | 262,309.97 |
Feb 1, 2023 | IDA-54680 | Int Charges | 262,309.97 |
Feb 1, 2023 | IDA-54680 | Int Charges | 5,360.38 |
Feb 28, 2024 | IDA-54680 | Loan Disb | 137,662.02 |
Jul 16, 2024 | IDA-54680 | Loan Disb | -4,750.02 |
Aug 1, 2024 | IDA-54680 | Int Charges | 1,968.91 |
Aug 1, 2024 | IDA-54680 | Int Charges | 1,968.91 |
Aug 1, 2024 | IDA-54680 | Int Charges | 304,419.75 |
Jan 25, 2024 | IDA-54680 | Loan Disb | 792,943.94 |
Feb 9, 2024 | IDA-54680 | Loan Disb | 339,920.90 |
Jan 26, 2024 | IDA-54680 | Loan Disb | 234,725.19 |
Feb 5, 2024 | IDA-54680 | Int Charges | 1,751.03 |
Feb 5, 2024 | IDA-54680 | Int Charges | 1,751.03 |
Feb 5, 2024 | IDA-54680 | Int Charges | 281,358.97 |
Feb 5, 2024 | IDA-54680 | Int Charges | 281,358.97 |
Aug 1, 2024 | IDA-54680 | Int Charges | 304,419.75 |
Aug 1, 2024 | IDA-54680 | Loan Repay | 820,497.10 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2023-12-01 |
Financial Management | Moderately Satisfactory | 2023-12-01 |
Procurement | Moderately Satisfactory | 2023-12-01 |
Project Management | Moderately Satisfactory | 2023-12-01 |
Counterpart Funding | Satisfactory | 2023-12-01 |
Monitoring and Evaluation | Satisfactory | 2023-12-01 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-01 |
INDICATOR | ICR REVIEW: 12-23-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Geothermal wells with potential to generate electricity | Value | 0.00 | 9.00 | 8.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Geothermal wells drilled and tested | Value | 0.00 | 12.00 | 14.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Geothermal sites confirmed | Value | 0.00 | 1.00 | 1.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Geothermal sector strategy developed | Value | No | No | Yes |
Date | May 26, 2020 | November 9, 2023 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Training/Workshops held | Value | 0.00 | 2.00 | 2.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Civil work and water supply construction finalized | Value | No | Yes | Yes |
Date | May 26, 2020 | November 9, 2023 | December 31, 2021 | |
Comment |
EEP Staff trained | Value | 0.00 | 28.00 | 45.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
First rig installed in Aluto site | Value | No | Yes | |
Date | May 26, 2020 | June 7, 2022 | ||
Comment |
EEP retrained procurement staff | Value | 0.00 | 2.00 | 4.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Second rig arrival in Aluto site | Value | No | Yes | |
Date | May 26, 2020 | June 7, 2022 | ||
Comment |
GSE/MoWIE/MoM staff trained | Value | 0.00 | 18.00 | 45.00 |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
First rig drilling operation starts | Value | No | Yes | |
Date | May 26, 2020 | June 7, 2022 | ||
Comment |
Feasibility study completed | Value | No | No | Yes |
Date | April 21, 2014 | November 9, 2023 | December 31, 2021 | |
Comment |
Second rig drilling operation starts | Value | No | Yes | |
Date | May 26, 2020 | June 7, 2022 | ||
Comment |
Geothermal capacity confirmed for electricity generation | Value | 0.00 | 26.00 | 35.00 |
Date | June 1, 2014 | November 9, 2023 | August 5, 2021 | |
Comment |