Financier | Commitments |
---|---|
IDA Credit | 410.00 |
Borrower/Recipient | 61.76 |
P133653
Closed
Kwabena Amankwah-Ayeh
People's Republic of Bangladesh
February 13, 2013
(as of board presentation)
January 14, 2014
April 6, 2014
US$ 471.76 million
Bangladesh Municipal Development Fund (BMDF),Local Government Engineering Department
2014
US$ 410.00 million
B
Not Applicable
May 31, 2022
Yes
BANK APPROVED
August 9, 2023
Financier | Commitments |
---|---|
IDA Credit | 410.00 |
Borrower/Recipient | 61.76 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 410.00 |
IBRD + IDA Commitment | 410.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 471.76 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 31, 2020 | IDA-53390 | Loan Disb | 12,531,486.00 |
Sep 10, 2020 | IDA-53390 | Loan Disb | 2,528,605.50 |
Dec 15, 2020 | IDA-53390 | Int Charges | 11,383.52 |
Dec 15, 2020 | IDA-53390 | Int Charges | 11,383.52 |
Dec 15, 2020 | IDA-53390 | Int Charges | 1,199,006.20 |
Dec 15, 2020 | IDA-53390 | Int Charges | 1,199,006.20 |
Dec 7, 2020 | IDA-53390 | Loan Disb | 12,045,462.00 |
Mar 18, 2021 | IDA-53390 | Loan Disb | 13,895,637.00 |
Mar 18, 2021 | IDA-53390 | Loan Disb | 4,084,648.50 |
Jun 15, 2021 | IDA-53390 | Int Charges | 24,722.18 |
Jun 15, 2021 | IDA-53390 | Int Charges | 24,722.18 |
Jun 15, 2021 | IDA-53390 | Int Charges | 1,315,325.60 |
Jun 15, 2021 | IDA-53390 | Int Charges | 1,315,325.60 |
Dec 15, 2019 | IDA-53390 | Int Charges | 12,680.71 |
Dec 15, 2019 | IDA-53390 | Int Charges | 12,680.71 |
Dec 15, 2019 | IDA-53390 | Int Charges | 855,084.30 |
Dec 15, 2019 | IDA-53390 | Int Charges | 855,084.30 |
Jun 15, 2020 | IDA-53390 | Int Charges | 41,881.70 |
Jun 15, 2020 | IDA-53390 | Int Charges | 41,881.70 |
Jun 15, 2020 | IDA-53390 | Int Charges | 1,129,432.00 |
Jun 15, 2020 | IDA-53390 | Int Charges | 1,129,432.00 |
Oct 1, 2018 | IDA-53390 | Loan Disb | 12,390,448.00 |
May 15, 2019 | IDA-53390 | Loan Disb | 19,909,112.00 |
Jun 15, 2019 | IDA-53390 | Int Charges | 673,226.44 |
Jun 3, 2019 | IDA-53390 | Loan Disb | 14,932,663.00 |
Jun 20, 2019 | IDA-53390 | Loan Disb | 9,245,149.00 |
Jun 15, 2019 | IDA-53390 | Int Charges | 8,324.46 |
Jun 15, 2019 | IDA-53390 | Int Charges | 8,324.46 |
Jun 15, 2019 | IDA-53390 | Int Charges | 673,226.44 |
Dec 2, 2019 | IDA-53390 | Loan Disb | 30,949,116.00 |
Dec 3, 2019 | IDA-53390 | Loan Disb | 25,677,268.00 |
Oct 24, 2019 | IDA-53390 | Loan Disb | 17,469,422.00 |
Dec 15, 2017 | IDA-53390 | Int Charges | 464,826.03 |
Dec 15, 2017 | IDA-53390 | Int Charges | 464,826.03 |
May 29, 2018 | IDA-53390 | Loan Disb | 14,845,998.00 |
Jun 15, 2018 | IDA-53390 | Int Charges | 5,801.26 |
Jun 15, 2018 | IDA-53390 | Int Charges | 5,801.26 |
Jun 15, 2018 | IDA-53390 | Int Charges | 503,488.80 |
Jun 15, 2018 | IDA-53390 | Int Charges | 503,488.80 |
Dec 15, 2018 | IDA-53390 | Int Charges | 5,274.87 |
Dec 15, 2018 | IDA-53390 | Int Charges | 5,274.87 |
Dec 15, 2018 | IDA-53390 | Int Charges | 603,386.30 |
Dec 15, 2018 | IDA-53390 | Int Charges | 603,386.30 |
Feb 11, 2019 | IDA-53390 | Loan Disb | 17,732,102.00 |
Mar 30, 2017 | IDA-53390 | Loan Disb | 17,576,898.00 |
Feb 23, 2017 | IDA-53390 | Loan Disb | 11,014,613.00 |
Feb 23, 2017 | IDA-53390 | Loan Disb | 5,067,591.50 |
Jun 15, 2017 | IDA-53390 | Int Charges | 365,856.56 |
Jun 15, 2017 | IDA-53390 | Int Charges | 365,856.56 |
Jun 15, 2017 | IDA-53390 | Int Charges | 8,625.25 |
Jun 15, 2017 | IDA-53390 | Int Charges | 8,625.25 |
Nov 1, 2017 | IDA-53390 | Loan Disb | 6,559,574.00 |
Apr 23, 2018 | IDA-53390 | Loan Disb | 14,796,698.00 |
Dec 15, 2017 | IDA-53390 | Int Charges | 8,734.87 |
Dec 15, 2017 | IDA-53390 | Int Charges | 8,734.87 |
Apr 27, 2016 | IDA-53390 | Loan Disb | 7,423,469.50 |
Jun 15, 2016 | IDA-53390 | Int Charges | 2,603.27 |
Jun 15, 2016 | IDA-53390 | Int Charges | 2,603.27 |
Jun 15, 2016 | IDA-53390 | Int Charges | 171,065.12 |
Jun 15, 2016 | IDA-53390 | Int Charges | 171,065.12 |
May 25, 2016 | IDA-53390 | Loan Disb | 7,452,450.50 |
Oct 13, 2016 | IDA-53390 | Loan Disb | 6,435,842.00 |
Jun 27, 2016 | IDA-53390 | Loan Disb | 9,250,255.00 |
Dec 15, 2016 | IDA-53390 | Int Charges | 10,093.62 |
Dec 15, 2016 | IDA-53390 | Int Charges | 10,093.62 |
Dec 15, 2016 | IDA-53390 | Int Charges | 287,279.78 |
Dec 15, 2016 | IDA-53390 | Int Charges | 287,279.78 |
Jun 16, 2016 | IDA-53390 | Loan Disb | 8,270,791.00 |
May 11, 2017 | IDA-53390 | Loan Disb | 2,831,448.00 |
Jan 14, 2015 | IDA-53390 | Loan Disb | 4,875,946.00 |
Jul 21, 2014 | IDA-53390 | Loan Disb | 2,165,335.00 |
Dec 15, 2014 | IDA-53390 | Int Charges | 45,271.76 |
Dec 15, 2014 | IDA-53390 | Int Charges | 45,271.76 |
Jul 3, 2014 | IDA-53390 | Loan Disb | 12,263,300.00 |
Jun 15, 2015 | IDA-53390 | Int Charges | 710.96 |
Jun 15, 2015 | IDA-53390 | Int Charges | 710.96 |
Jun 15, 2015 | IDA-53390 | Int Charges | 62,068.67 |
Jun 15, 2015 | IDA-53390 | Int Charges | 62,068.67 |
Jan 14, 2014 | IDA-53390 | Loan Commitment | 410,000,000.00 |
Jun 15, 2024 | IDA-53390 | Int Charges | 29,339.14 |
Jun 15, 2024 | IDA-53390 | Int Charges | 29,339.14 |
Jun 15, 2024 | IDA-53390 | Loan Repay | 3,398,131.00 |
Jun 15, 2024 | IDA-53390 | Int Charges | 1,269,838.60 |
Jun 15, 2024 | IDA-53390 | Int Charges | 1,269,838.60 |
Dec 15, 2023 | IDA-53390 | Int Charges | 20,060.77 |
Dec 15, 2023 | IDA-53390 | Int Charges | 1,246,791.50 |
Dec 15, 2023 | IDA-53390 | Int Charges | 1,246,791.50 |
Dec 15, 2023 | IDA-53390 | Int Charges | 20,060.77 |
Jun 15, 2023 | IDA-53390 | Int Charges | 54,376.34 |
Jun 15, 2023 | IDA-53390 | Int Charges | 54,376.34 |
Jun 15, 2023 | IDA-53390 | Int Charges | 1,286,991.50 |
Jun 15, 2023 | IDA-53390 | Int Charges | 1,286,991.50 |
Dec 15, 2022 | IDA-53390 | Int Charges | 1,239,968.60 |
Dec 15, 2022 | IDA-53390 | Int Charges | 1,239,968.60 |
Dec 15, 2022 | IDA-53390 | Int Charges | 34,432.63 |
Dec 15, 2022 | IDA-53390 | Int Charges | 34,432.63 |
Dec 4, 2022 | IDA-53390 | Loan Disb | -9,992,706.00 |
Dec 4, 2022 | IDA-53390 | Loan Cancel | 11,557,832.00 |
Jan 13, 2022 | IDA-53390 | Loan Disb | 6,315,659.00 |
Oct 10, 2022 | IDA-53390 | Loan Disb | -1,034,322.60 |
Dec 15, 2021 | IDA-53390 | Int Charges | 11,030.28 |
Dec 15, 2021 | IDA-53390 | Int Charges | 11,030.28 |
Dec 15, 2021 | IDA-53390 | Int Charges | 1,370,742.80 |
Dec 15, 2021 | IDA-53390 | Int Charges | 1,370,742.80 |
Jun 15, 2022 | IDA-53390 | Int Charges | 1,310,966.20 |
Jun 15, 2022 | IDA-53390 | Int Charges | 1,310,966.20 |
Jun 15, 2022 | IDA-53390 | Int Charges | 15,177.79 |
Jun 15, 2022 | IDA-53390 | Int Charges | 15,177.79 |
Jun 10, 2021 | IDA-53390 | Loan Disb | 13,970,519.00 |
Jun 16, 2015 | IDA-53390 | Loan Disb | 18,622,458.00 |
Dec 15, 2015 | IDA-53390 | Int Charges | 1,443.05 |
Dec 15, 2015 | IDA-53390 | Int Charges | 1,443.05 |
Dec 15, 2015 | IDA-53390 | Int Charges | 149,180.77 |
Dec 15, 2015 | IDA-53390 | Int Charges | 149,180.77 |
Oct 7, 2015 | IDA-53390 | Loan Disb | 9,798,201.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2022-12-14 |
Counterpart Funding | Satisfactory | 2022-12-14 |
Monitoring and Evaluation | Satisfactory | 2022-12-14 |
Overall Implementation Progress (IP) | Satisfactory | 2022-12-14 |
Project Management | Satisfactory | 2022-12-14 |
Procurement | Satisfactory | 2022-12-14 |
Financial Management | Satisfactory | 2022-12-14 |
Overall Safeguards Rating | Satisfactory | 2022-12-14 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-12-2023 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-11-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries satisfied with basic services under the project | Value | 0.00 | 94.30 | 0.00 |
Date | May 25, 2017 | May 31, 2022 | ||
Comment |
Female beneficiaries satisfied with basic services under the project | Value | 0.00 | 89.00 | 0.00 |
Date | May 25, 2017 | May 31, 2022 | ||
Comment |
People provided with improved urban living conditions | Value | 0.00 | 7010000.00 | 3450000.00 |
Date | October 31, 2013 | May 31, 2022 | March 9, 2022 | |
Comment |
Number of people benefitting from local infrastructure that are rehabilitated or reconstructed as a result of a crisis or calamity. | Value | 0.00 | 0.00 | 0.00 |
Date | March 9, 2020 | May 31, 2022 | ||
Comment |
People provided with improved urban living conditions - Female (RMS requirement) | Value | 0.00 | 1420000.00 | 0.00 |
Date | ||||
Comment |
Direct project beneficiaries | Value | 0.00 | 7010000.00 | 3430000.00 |
Date | October 31, 2013 | May 31, 2022 | June 30, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 49.30 | 0.00 |
Date | October 31, 2013 | February 20, 2018 | ||
Comment |
Loan repayment ratio from ULBs borrowing from BMDF | Value | 40.00 | 87.30 | 0.00 |
Date | May 25, 2017 | May 31, 2022 | ||
Comment |
Number of ULBs achieving an aggregate rating of at least 60 percent in the project's performance assessment on municipal planning, social accountability, public financial management and public revenue | Value | 0.00 | 26.00 | 0.00 |
Date | October 31, 2013 | August 30, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of roads constructed/ rehabilitated under the project | Value | 0.00 | 989.82 | 690.00 |
Date | May 25, 2017 | May 31, 2022 | March 10, 2020 | |
Comment |
Number of ULBs with revenue enhancement action plans or REAP | Value | 0.00 | 78.00 | 0.00 |
Date | May 25, 2017 | May 31, 2022 | ||
Comment |
Number of ULB staff including community people trained by LGED and BMDF | Value | 0.00 | 33.48 | 16.40 |
Date | October 31, 2013 | May 31, 2022 | March 9, 2020 | |
Comment |
Other local facilities constructed/ rehabilitated under the project | Value | 0.00 | 18.00 | 15.00 |
Date | May 25, 2017 | May 31, 2022 | March 9, 2020 | |
Comment |
Number of Grievance and Redress Cell (GRC) formed and functional | Value | 0.00 | 28.00 | 26.00 |
Date | May 25, 2017 | January 25, 2021 | June 29, 2018 | |
Comment |
Number of revenue-generating facilities constructed/ rehabilitated under the project | Value | 0.00 | 73.00 | 60.00 |
Date | May 25, 2017 | May 31, 2022 | March 9, 2020 | |
Comment |
Length of drainage constructed/ rehabilitated under the project | Value | 0.00 | 437.10 | 300.00 |
Date | May 25, 2017 | May 31, 2022 | June 30, 2020 | |
Comment |
Number of ULBs with approved O&M plans | Value | 0.00 | 28.00 | 28.00 |
Date | October 31, 2013 | May 31, 2022 | March 9, 2020 | |
Comment |
BMDF Incremental operating cost covered by own source revenue | Value | 25.00 | 100.00 | 25.00 |
Date | October 31, 2013 | May 31, 2022 | ||
Comment |
Number of ULBs with approved capital investment plans | Value | 0.00 | 28.00 | 28.00 |
Date | May 25, 2017 | May 31, 2022 | March 9, 2022 | |
Comment |