Financier | Commitments |
---|---|
IDA Credit | 100.00 |
P133777
Closed
Gabi Afram
Ministry of Finance
June 29, 2015
(as of board presentation)
June 29, 2015
September 30, 2015
US$ 100.00 million
N/A
2015
US$ 100.00 million
N/A
May 27, 2021
December 31, 2015
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2016 | IDA-57010 | Int Charges | 361,740.60 |
Dec 15, 2016 | IDA-57010 | Int Charges | 361,740.60 |
Dec 15, 2016 | IDA-57010 | Int Charges | 182.53 |
Dec 15, 2016 | IDA-57010 | Int Charges | 182.53 |
Jun 15, 2016 | IDA-57010 | Int Charges | 54,842.19 |
Jun 15, 2016 | IDA-57010 | Int Charges | 54,842.19 |
Jun 15, 2016 | IDA-57010 | Int Charges | 379,485.12 |
Jun 15, 2016 | IDA-57010 | Int Charges | 379,485.12 |
Nov 19, 2015 | IDA-57010 | Loan Disb | 99,422,640.00 |
Jun 15, 2024 | IDA-57010 | Int Charges | 41,807.54 |
Jun 15, 2024 | IDA-57010 | Int Charges | 41,807.54 |
Jun 15, 2024 | IDA-57010 | Loan Repay | 1,482,322.50 |
Jun 29, 2015 | IDA-57010 | Loan Commitment | 100,000,000.00 |
Jun 15, 2024 | IDA-57010 | Int Charges | 326,206.78 |
Jun 15, 2024 | IDA-57010 | Int Charges | 326,206.78 |
Jun 15, 2023 | IDA-57010 | Int Charges | 75,520.37 |
Jun 15, 2023 | IDA-57010 | Int Charges | 75,520.37 |
Jun 15, 2023 | IDA-57010 | Loan Repay | 1,501,458.80 |
Jun 15, 2023 | IDA-57010 | Int Charges | 343,458.66 |
Jun 15, 2023 | IDA-57010 | Int Charges | 343,458.66 |
Dec 15, 2023 | IDA-57010 | Int Charges | 296,844.75 |
Dec 15, 2023 | IDA-57010 | Int Charges | 296,844.75 |
Dec 15, 2023 | IDA-57010 | Loan Repay | 28,721.02 |
Dec 15, 2023 | IDA-57010 | Loan Repay | 1,479,667.80 |
Dec 15, 2021 | IDA-57010 | Int Charges | 377,065.80 |
Dec 15, 2021 | IDA-57010 | Int Charges | 377,065.80 |
Dec 15, 2022 | IDA-57010 | Loan Repay | 48,093.22 |
Dec 15, 2022 | IDA-57010 | Loan Repay | 1,449,068.00 |
Dec 15, 2022 | IDA-57010 | Int Charges | 272,785.78 |
Dec 15, 2022 | IDA-57010 | Int Charges | 272,785.78 |
Dec 15, 2021 | IDA-57010 | Int Charges | 2,820.79 |
Dec 15, 2021 | IDA-57010 | Int Charges | 2,820.79 |
Dec 15, 2021 | IDA-57010 | Loan Repay | 1,571,107.50 |
Jun 15, 2022 | IDA-57010 | Loan Repay | 1,476,867.20 |
Jun 15, 2022 | IDA-57010 | Int Charges | 353,972.75 |
Jun 15, 2022 | IDA-57010 | Int Charges | 353,972.75 |
Jun 15, 2022 | IDA-57010 | Loan Repay | 21,430.28 |
Jun 15, 2021 | IDA-57010 | Int Charges | 7,216.79 |
Jun 15, 2021 | IDA-57010 | Int Charges | 7,216.79 |
Jun 15, 2021 | IDA-57010 | Int Charges | 385,669.00 |
Jun 15, 2021 | IDA-57010 | Int Charges | 385,669.00 |
Dec 15, 2020 | IDA-57010 | Int Charges | 381,043.78 |
Dec 15, 2020 | IDA-57010 | Int Charges | 381,043.78 |
Dec 15, 2020 | IDA-57010 | Int Charges | 3,620.62 |
Dec 15, 2020 | IDA-57010 | Int Charges | 3,620.62 |
Jun 15, 2020 | IDA-57010 | Int Charges | 368,951.50 |
Jun 15, 2020 | IDA-57010 | Int Charges | 3,594.85 |
Jun 15, 2020 | IDA-57010 | Int Charges | 3,594.85 |
Jun 15, 2020 | IDA-57010 | Int Charges | 368,951.50 |
Dec 15, 2019 | IDA-57010 | Int Charges | 1,938.60 |
Dec 15, 2019 | IDA-57010 | Int Charges | 1,938.60 |
Dec 15, 2019 | IDA-57010 | Int Charges | 368,158.50 |
Dec 15, 2019 | IDA-57010 | Int Charges | 368,158.50 |
Jun 15, 2019 | IDA-57010 | Int Charges | 5,092.20 |
Jun 15, 2019 | IDA-57010 | Int Charges | 5,092.20 |
Jun 15, 2019 | IDA-57010 | Int Charges | 368,406.90 |
Jun 15, 2019 | IDA-57010 | Int Charges | 368,406.90 |
Dec 15, 2018 | IDA-57010 | Int Charges | 11,709.90 |
Dec 15, 2018 | IDA-57010 | Int Charges | 11,709.90 |
Dec 15, 2018 | IDA-57010 | Int Charges | 360,617.40 |
Dec 15, 2018 | IDA-57010 | Int Charges | 360,617.40 |
Jun 15, 2018 | IDA-57010 | Int Charges | 194.98 |
Jun 15, 2018 | IDA-57010 | Int Charges | 194.98 |
Jun 15, 2018 | IDA-57010 | Int Charges | 380,788.53 |
Jun 15, 2018 | IDA-57010 | Int Charges | 380,788.53 |
Jun 15, 2017 | IDA-57010 | Int Charges | 10,497.50 |
Dec 15, 2017 | IDA-57010 | Int Charges | 381,796.20 |
Dec 15, 2017 | IDA-57010 | Int Charges | 381,796.20 |
Dec 15, 2017 | IDA-57010 | Int Charges | 6,521.63 |
Dec 15, 2017 | IDA-57010 | Int Charges | 6,521.63 |
Jun 15, 2017 | IDA-57010 | Int Charges | 356,321.80 |
Jun 15, 2017 | IDA-57010 | Int Charges | 356,321.80 |
Jun 15, 2017 | IDA-57010 | Int Charges | 10,497.50 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2015-11-30 |
Program Management | Satisfactory | 2015-11-30 |
Monitoring and Evaluation | Satisfactory | 2015-11-30 |
Overall Implementation Progress (IP) | Satisfactory | 2015-11-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2020 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 02-02-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | N/a |