Financier | Commitments |
---|---|
Borrower/Recipient | 2.00 |
IDA Grant | 100.00 |
P133811
Closed
Lire Ersado
N/A
Yemen, Republic of
February 14, 2013
(as of board presentation)
February 14, 2013
May 8, 2013
US$ 102.00 million
N/A
2013
US$ 100.00 million
C
December 2, 2013
June 30, 2014
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 2.00 |
IDA Grant | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 102.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 6, 2013 | IDA-H8270 | Loan Disb | 1,856,863.60 |
Jul 1, 2014 | IDA-H8270 | Loan Disb | 11,324,265.00 |
Nov 10, 2014 | IDA-H8270 | Loan Disb | 5,211.97 |
Oct 27, 2014 | IDA-H8270 | Loan Disb | 251,075.20 |
Oct 22, 2014 | IDA-H8270 | Loan Disb | 1,695,328.40 |
Oct 28, 2014 | IDA-H8270 | Loan Disb | 40,020.48 |
Feb 17, 2015 | IDA-H8270 | Loan Disb | -94,759.00 |
Jul 12, 2013 | IDA-H8270 | Loan Disb | 4,649,541.00 |
Feb 14, 2013 | IDA-H8270 | Loan Commitment | 100,000,000.00 |
Feb 17, 2015 | IDA-H8270 | Loan Cancel | 153,289.00 |
Jun 30, 2014 | IDA-H8270 | Loan Disb | 137,999.98 |
Dec 30, 2013 | IDA-H8270 | Loan Disb | 46,835,736.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2014-07-03 |
Project Management | Satisfactory | 2014-07-03 |
Financial Management | Satisfactory | 2014-07-03 |
Monitoring and Evaluation | Satisfactory | 2014-07-03 |
Overall Implementation Progress (IP) | Satisfactory | 2014-07-03 |
Procurement | Satisfactory | 2014-07-03 |
Counterpart Funding | Satisfactory | 2014-07-03 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2014 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 04-20-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of households receiving cash transfers through the project | Value | 0.00 | 393743.00 | 400000.00 |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment |
Number of direct project beneficiaries (Number in millions) of which female (percentage) | Value | 0.00 | 2.35 | 2.40 |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment | 2.35 million of which 37.4% female. | 2.4 million of which 50% female. |
Beneficiaries of Safety Nets programs (number) | Value | 0.00 | 393743.00 | 400000.00 |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment |
Beneficiaries of Safety Nets programs - Female (number) | Value | 0.00 | 204746.00 | 200000.00 |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment | 52% of beneficiaries were female. |
Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) | Value | 0.00 | 393743.00 | 400000.00 |
Date | January 31, 2013 | March 31, 2014 | June 30, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Amount of grant transferred to beneficiaries ($US million) | Value | 0.00 | 85.00 | 99.80 |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment | Last disbursement under process. Expected to reach million 99.8 (100%) |
Timely submission of financial statements for reimbursement of cash transfers | Value | N/A | All financial statements for reimbursement of cash | Timely submission of quarterly financial statement |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment | audited IFR overdue | External auditor conducted field visits to about 2,000 randomly selected cases and identified all target beneficiaries except foronly 2 %. |
Timely submission of Monitoring Reports | Value | N/A | Regular progress reports received from PST. | Timely submission of quarterly monitoring reports |
Date | January 31, 2013 | June 30, 2014 | June 30, 2014 | |
Comment |