NP Rural Water Supply and Sanitation Improvement Project

Abstract*

The development objectives of the Rural Water Supply and Sanitation Improvement Project for Nepal are to: (i) increase sustainable access to improved water services and promote improved sanitation and hygiene practices in rural areas; and (ii) develop and implement a long-term support mechanism to promote the sustainability of water supply schemes in selected districts. The project comprises of four components. The first component, access to improved...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objectives of the project are to: (i) Increase sustainable access to improved water services and promote improved sanitation and hygiene practices in rural areas; and (ii) Develop and implement a long-term support mechanism to promote the sustainability of water supply schemes in selected districts.

Key Details

Project Details

  • P143036

  • Closed

  • Feriha Mugisha

  • Government of Nepal

  • Nepal

  • July 16, 2013

  • (as of board presentation)

    May 29, 2014

  • November 10, 2014

  • US$ 90.00 million

  • Ministry of Water Supply and Sanitation,Rural Water Supply and Sanitation Fund Development Board

  • South Asia

  • 2014

  • US$ 72.00 million

  • B

  • Not Applicable

  • July 15, 2021

  • Yes

  • BANK APPROVED

  • September 2, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA recommitted as a Credit 72.00
Local Communities 7.50
Borrower/Recipient 10.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 72.00
IBRD + IDA Commitment 72.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 90.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2016 IDA-54460 Int Charges 19,173.23
May 15, 2016 IDA-54460 Int Charges 19,173.23
Aug 4, 2016 IDA-54460 Loan Disb 188,344.97
Aug 4, 2016 IDA-H9450 Loan Disb 173,181.06
Nov 15, 2016 IDA-54460 Int Charges 23,589.91
Nov 15, 2016 IDA-54460 Int Charges 23,589.91
Jun 17, 2016 IDA-H9450 Loan Disb 200,000.00
Jun 17, 2016 IDA-54460 Loan Disb 300,000.00
May 28, 2015 IDA-54460 Loan Disb 3,818,890.00
Nov 15, 2015 IDA-54460 Int Charges 17,440.68
Nov 15, 2015 IDA-54460 Int Charges 17,440.68
Jun 23, 2015 IDA-H9450 Loan Disb 403,539.40
Jun 3, 2015 IDA-54460 Loan Disb 1,219,164.00
May 15, 2020 IDA-54460 Loan Disb 299,999.44
Jul 2, 2020 IDA-H9450 Loan Disb -968,319.30
Aug 4, 2020 IDA-H9450 Loan Disb 124,391.15
Dec 18, 2020 IDA-54460 Loan Disb 289,637.12
Dec 18, 2020 IDA-H9450 Loan Disb 198,639.05
May 15, 2019 IDA-54460 Int Charges 1,406.65
May 15, 2019 IDA-54460 Int Charges 1,406.65
May 15, 2019 IDA-54460 Int Charges 104,008.76
May 15, 2019 IDA-54460 Int Charges 104,008.76
Apr 15, 2019 IDA-54460 Loan Disb 5,559,572.50
Apr 15, 2019 IDA-H9450 Loan Disb 2,839,869.80
Nov 15, 2019 IDA-54460 Int Charges 2,679.69
Nov 15, 2021 IDA-54460 Int Charges 144,944.02
May 15, 2022 IDA-54460 Int Charges 131,741.16
May 15, 2022 IDA-54460 Int Charges 131,741.16
May 15, 2022 IDA-54460 Int Charges 2,190.01
May 15, 2022 IDA-54460 Int Charges 2,190.01
Feb 18, 2020 IDA-H9450 Loan Disb 3,482,040.00
Feb 18, 2020 IDA-54460 Loan Disb 5,469,987.00
Feb 6, 2020 IDA-54460 Loan Disb 153,571.94
Feb 6, 2020 IDA-H9450 Loan Disb 68,996.12
Mar 17, 2020 IDA-54460 Loan Cancel 4,645,441.50
Mar 17, 2020 IDA-H9450 Loan Cancel 355,910.60
Jun 16, 2020 IDA-54460 Loan Disb 299,057.60
Jun 16, 2020 IDA-H9450 Loan Disb 16,205.96
May 15, 2020 IDA-54460 Int Charges 133,474.39
May 15, 2020 IDA-54460 Int Charges 133,474.39
May 15, 2020 IDA-54460 Int Charges 122.79
May 15, 2020 IDA-54460 Int Charges 122.79
May 15, 2020 IDA-H9450 Loan Disb 140,736.98
Nov 15, 2019 IDA-54460 Int Charges 2,679.69
Nov 15, 2019 IDA-54460 Int Charges 124,548.32
Nov 15, 2019 IDA-54460 Int Charges 124,548.32
Jul 27, 2018 IDA-54460 Loan Disb 125,531.42
Sep 21, 2018 IDA-54460 Loan Disb 144,460.77
Sep 21, 2018 IDA-H9450 Loan Disb 160,837.40
Aug 6, 2018 IDA-54460 Loan Disb 209,463.44
Jul 24, 2018 IDA-H9450 Loan Disb 59,664.22
May 15, 2018 IDA-54460 Int Charges 11,586.08
May 15, 2018 IDA-54460 Int Charges 11,586.08
May 15, 2018 IDA-54460 Int Charges 101,760.10
May 15, 2018 IDA-54460 Int Charges 101,760.10
Nov 15, 2018 IDA-54460 Int Charges 1,845.12
Nov 15, 2018 IDA-54460 Int Charges 1,845.12
Aug 6, 2018 IDA-H9450 Loan Disb 94,102.60
Aug 28, 2018 IDA-54460 Loan Disb 294,521.84
Aug 28, 2018 IDA-H9450 Loan Disb 132,319.39
May 7, 2018 IDA-H9450 Loan Disb 715,042.40
May 7, 2018 IDA-54460 Loan Disb 852,042.00
May 15, 2023 IDA-54460 Int Charges 133,311.77
May 15, 2023 IDA-54460 Int Charges 133,311.77
May 15, 2023 IDA-54460 Int Charges 2,155.94
May 15, 2023 IDA-54460 Int Charges 2,155.94
Nov 15, 2023 IDA-54460 Int Charges 1,148.00
Nov 15, 2023 IDA-54460 Int Charges 1,148.00
Nov 15, 2023 IDA-54460 Int Charges 132,069.56
Nov 15, 2023 IDA-54460 Int Charges 132,069.56
Jul 18, 2022 IDA-54460 Loan Disb -181,609.00
Dec 10, 2021 IDA-H9450 Loan Disb 189,640.12
Dec 8, 2021 IDA-54460 Loan Disb 92,941.68
Jul 18, 2022 IDA-54460 Loan Disb 100.00
Jul 18, 2022 IDA-54460 Loan Disb -74.85
Jul 18, 2022 IDA-54460 Loan Disb 74.85
Jul 18, 2022 IDA-54460 Loan Disb -100.00
Dec 10, 2021 IDA-H9450 Loan Disb -200.00
Dec 10, 2021 IDA-H9450 Loan Disb 200.00
Nov 16, 2021 IDA-54460 Loan Disb -75,095.17
Nov 16, 2021 IDA-H9450 Loan Disb -6,987.03
Jul 18, 2022 IDA-54460 Loan Cancel 252,099.90
Nov 15, 2022 IDA-54460 Int Charges 125,038.98
Nov 15, 2022 IDA-54460 Int Charges 125,038.98
Nov 15, 2022 IDA-54460 Int Charges 4,887.17
Nov 15, 2022 IDA-54460 Int Charges 4,887.17
Dec 10, 2021 IDA-H9450 Loan Cancel 1,152,046.10
Nov 15, 2020 IDA-54460 Int Charges 150,624.83
Nov 15, 2020 IDA-54460 Int Charges 150,624.83
May 15, 2021 IDA-54460 Int Charges 346.81
May 15, 2021 IDA-54460 Int Charges 346.81
May 15, 2021 IDA-54460 Int Charges 154,818.22
May 15, 2021 IDA-54460 Int Charges 154,818.22
Nov 15, 2020 IDA-54460 Int Charges 1,844.66
Nov 15, 2020 IDA-54460 Int Charges 1,844.66
Jul 13, 2021 IDA-54460 Loan Disb -2,999,900.00
Jul 14, 2021 IDA-54460 Loan Cancel 2,995,914.20
Oct 19, 2021 IDA-H9450 Loan Disb -680,738.56
Nov 15, 2021 IDA-54460 Int Charges 1,084.06
Nov 15, 2021 IDA-54460 Int Charges 1,084.06
Nov 15, 2021 IDA-54460 Int Charges 144,944.02
Nov 15, 2018 IDA-54460 Int Charges 101,229.61
Nov 15, 2018 IDA-54460 Int Charges 101,229.61
Jun 29, 2016 IDA-54460 Loan Disb 729,745.10
Nov 15, 2016 IDA-54460 Int Charges 231.45
Nov 15, 2016 IDA-54460 Int Charges 231.45
May 15, 2017 IDA-54460 Int Charges 38,831.12
May 15, 2017 IDA-54460 Int Charges 38,831.12
May 15, 2017 IDA-54460 Int Charges 642.21
May 15, 2017 IDA-54460 Int Charges 642.21
Apr 5, 2017 IDA-H9450 Loan Disb 2,470,845.20
Apr 5, 2017 IDA-54460 Loan Disb 5,178,904.50
Sep 19, 2017 IDA-54460 Loan Disb 10,339,564.00
Nov 15, 2017 IDA-54460 Int Charges 62,086.28
Nov 15, 2017 IDA-54460 Int Charges 62,086.28
Nov 15, 2017 IDA-54460 Int Charges 5,117.92
Nov 15, 2017 IDA-54460 Int Charges 5,117.92
Sep 13, 2017 IDA-H9450 Loan Disb 4,350,290.00
Feb 13, 2018 IDA-54460 Loan Disb 96,233.19
Feb 13, 2018 IDA-H9450 Loan Disb 43,235.22
Jan 25, 2018 IDA-54460 Loan Disb 128,640.94
Jan 25, 2018 IDA-H9450 Loan Disb 57,505.04
May 28, 2015 IDA-H9450 Loan Disb 1,715,733.20
Sep 22, 2015 IDA-H9450 Loan Disb 54,175.04
Sep 22, 2015 IDA-54460 Loan Disb 120,583.15
Nov 15, 2016 IDA-H9450 Loan Disb 1,813,416.50
Nov 15, 2016 IDA-54460 Loan Disb 3,738,622.50
Jun 28, 2016 IDA-54460 Loan Disb 479,257.06
Jun 28, 2016 IDA-H9450 Loan Disb 203,502.00
Jun 30, 2016 IDA-H9450 Loan Disb 210,588.69
Nov 23, 2016 IDA-H9450 Loan Disb 93,262.21
Nov 23, 2016 IDA-54460 Loan Disb 194,699.12
May 15, 2016 IDA-54460 Int Charges 199.19
May 15, 2016 IDA-54460 Int Charges 199.19
May 15, 2024 IDA-54460 Int Charges 132,536.88
May 15, 2024 IDA-54460 Int Charges 132,536.88
May 15, 2024 IDA-54460 Int Charges 769.02
May 15, 2024 IDA-54460 Int Charges 769.02
May 29, 2014 IDA-54460 Loan Commitment 50,000,000.00
May 29, 2014 IDA-H9450 Loan Commitment 22,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2021-07-13
Progress towards achievement of PDO Moderately Satisfactory 2021-07-13
Procurement Moderately Satisfactory 2021-07-13
Financial Management Moderately Satisfactory 2021-07-13
Counterpart Funding Satisfactory 2021-07-13
Monitoring and Evaluation Moderately Satisfactory 2021-07-13
Overall Implementation Progress (IP) Moderately Satisfactory 2021-07-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-14-2022
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.00794994.00720000.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Number of schemes visited by the backstopping facility at the District level; of which (percentage of schemes non-functioning).Value0.00965.00830.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Number of VDCs declared ODF by the Districts.Value0.00130.00130.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved community water points constructed or rehabilitated under the projectValue0.0010782.008920.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • People provided with improved water supply through rehabilitation of schemes in earthquake affects districtsValue0.00345776.00321000.00
    DateJuly 31, 2015July 15, 2021July 15, 2021
    Comment
  • Number of water supply schemes completed and in operation; of which (Jagaran Committee established).Value0.00881.00854.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Municipal Water and Sanitation Units (MWASH Unit) formally established under the Local Government with defined functionsValue0.006.006.00
    DateJune 1, 2018July 15, 2021June 30, 2020
    Comment
  • Households provided with improved and rehabilitated latrines in the earthquake-affected districtsValue0.000.0022000.00
    DateJuly 31, 2015July 15, 2021June 15, 2021
    Comment
  • Number of WSUCs formed; (those with at least 3 women members).Value0.00912.00854.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Local Government Level M&E system established and 25% of detected functionality issues addressedValue0.006.006.00
    DateJune 1, 2018July 15, 2021June 30, 2020
    Comment
  • Improved public latrines constructed under the project (number) in schools and health posts.Value0.00184.00180.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Number of community, municipal, private sector WASH stakeholders trained by the projectValue0.002424.002295.00
    DateJune 1, 2018July 15, 2021June 30, 2020
    Comment
  • People trained to improve hygiene behavior/sanitation practices under the projValue0.002859000.00813.00
    DateJuly 16, 2014July 15, 2021
    Comment
  • People trained to improve hygiene behavior/sanitation practices - femaleValue0.001400910.001200000.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • People trained on improved hygiene behavior, and sanitation practices - StudentsValue0.001715400.001000000.00
    DateJuly 16, 2014July 15, 2021July 15, 2021
    Comment
  • Number of household yard connections (new or rehabilitated under the project)Value0.0051381.000.00
    DateJune 1, 2018July 15, 2021
    Comment
  • Number of newly constructed schemes provided with post-construction support by the project.Value432.00550.000.00
    DateJune 1, 2018July 15, 2021
    Comment
  • Number of households (HHs) to achieve total sanitation. Target 150,000 HH.Value0.00163398.000.00
    DateJune 1, 2018July 15, 2021
    Comment