| Financier | Commitments |
|---|---|
| Borrower/Recipient | 32.00 |
| IDA Credit | 75.00 |
P143608
Closed
Raj Ganguly , Vinay Kumar Vutukuru
Department of Economic Affairs, Ministry of Finance, Government of India
March 25, 2014
(as of board presentation)
December 19, 2014
April 18, 2016
US$ 107.00 million
Society for Elimination of Rural Poverty (SERP)
2015
US$ 75.00 million
B
Not Applicable
April 15, 2019
Yes
Bank Approved
March 8, 2022
| Financier | Commitments |
|---|---|
| Borrower/Recipient | 32.00 |
| IDA Credit | 75.00 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | N/A |
| IDA Commitment | 75.00 |
| IBRD + IDA Commitment | 75.00 |
| Lending Instrument | |
|---|---|
| Grant Amount | N/A |
| Total Project Cost** | 107.00 |
| Name | Review | Date |
|---|---|---|
| Counterpart Funding | Unsatisfactory | 2018-11-13 |
| Financial Management | Moderately Unsatisfactory | 2018-11-13 |
| Monitoring and Evaluation | Unsatisfactory | 2018-11-13 |
| Overall Implementation Progress (IP) | Unsatisfactory | 2018-11-13 |
| Procurement | Unsatisfactory | 2018-11-13 |
| Progress towards achievement of PDO | Unsatisfactory | 2018-11-13 |
| Project Management | Unsatisfactory | 2018-11-13 |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| % increase in pregnant and lactating women who practice core child nutrition and health care behaviors | Value | 0.00 | 0.00 | 20.00 |
| Date | February 28, 2015 | October 11, 2018 | January 15, 2020 | |
| Comment |
| % increase in use of HD services (ICDS, health and sanitation services) by households | Value | 0.00 | 0.00 | 30.00 |
| Date | December 31, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| 50% incremental income increase of the target households | Value | 0.00 | 0.00 | 50.00 |
| Date | January 31, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| 70% of the producers benefiting are from poorest and SC/ST households | Value | 0.00 | 0.00 | 70.00 |
| Date | December 19, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Where one stop shop has been established, percentage of eligible households with access to at least three entitlement programs or key services | Value | 0.00 | 0.00 | 80.00 |
| Date | December 22, 2014 | October 11, 2018 | January 15, 2020 | |
| Comment |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| % increase in per unit price realization | Value | 0.00 | 0.00 | 20.00 |
| Date | February 1, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| % increase in productivity from improved practices among target farmers | Value | 0.00 | 0.00 | 30.00 |
| Date | February 28, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| % of exception reports generated by the Mother and Child Tracking system acted upon by the field functionaries | Value | 0.00 | 0.00 | 95.00 |
| Date | December 19, 2014 | October 11, 2018 | May 30, 2020 | |
| Comment |
| % of enrolled beneficiaries in targeted gram panchayats who receive payments on time for key entitlements (NREGA, social pensions, Insurance) | Value | 0.00 | 0.00 | 80.00 |
| Date | December 31, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| % of targeted households organized into producer organizations | Value | 0.00 | 33.00 | 70.00 |
| Date | February 28, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| % of villages in the target mandals that have prepared and are implementing Village HD/WASH plans | Value | 0.00 | 0.00 | 0.00 |
| Date | March 16, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Extent of utilization of ICT for measurement and decision support ( index to be developed) | Value | 0.00 | 0.00 | 80.00 |
| Date | December 31, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| No. of targeted panchayats that have operationalized one stop Shop services for safety nets and entitlements | Value | 0.00 | 304.00 | 2800.00 |
| Date | February 1, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Number of VHNSC and PRI members trained | Value | 0.00 | 0.00 | 10000.00 |
| Date | January 1, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Number of good qualitty technical support agencies working with the project | Value | 0.00 | 0.00 | 8.00 |
| Date | December 19, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Number of partners working with the project in providing market access for producers | Value | 0.00 | 0.00 | 8.00 |
| Date | December 19, 2014 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Percent increase in quality and size of consumer basket purchased at a KRuSHE Mart | Value | 0.00 | 0.00 | 40.00 |
| Date | February 28, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |
| Project Implementation procedures and agreed business standards are followed for at least 80% of the project interventions | Value | 0.00 | 0.00 | 80.00 |
| Date | March 16, 2015 | October 11, 2018 | June 30, 2020 | |
| Comment |