Clean and Efficient Energy Project

Abstract*

The development objective of the Clean and Efficient Energy Project for Morocco is to improve the capacity of office national de l'electricite et de l'eau potable (national electricity and water utility company) (ONEE) to supply and dispatch clean electricity and to meet the demand of targeted customers more efficiently in the project area. The project comprises of four components. The first component, support to ONEE's solar photovoltaic (PV) program...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To support clean power generation and to improve operational efficiency of Morocco's national power utility.

Key Details

Project Details

  • P143689

  • Active

  • Lucine Lominy , Noreddine Citroen

  • Office National de l'Electricité et de l'Eau potable (ONEE)

  • Morocco

  • November 12, 2013

  • (as of board presentation)

    April 24, 2015

  • October 28, 2015

  • US$ 158.31 million

  • Office National de l'Electricité et de l'Eau potable (ONEE)

  • Middle East and North Africa

  • 2015

  • US$ 148.95 million

  • B

  • February 14, 2024

  • December 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 125.00
Borrower/Recipient 9.36
Clean Technology Fund 23.95

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 125.00
IDA Commitment N/A
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount 23.95
Total Project Cost** 158.31

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 1, 2023 IBRD-85060 Loan Repay 2,730,234.00
May 1, 2023 IBRD-85060 Int Charges 7,930.57
Nov 1, 2021 IBRD-85060 Int Charges 61,821.92
Nov 1, 2021 IBRD-85060 Int Charges 373,678.94
Nov 1, 2021 IBRD-85060 Loan Repay 1,899,960.00
May 1, 2022 IBRD-85060 Int Charges 60,813.96
May 1, 2022 IBRD-85060 Int Charges 350,773.75
May 1, 2022 IBRD-85060 Loan Repay 1,899,960.00
Nov 1, 2020 IBRD-85060 Int Charges 62,928.28
Nov 1, 2020 IBRD-85060 Int Charges 1,654.73
Nov 1, 2020 IBRD-85060 Int Charges 593,715.70
Nov 1, 2020 IBRD-85060 Loan Repay 1,873,274.60
Dec 21, 2020 IBRD-85060 Loan Disb 1,014,656.10
May 1, 2021 IBRD-85060 Int Charges 376,055.40
May 1, 2021 IBRD-85060 Loan Repay 1,899,960.00
May 1, 2021 IBRD-85060 Int Charges 61,104.50
Nov 1, 2019 IBRD-85060 Int Charges 63,100.66
Nov 1, 2019 IBRD-85060 Int Charges 1,305,963.80
May 21, 2020 IBRD-85060 Int Charges 62,301.42
May 21, 2020 IBRD-85060 Int Charges 1,026,596.10
May 21, 2020 IBRD-85060 Loan Repay 1,873,274.60
Jun 20, 2018 IBRD-85060 Loan Disb 29,819,366.00
May 2, 2018 IBRD-85060 Int Charges 107,793.60
May 2, 2018 IBRD-85060 Int Charges 445,750.50
Nov 1, 2018 IBRD-85060 Int Charges 73,312.77
Nov 1, 2018 IBRD-85060 Int Charges 1,123,748.10
May 2, 2019 IBRD-85060 Int Charges 62,071.85
May 2, 2019 IBRD-85060 Int Charges 1,352,483.50
Apr 24, 2017 IBRD-85060 Loan Disb 31,811,882.00
May 2, 2017 IBRD-85060 Int Charges 23,534.19
May 2, 2017 IBRD-85060 Int Charges 150,354.88
Nov 1, 2017 IBRD-85060 Int Charges 10,660.49
Nov 1, 2017 IBRD-85060 Int Charges 114,448.06
Nov 1, 2017 IBRD-85060 Int Charges 380,929.62
Nov 1, 2017 IBRD-85060 Int Charges 1,525.23
Feb 26, 2018 IBRD-85060 Loan Disb 10,923,678.00
Oct 28, 2015 IBRD-85060 Loan Disb 312,500.00
Oct 28, 2015 IBRD-85060 Fee Charges 312,500.00
Apr 24, 2015 IBRD-85060 Loan Commitment 125,000,000.00
Apr 24, 2015 TF-19266 Loan Commitment 23,950,000.00
Nov 1, 2023 IBRD-85060 Int Charges 39,920.18
Nov 1, 2023 IBRD-85060 Int Charges 2,834,680.80
Nov 1, 2023 IBRD-85060 Int Charges 26,231.04
Nov 1, 2023 IBRD-85060 Loan Repay 2,730,234.00
May 2, 2024 IBRD-85060 Loan Repay 2,730,234.00
May 2, 2024 IBRD-85060 Int Charges 17,309.44
May 2, 2024 IBRD-85060 Int Charges 25,898.77
May 2, 2024 IBRD-85060 Int Charges 2,912,198.00
Sep 21, 2022 IBRD-85060 Loan Disb 28,240,610.00
Nov 1, 2022 IBRD-85060 Int Charges 1,050,638.40
Nov 1, 2022 IBRD-85060 Loan Repay 1,899,960.00
Nov 1, 2022 IBRD-85060 Int Charges 53,891.35
May 1, 2023 IBRD-85060 Int Charges 189,426.75
May 1, 2023 IBRD-85060 Int Charges 25,803.36
May 1, 2023 IBRD-85060 Int Charges 2,413,756.80
Nov 1, 2016 IBRD-85060 Int Charges 154,441.70
Nov 1, 2016 IBRD-85060 Int Charges 16,996.69
May 1, 2016 IBRD-85060 Int Charges 53,082.19
May 1, 2016 IBRD-85060 Int Charges 155,141.47
May 1, 2016 IBRD-85060 Int Charges 1,933.69
May 24, 2016 IBRD-85060 Loan Disb 2,063,557.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2025-01-15
Progress towards achievement of PDO Moderately Satisfactory 2025-01-15
Financial Management Moderately Satisfactory 2025-01-15
Monitoring and Evaluation Moderately Satisfactory 2025-01-15
Procurement Satisfactory 2025-01-15
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Clean Energy GenerationValue0.00132.00200.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Displaced Fossil Fuel EnergyValue0.000.00100.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Energy billed as a result of commercial losses reductionValue0.000.0050.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Direct project beneficiariesValue0.00271957.00412056.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Female beneficiariesValue0.000.0050.00
    DateApril 23, 2015November 30, 2020
    Comment
  • Green-House Gas (GHG) emissions avoidedValue0.0051492.0078018.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Citizen Engagement - Consultation ProcessValue0.002.003.00
    DateNovember 2, 2015February 8, 2024October 31, 2024
    Comment
  • ONEE Unbundling Study CompletedValueNoNoYes
    DateNovember 30, 2015February 8, 2024October 31, 2024
    Comment
  • Number of Solar PV Plants commissionedValue0.003.003.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Upgraded Dispatch Center operationalValueNoYesYes
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Number of clients equipped with Smart MetersValue0.0045800.0063600.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Energy demand forecast model acquiredValueNoNoYes
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.00100.00100.00
    DateApril 23, 2015February 8, 2024October 31, 2024
    Comment