Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.77 |
Borrower/Recipient | 23.20 |
P143921
Closed
Natasa Vetma , Stjepan Gabric
Ministry of Finance
Western Balkans
November 7, 2013
(as of board presentation)
June 11, 2014
December 5, 2014
US$ 29.97 million
Ministry of Foreign Trade and Economic Relations,Environmental Protection and Energy Efficiency Fund
2014
US$ 6.77 million
B
October 12, 2023
February 15, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.77 |
Borrower/Recipient | 23.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.77 |
Total Project Cost** | 29.97 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Unsatisfactory | 2019-02-15 |
Procurement | Moderately Unsatisfactory | 2019-02-15 |
Counterpart Funding | Satisfactory | 2019-02-15 |
Summary Global Objective Rating | Moderately Unsatisfactory | 2019-02-15 |
Financial Management | Moderately Satisfactory | 2019-02-15 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2019-02-15 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2019-02-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-15-2019 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-06-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Nutrient load reduction (Nitrogen(N)) achieved under the project | Value | 0.00 | 20.00 | 70.00 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Investment Proposals prepared for EU funding | Value | 0.00 | 10.00 | 6.00 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Number of sea water quality measurements reported annually by the Croatian Ministry of Environment and Natural Resources from the new monitoring system | Value | Manual reporting | 43,267 | 3,000 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 15500.00 | 140500.00 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | September 19, 2013 | June 20, 2017 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Analysis of the policy, legal and/or institutional reforms conducted and draft report completed per TOR | Value | No | Yes | Yes |
Date | September 9, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Leachate management systems completed | Value | 0.00 | 1.00 | 2.00 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Approval of the Strategic Environmental Assessment for leachate management plan | Value | No | Yes | Yes |
Date | September 9, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |
Feasibility studies for the rehabilitation of leachate and wastewater treatment plants completed | Value | 0.00 | 4.00 | 4.00 |
Date | September 19, 2013 | October 26, 2018 | September 19, 2016 | |
Comment |
Monitoring stations sampled | Value | 0.00 | 105.00 | 60.00 |
Date | September 19, 2013 | July 15, 2019 | September 19, 2016 | |
Comment |