P144454
Closed
Elena Roseo , Juan Baron
Islamic Republic of Pakistan
February 7, 2014
(as of board presentation)
March 18, 2015
March 25, 2015
US$ 34.00 million
Secondary Education Department of Balochistan
2015
US$ 34.00 million
B
September 6, 2022
August 31, 2021
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Education for All Supervising Entity | 34.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 34.00 |
Total Project Cost** | 34.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2021-08-31 |
Project Management | Satisfactory | 2021-08-31 |
Monitoring and Evaluation | Satisfactory | 2021-08-31 |
Overall Implementation Progress (IP) | Satisfactory | 2021-08-31 |
Procurement | Satisfactory | 2021-08-31 |
Financial Management | Moderately Satisfactory | 2021-08-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-18-2022 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Girls enrolled in grades 1-5 of project supported government schools | Value | 0.00 | 99558.00 | 48366.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Boys enrolled in grades 1-5 of project supported government schools | Value | 0.00 | 30931.00 | 19942.00 |
Date | April 30, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Girls enrolled in grades 6-10 of project supported government schools | Value | 0.00 | 39014.00 | 9127.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Student retention in project schools | Value | 0.00 | 81.70 | 81.00 |
Date | July 7, 2014 | August 24, 2021 | August 31, 2021 | |
Comment |
Regular reports generated and made public annually on selected indicators for schools | Value | 0.00 | 3.00 | 0.00 |
Date | April 1, 2015 | August 24, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of new primary schools established through community support | Value | 0.00 | 708.00 | 725.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of government schools to which furniture (incl blackboard) is provided | Value | 0.00 | 1099.00 | 1145.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of PTSMC members trained in targetted project schools | Value | 0.00 | 5927.00 | 6365.00 |
Date | April 1, 2015 | August 24, 2021 | June 30, 2020 | |
Comment |
Number of schools upgraded from primary to middle level | Value | 0.00 | 195.00 | 195.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of schools to which TLM kits provided | Value | 0.00 | 1113.00 | 1145.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of teaching staff trained in the project specific schools | Value | 0.00 | 2623.00 | 2488.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of schools upgraded from middle to high/higher secondary level | Value | 0.00 | 25.00 | 25.00 |
Date | May 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
Number of government schools in which ECE program established | Value | 0.00 | 828.00 | 845.00 |
Date | April 1, 2015 | August 24, 2021 | August 31, 2021 | |
Comment |
School information collected and reports generated on selected indicators | Value | 0.00 | 11.00 | 0.00 |
Date | April 1, 2015 | August 24, 2021 | ||
Comment |
Number of female students and female teachers provided with transport | Value | 0.00 | 700.00 | 0.00 |
Date | March 1, 2019 | August 31, 2021 | ||
Comment |
Number of classrooms made functional | Value | 0.00 | 1000.00 | 0.00 |
Date | March 1, 2019 | August 31, 2021 | ||
Comment |
Number of classrooms (that have been made functional) provided with furniture | Value | 0.00 | 1000.00 | 0.00 |
Date | March 1, 2019 | August 31, 2021 | ||
Comment |
Improved management and planning of transportation services | Value | No study has been conducted evaluating the plannin | Study and recommendations for the provision of tra | |
Date | March 1, 2019 | August 31, 2021 | ||
Comment |
Gender enrollment gap in project-supported schools | Value | 2.10 | 3.20 | 0.00 |
Date | March 1, 2019 | August 24, 2021 | ||
Comment |