Financier | Commitments |
---|---|
Inter-American Development Bank | 200.00 |
International Bank for Reconstruction and Development | 205.00 |
Borrower/Recipient | 769.88 |
EC: European Investment Bank | 259.28 |
Andean Development Corporation | 250.00 |
P144489
Closed
Alejandro Hoyos Guerrero
Municipality of Quito
May 5, 2013
(as of board presentation)
July 25, 2013
September 25, 2015
US$ 1684.16 million
Empresa Publica Metropolitana de Metro de Quito
2014
US$ 914.28 million
A
June 29, 2024
December 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Inter-American Development Bank | 200.00 |
International Bank for Reconstruction and Development | 205.00 |
Borrower/Recipient | 769.88 |
EC: European Investment Bank | 259.28 |
Andean Development Corporation | 250.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 205.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 205.00 |
Lending Instrument | |
---|---|
Grant Amount | 709.28 |
Total Project Cost** | 1684.16 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2021 | IBRD-88890 | Int Charges | 1,512,417.10 |
Mar 15, 2022 | IBRD-88890 | Int Charges | 7,071.03 |
Mar 15, 2022 | IBRD-88890 | Int Charges | 1,522,411.00 |
Feb 15, 2022 | IBRD-82850 | Int Charges | 917,923.94 |
Dec 22, 2021 | IBRD-82850 | Loan Disb | 1,437,200.00 |
Aug 15, 2022 | IBRD-82850 | Int Charges | 1,954.19 |
Aug 15, 2022 | IBRD-82850 | Int Charges | 1,402,959.80 |
Sep 15, 2019 | IBRD-88890 | Int Charges | 133,215.64 |
Sep 15, 2019 | IBRD-88890 | Int Charges | 2,464,933.50 |
Mar 15, 2020 | IBRD-88890 | Int Charges | 63,485.16 |
Mar 15, 2020 | IBRD-88890 | Int Charges | 2,941,423.80 |
Feb 15, 2020 | IBRD-82850 | Int Charges | 2,805,340.50 |
Aug 18, 2020 | IBRD-82850 | Int Charges | 2,438,193.50 |
Sep 15, 2020 | IBRD-88890 | Int Charges | 1,827,400.10 |
Sep 15, 2020 | IBRD-88890 | Int Charges | 57,441.82 |
Oct 27, 2020 | IBRD-88890 | Loan Disb | 15,000,000.00 |
Mar 15, 2021 | IBRD-88890 | Int Charges | 42,305.40 |
Mar 15, 2021 | IBRD-88890 | Int Charges | 1,457,085.90 |
Feb 15, 2021 | IBRD-82850 | Int Charges | 1,072,630.20 |
Dec 10, 2018 | IBRD-82850 | Loan Disb | 1,640,799.20 |
Feb 15, 2019 | IBRD-82850 | Int Charges | 3,273,076.00 |
Mar 15, 2019 | IBRD-88890 | Int Charges | 33,303.90 |
Mar 15, 2019 | IBRD-88890 | Int Charges | 1,079,375.10 |
Dec 28, 2018 | IBRD-88890 | Loan Disb | 124,296,288.00 |
Dec 27, 2018 | IBRD-88890 | Fee Charges | 575,000.00 |
Oct 1, 2019 | IBRD-88890 | Loan Disb | 60,000,000.00 |
Aug 15, 2019 | IBRD-82850 | Int Charges | 3,490,084.00 |
Feb 15, 2018 | IBRD-82850 | Int Charges | 100,025.28 |
Feb 15, 2018 | IBRD-82850 | Int Charges | 1,962,035.10 |
Aug 15, 2018 | IBRD-82850 | Int Charges | 2,737,162.50 |
Aug 15, 2016 | IBRD-82850 | Int Charges | 823,257.06 |
Feb 15, 2017 | IBRD-82850 | Int Charges | 1,053,475.50 |
Jun 21, 2017 | IBRD-82850 | Loan Disb | 33,066,204.00 |
Aug 15, 2017 | IBRD-82850 | Int Charges | 1,133,631.20 |
Oct 17, 2017 | IBRD-82850 | Loan Disb | 53,208,236.00 |
Nov 20, 2015 | IBRD-82850 | Fee Charges | 512,500.00 |
Feb 15, 2016 | IBRD-82850 | Int Charges | 260,616.88 |
Mar 15, 2024 | IBRD-88890 | Int Charges | 8,020,340.50 |
Mar 15, 2024 | IBRD-88890 | Int Charges | 3,758.68 |
Nov 30, 2015 | IBRD-82850 | Loan Disb | 113,875,560.00 |
Feb 15, 2024 | IBRD-82850 | Int Charges | 59,453.66 |
Feb 15, 2024 | IBRD-82850 | Int Charges | 6,698,477.00 |
Jun 22, 2018 | IBRD-88890 | Loan Commitment | 230,000,000.00 |
Jul 25, 2013 | IBRD-82850 | Loan Commitment | 205,000,000.00 |
Sep 15, 2022 | IBRD-88890 | Int Charges | 7,188.24 |
Sep 15, 2022 | IBRD-88890 | Int Charges | 2,671,119.50 |
Mar 15, 2023 | IBRD-88890 | Int Charges | 7,071.03 |
Mar 15, 2023 | IBRD-88890 | Int Charges | 5,683,668.00 |
Mar 28, 2023 | IBRD-88890 | Loan Disb | 2,299,264.50 |
Mar 28, 2023 | IBRD-82850 | Loan Disb | 1,458,926.50 |
Feb 15, 2023 | IBRD-82850 | Int Charges | 4,686,397.00 |
Feb 15, 2023 | IBRD-82850 | Int Charges | 328,187.72 |
Sep 15, 2023 | IBRD-88890 | Int Charges | 4,495.24 |
Sep 15, 2023 | IBRD-88890 | Int Charges | 7,233,279.50 |
Aug 15, 2023 | IBRD-82850 | Int Charges | 213,099.36 |
Aug 15, 2023 | IBRD-82850 | Int Charges | 5,783,164.00 |
Dec 26, 2023 | IBRD-88890 | Loan Disb | 879,104.50 |
Dec 26, 2023 | IBRD-82850 | Loan Disb | 40,204.26 |
Aug 15, 2024 | IBRD-82850 | Int Charges | 37,981.29 |
Aug 15, 2024 | IBRD-82850 | Int Charges | 6,719,822.50 |
Jun 7, 2021 | IBRD-88890 | Loan Disb | 25,000,000.00 |
Aug 15, 2021 | IBRD-82850 | Int Charges | 943,540.20 |
Sep 15, 2021 | IBRD-88890 | Int Charges | 21,571.80 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Moderately Satisfactory | 2023-12-22 |
Procurement | Moderately Satisfactory | 2023-12-22 |
Project Management | Moderately Satisfactory | 2023-12-22 |
Financial Management | Moderately Satisfactory | 2023-12-22 |
Monitoring and Evaluation | Satisfactory | 2023-12-22 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-22 |
Progress towards achievement of PDO | Moderately Satisfactory | 2023-12-22 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2024 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-05-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Passengers per day in PLMQ | Value | 0.00 | 152610.00 | 295999.00 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
Travel time for public transportation users | Value | 38.50 | 23.10 | 23.10 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
Operating costs of Quito's vehicle fleet | Value | 0.00 | 58.50 | 59.40 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
GHG emissions from transport in DMQ | Value | 0.00 | 64056.00 | 58170.00 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
Adequate passenger capacity provided by PLMQ | Value | No | Yes | Yes |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
Percentage of users satisfied with overall metro service, its security and comfort (differentiated by gender and income) | Value | 0.00 | 97.80 | 65.00 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
Percentage of female users satisfied with overall metro service, its security and comfort | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Percentage of low-income users satisfied with overall metro service, its security and comfort | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Percentage of jobs accessible in 60 minutes of travel time | Value | 45.30 | 50.80 | 50.80 |
Date | June 28, 2013 | May 22, 2024 | June 22, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of physical work progress in civil works other than stations | Value | 0.00 | 99.98 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of rolling stock completed | Value | 0.00 | 100.00 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of metro feeder routes in operation | Value | 0.00 | 0.00 | 15.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of physical work progress in stations and universal access | Value | 0.00 | 100.00 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of bus fleet under unified fare-collection system | Value | 0.00 | 0.00 | 25.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of physical work progress in rail yard | Value | 0.00 | 100.00 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Implementation of a reporting mechanism for cases of violence against women and girls in the PLMQ | Value | No | Yes | Yes |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of progress in installation of power supply, auxiliary, signaling and telecom systems | Value | 0.00 | 99.35 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of technical and professional staff, directly empoyed by the operator of PLMQ, that is female | Value | 0.00 | 41.01 | 20.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of fare-collection system installed | Value | 0.00 | 100.00 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |
Percentage of progress in installation of permanent way | Value | 0.00 | 100.00 | 100.00 |
Date | June 28, 2013 | March 22, 2024 | June 22, 2021 | |
Comment |