Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 2.10 |
IDA Grant | 7.00 |
P144573
Active
Ximing Peng , Ximing Peng
Tuvalu
October 24, 2013
(as of board presentation)
January 26, 2015
May 6, 2015
US$ 9.10 million
Tuvalu Electricity Corporation
2015
US$ 9.10 million
B
Not Applicable
March 31, 2026
Yes
BANK APPROVED
August 28, 2024
Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 2.10 |
IDA Grant | 7.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 7.00 |
IBRD + IDA Commitment | 7.00 |
Lending Instrument | |
---|---|
Grant Amount | 2.10 |
Total Project Cost** | 9.10 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 11, 2020 | IDA-D0290 | Loan Disb | 2,578.24 |
May 4, 2020 | IDA-D0290 | Loan Disb | 369,113.97 |
Jun 12, 2018 | IDA-D0290 | Loan Disb | 56,549.30 |
Mar 18, 2016 | IDA-D0290 | Loan Disb | 358,704.00 |
Mar 2, 2023 | IDA-D0290 | Loan Disb | 85,462.86 |
Jun 15, 2023 | IDA-D0290 | Loan Disb | 112,559.61 |
May 10, 2024 | IDA-D0290 | Loan Disb | 144,570.20 |
Nov 20, 2023 | IDA-D0290 | Loan Disb | 163,727.19 |
Jan 26, 2015 | IDA-D0290 | Loan Commitment | 7,000,000.00 |
Jun 11, 2024 | IDA-D0290 | Loan Disb | 88,155.63 |
Jun 26, 2024 | IDA-D0290 | Loan Disb | 164,762.22 |
Dec 6, 2022 | IDA-D0290 | Loan Disb | 162,583.00 |
Aug 31, 2022 | IDA-D0290 | Loan Disb | 66,021.45 |
Aug 10, 2022 | IDA-D0290 | Loan Disb | 186,406.08 |
Nov 18, 2021 | IDA-D0290 | Loan Disb | 220,340.50 |
Nov 23, 2021 | IDA-D0290 | Loan Disb | 176,335.48 |
Sep 29, 2021 | IDA-D0290 | Loan Disb | 88,221.25 |
Jun 12, 2020 | IDA-D0290 | Loan Disb | 131,551.19 |
Jun 3, 2020 | IDA-D0290 | Loan Disb | 72,993.92 |
May 6, 2020 | IDA-D0290 | Loan Disb | -66,591.15 |
Dec 18, 2020 | IDA-D0290 | Loan Disb | 63,213.76 |
May 19, 2021 | IDA-D0290 | Loan Disb | 75,745.59 |
Mar 29, 2021 | IDA-D0290 | Loan Disb | 236,463.45 |
Nov 26, 2019 | IDA-D0290 | Loan Disb | -116,228.66 |
Oct 17, 2019 | IDA-D0290 | Loan Disb | 142,209.75 |
Feb 27, 2020 | IDA-D0290 | Loan Disb | 285,437.75 |
Apr 30, 2020 | IDA-D0290 | Loan Disb | 246,900.70 |
May 11, 2020 | IDA-D0290 | Loan Disb | 16,478.39 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2025-05-14 |
Financial Management | Moderately Satisfactory | 2025-05-14 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-05-14 |
Monitoring and Evaluation | Satisfactory | 2025-05-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-05-14 |
Project Management | Moderately Satisfactory | 2025-05-14 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 800.00 | 1500.00 |
Date | December 30, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | December 30, 2014 | |||
Comment |
Projected lifetime energy savings | Value | 0.00 | 400.00 | 12750.00 |
Date | December 30, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
Debtor days | Value | 100.00 | 8.00 | 10.00 |
Date | December 30, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of customers with prepaid meters excluding Government facilities | Value | 0.00 | 95.00 | 100.00 |
Date | December 30, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
People trained through the project | Value | 0.00 | 20.00 | 50.00 |
Date | December 30, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
Customers with pre-paid meters that have been surveyed (Percentage) | Value | 0.00 | 0.00 | 0.00 |
Date | December 30, 2014 | |||
Comment |
Responses provided to relevant complaints / requests from customers | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Enable remote monitoring in outer islands with communication system | Value | 0.00 | 0.00 | 3.00 |
Date | May 31, 2015 | March 19, 2024 | September 30, 2024 | |
Comment |
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 0.75 |
Date | December 31, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 0.00 | 0.75 |
Date | December 31, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |
Storage capacity of battery constructed | Value | 0.00 | 0.00 | 1.00 |
Date | December 31, 2014 | March 19, 2024 | September 30, 2024 | |
Comment |