Skip to Main Navigation

National Cyclone Risk Mitigation Project-II

Abstract*

The development objective of the Second Phase of the National Cyclone Risk Mitigation Project for India is to reduce vulnerability to cyclone and other hydro-meteorological hazards of coastal communities in project states, and increase the capacity of the state entities to effectively plan for and respond to disasters. The project comprises of four components. The first component, early warning dissemination systems (EWDS) will reduce the vulnerability...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to reduce vulnerability to cyclone and other hydro-meteorological hazards of coastal communities in project States, and increase the capacity of the State entities to effectively plan for and respond to disasters.

Key Details

Project Details

  • P144726

  • Closed

  • Anup Karanth , Deepak Singh, Melanie Kappes

  • National Disaster Management Authority,Department of Economic Affairs

  • India

  • February 26, 2014

  • (as of board presentation)

    May 28, 2015

  • November 9, 2015

  • US$ 387.00 million

  • West Bengal: Department of Disaster Management and Civil Defense,Karnataka: Department of Revenue and Disaster Management,Gujarat: Gujarat State Disaster Management Authority,Maharashtra: Department of Relief and Rehabilitation,Kerala: Department of Revenue and Disaster Management,Goa: Water Resources Department

  • South Asia

  • 2015

  • US$ 308.40 million

  • A

  • April 19, 2024

  • March 14, 2023

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 308.40
Borrower/Recipient 78.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 308.40
IBRD + IDA Commitment 308.40
Lending Instrument
Grant Amount N/A
Total Project Cost** 387.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2024 IDA-56930 Int Charges 5,372,344.00
May 15, 2024 IDA-56930 Loan Repay 4,742,913.50
Dec 3, 2018 IDA-56930 Loan Disb 5,736,713.50
Nov 15, 2018 IDA-56930 Int Charges 1,206,390.90
Nov 6, 2018 IDA-56930 Loan Disb 10,096,565.00
May 15, 2019 IDA-56930 Int Charges 8,910.22
May 15, 2019 IDA-56930 Int Charges 1,634,651.60
Jun 20, 2019 IDA-56930 Loan Disb 8,745,191.00
May 3, 2019 IDA-56930 Loan Disb 4,068,191.20
Nov 15, 2019 IDA-56930 Int Charges 1,760,590.40
Nov 15, 2019 IDA-56930 Int Charges 5,247.97
Jan 22, 2020 IDA-56930 Loan Disb 7,209,648.00
Mar 19, 2020 IDA-56930 Loan Disb 6,769,750.50
May 26, 2020 IDA-56930 Loan Disb 5,897,566.00
May 15, 2020 IDA-56930 Int Charges 1,509,588.10
Aug 13, 2020 IDA-56930 Loan Disb 3,289,551.00
Nov 15, 2020 IDA-56930 Int Charges 1,024,442.20
Nov 15, 2020 IDA-56930 Int Charges 31,405.99
Jun 9, 2016 IDA-56930 Loan Disb 2,895,931.00
Nov 15, 2016 IDA-56930 Int Charges 50,229.76
Nov 15, 2016 IDA-56930 Int Charges 36,624.94
Nov 15, 2016 IDA-56930 Int Charges 35,533.32
Jun 16, 2016 IDA-56930 Loan Disb 7,521,877.00
Jun 10, 2016 IDA-56930 Loan Disb 1,205,809.00
Jun 28, 2017 IDA-56930 Loan Disb 10,273,432.00
May 15, 2017 IDA-56930 Int Charges 298,889.60
Aug 29, 2016 IDA-56930 Loan Disb 6,416,404.50
Feb 17, 2017 IDA-56930 Loan Disb 10,601,969.00
Feb 17, 2017 IDA-56930 Loan Disb 6,350,391.50
May 28, 2015 IDA-56930 Loan Commitment 308,400,000.00
Feb 4, 2022 IDA-56930 Loan Disb 8,136,665.50
Nov 15, 2022 IDA-56930 Int Charges 107,717.18
Nov 15, 2022 IDA-56930 Loan Repay 5,353,274.00
Nov 15, 2022 IDA-56930 Int Charges 2,107,879.20
Aug 23, 2022 IDA-56930 Loan Cancel 10,995,986.00
Dec 12, 2022 IDA-56930 Loan Disb 3,672,155.80
Mar 13, 2023 IDA-56930 Loan Cancel 15,000,000.00
Mar 3, 2023 IDA-56930 Loan Disb 4,190,485.50
May 15, 2023 IDA-56930 Loan Repay 1,729,669.10
May 15, 2023 IDA-56930 Int Charges 4,510,284.00
Aug 18, 2023 IDA-56930 Loan Cancel 6,180,819.00
Jul 12, 2023 IDA-56930 Loan Disb 12,756,829.00
Aug 18, 2023 IDA-56930 Loan Disb 3,076,120.20
May 15, 2023 IDA-56930 Loan Repay 3,195,033.20
Nov 15, 2023 IDA-56930 Loan Repay 4,742,913.50
Nov 15, 2023 IDA-56930 Int Charges 5,059,652.00
Nov 15, 2020 IDA-56930 Loan Repay 7,710,000.00
Mar 15, 2021 IDA-56930 Loan Disb 3,770,527.50
Dec 16, 2020 IDA-56930 Loan Cancel 80,000,000.00
Dec 28, 2020 IDA-56930 Loan Disb 9,466,530.00
May 15, 2021 IDA-56930 Loan Repay 5,658,718.00
May 15, 2021 IDA-56930 Int Charges 760,639.44
Jun 23, 2021 IDA-56930 Loan Disb 14,961,185.00
Sep 7, 2021 IDA-56930 Loan Disb 1,797,480.90
Nov 15, 2021 IDA-56930 Int Charges 8,050.08
Nov 15, 2021 IDA-56930 Loan Repay 5,658,718.00
Nov 15, 2021 IDA-56930 Int Charges 815,084.75
Jun 9, 2022 IDA-56930 Loan Disb 5,688,029.00
May 15, 2022 IDA-56930 Loan Repay 5,658,718.00
May 15, 2022 IDA-56930 Int Charges 859,859.75
Jun 29, 2022 IDA-56930 Loan Disb 2,801,533.80
Aug 18, 2022 IDA-56930 Loan Disb 829,928.80
Feb 28, 2022 IDA-56930 Loan Disb 4,513,932.00
Nov 15, 2017 IDA-56930 Loan Disb 1,632,536.10
Jul 27, 2017 IDA-56930 Loan Disb 3,680,242.50
Nov 15, 2017 IDA-56930 Int Charges 563,866.50
Feb 27, 2018 IDA-56930 Loan Disb 3,727,988.20
Jun 8, 2018 IDA-56930 Loan Disb 14,442,035.00
May 15, 2018 IDA-56930 Int Charges 689,774.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2023-03-15
Procurement Moderately Satisfactory 2023-03-15
Monitoring and Evaluation Satisfactory 2023-03-15
Overall Implementation Progress (IP) Moderately Satisfactory 2023-03-15
Financial Management Moderately Satisfactory 2023-03-15
Counterpart Funding Satisfactory 2023-03-15
Project Management Moderately Satisfactory 2023-03-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-18-2025PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Proportion of the targeted coastal population covered by the EWDSValue0.0045.0075.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Results of the vulnerability assessment presented to officials of NDMA for investment planningValueNoYesYes
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Proportion of vulnerable coastal population with access to Project financed emergency sheltersValue0.0017.0017.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Results of the comprehensive multi-hazard risk financing strategy presented to and used by officials of NDMA for policy makingValueNoNoYes
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of sirens installedValue0.00193.00200.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Number of multi-purpose cyclone and flood shelters completedValue0.00260.00262.00
    DateJune 15, 2015March 14, 2023September 3, 2021
    Comment
  • Multi-hazard risk assessment for selected areas completedValueNoYesYes
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Physical structural assessment of lifeline infrastructure completedValueNoYesYes
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Number of people with access to multi-purpose cyclone and flood shelters built or rehabilitated under the ProjectValue0.000.000.00
    DateJune 15, 2015
    Comment
  • Roads rehabilitated, RuralValue0.00205.00205.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Probabilistic risk model for selected areas completedValueNoYesYes
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Number of bridges completed under the projectValue0.002.002.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Hydro-meteorological Resilience Action Plans completedValueNoYesYes
    DateDecember 15, 2014March 14, 2023March 14, 2023
    Comment
  • Kilometers of embankments rehabilitated under the ProjectValue0.0030.0630.00
    DateMarch 18, 2016March 14, 2023March 14, 2023
    Comment
  • Number of training modules on disaster damage assessment implementedValue0.009.008.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment
  • Square kilometers protected by embankments rehabilitated by the ProjectValue0.000.000.00
    DateJune 15, 2015
    Comment
  • Kilometers of HT and LT lines moved undergroudValue0.001409.001286.00
    DateJune 15, 2015March 14, 2023March 14, 2023
    Comment