Financier | Commitments |
---|---|
Single Purpose Trust Fund | 8.30 |
P144966
Closed
Abebaw Alemayehu
N/A
May 4, 2015
(as of board presentation)
June 8, 2015
N/A
US$ 8.30 million
N/A
2015
US$ 8.30 million
B
August 5, 2024
December 31, 2020
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Single Purpose Trust Fund | 8.30 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.30 |
Total Project Cost** | 8.30 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2017-09-11 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-09-11 |
Procurement | Moderately Satisfactory | 2017-09-11 |
Counterpart Funding | Moderately Satisfactory | 2017-09-11 |
Project Management | Satisfactory | 2017-09-11 |
Financial Management | Satisfactory | 2017-09-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-09-11 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People benefiting from improved tenure security under component 2 of the KISIP. | Value | 0.00 | 22000.00 | 200000.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 22000.00 | 1100000.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment |
People in informal settlements provided with access to improved drainage infrastructure under KISIP | Value | 0.00 | 0.00 | 1000000.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Works have commenced in Eldoret and Nakuru with drainage works |
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project | Value | 0.00 | 0.00 | 1000000.00 |
Date | April 3, 2012 | December 31, 2014 | June 30, 2016 | |
Comment | Works have commenced in Eldoret, Nakuru, Mombasa and Machakos, and Nairobi |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 0.00 | 100000.00 |
Date | April 3, 2012 | December 31, 2014 | June 30, 2016 | |
Comment | Works has began in Nairobi, Kayole Soweto settlements. |
Female beneficiaries | Value | 0.00 | 11000.00 | 550000.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Informal settlements benefiting from enhanced tenure security under KISIP. | Value | 0.00 | 13.00 | 67.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | 13 (65 hectares) | (905 hectares) |
GIS lab at the ministry upgraded and operational. | Value | No | No | Yes |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Upgrade is nearly complete with hardware received and training completed. | GIS lab operational |
Infrastructure sub-projects functioning one year after completion and with operations and maintenance arrangement in place. | Value | 0.00 | 0.00 | 90.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment |
People in settlements provided with access to improved shared sanitation facilities under the KISIP. | Value | 0.00 | 0.00 | 2250.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Works on ablution blocks have commenced in Eldoret and Mombasa. |
Policies, frameworks, and guidelines for slum upgrading developed and adopted by the MLHUD | Value | 0.00 | 1.00 | 1.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Activity completed. |
Housing quality index established. | Value | 0.00 | Housing quality index updated and published. | |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | This indicator to be dropped. |
Database with slum inventory operational and accessible to the public. | Value | No | No | Yes |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | TORs for consultancy to conduct data gathering currently being drafted. | Database operational and accessible to the public. |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 0.00 | 4000.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Works have commenced in several settlements. |
Roads rehabilitated, Non-rural | Value | 0.00 | 0.00 | 1540.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Works started in Feb/March 2014 and expected to complete in 12 months. |
New street or security lights put into place under the KISIP. | Value | 0.00 | 0.00 | 40.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Works started in Feb/March 2014 and expected to complete in 6 months. |
Study of constraints to delivery of serviced land completed. | Value | No | No | Yes |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | To be dropped. |
Preparation of city-specific housing strategies and action plans. | Value | 0.00 | 0.00 | 5.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | To be dropped. |
New Sewer connections constructed under the project | Value | 0.00 | 0.00 | 2200.00 |
Date | October 25, 2010 | December 31, 2014 | June 30, 2016 | |
Comment | Sewerage works in Kayole Soweto commenced in Feb/March 2014 and expected to be completed in 18 months |
Drainage System Rehabiliated | Value | 0.00 | 0.00 | 40.00 |
Date | December 31, 2014 | June 30, 2016 | ||
Comment |
Footpaths Rehabilitated | Value | 0.00 | 0.00 | 37.00 |
Date | December 31, 2014 | June 30, 2016 | ||
Comment |
Situational Analysis | Value | No | Yes | Yes |
Date | December 31, 2014 | June 30, 2016 | ||
Comment |
Housing Survey | Value | No | Yes | Yes |
Date | December 31, 2014 | June 30, 2016 | ||
Comment |
Planning manual for informal settlements | Value | No | No | Yes |
Date | December 31, 2014 | June 30, 2016 | ||
Comment |