Skip to Main Navigation

Pacific Aviation Safety Office Reform Project

Abstract*

The development objective of the Pacific Aviation Safety Office Reform Project for Pacific Islands is to ensure effective regional delivery of aviation safety and security oversight in Pacific Island countries by strengthening the Pacific Aviation Safety Office's (PASO's) technical and coordination capacity. There are three components to the project. The first component of the project is transitional management and support. This component comprises...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to strengthen the coordination capacity of the Pacific Aviation Safety Office to deliver regional aviation safety and security oversight, and technical and advisory services to the Pacific Island Countries.

Key Details

Project Details

  • P145057

  • Closed

  • Dung Hoang

  • Pacific Aviation Safety Office

  • Pacific Islands

  • May 2, 2013

  • (as of board presentation)

    September 30, 2013

  • December 12, 2013

  • US$ 2.15 million

  • Pacific Aviation Safety Office

  • East Asia and Pacific

  • 2014

  • US$ 2.15 million

  • C

  • Not Applicable

  • December 31, 2022

  • Yes

  • BANK APPROVED

  • May 30, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 2.15

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 2.15
IBRD + IDA Commitment 2.15
Lending Instrument
Grant Amount N/A
Total Project Cost** 2.15

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 30, 2013 IDA-H8830 Loan Commitment 2,150,000.00
May 23, 2018 IDA-D3190 Loan Commitment 3,550,000.00
Apr 30, 2023 IDA-D3190 Loan Cancel 49,771.59
Mar 15, 2023 IDA-D3190 Loan Disb -19,234.11
Mar 15, 2023 IDA-D3190 Loan Disb -29,953.25
Nov 14, 2022 IDA-D3190 Loan Disb 66,900.77
Sep 6, 2022 IDA-D3190 Loan Disb 113,655.64
Oct 11, 2022 IDA-D3190 Loan Disb 231,854.22
Nov 23, 2022 IDA-D3190 Loan Disb 1,230.98
Jun 15, 2022 IDA-H8830 Loan Cancel 38,987.18
Mar 3, 2022 IDA-D3190 Loan Disb 141,681.12
Jun 15, 2022 IDA-D3190 Loan Disb 263,697.03
Nov 10, 2021 IDA-D3190 Loan Disb 35,360.73
Jul 11, 2022 IDA-D3190 Loan Disb 52,371.46
Jun 15, 2022 IDA-H8830 Loan Disb -38,987.18
Jul 22, 2022 IDA-D3190 Loan Disb 223,355.30
Sep 16, 2021 IDA-D3190 Loan Disb 279,721.34
Sep 17, 2021 IDA-D3190 Loan Disb 82,469.26
Jun 21, 2021 IDA-D3190 Loan Disb 227,766.20
Jul 31, 2020 IDA-D3190 Loan Disb 339,832.03
Nov 24, 2020 IDA-D3190 Loan Disb 108,604.22
Feb 6, 2020 IDA-D3190 Loan Disb 180,775.55
May 28, 2020 IDA-D3190 Loan Disb 252,364.34
Sep 19, 2019 IDA-D3190 Loan Disb 83,722.39
Jun 26, 2019 IDA-D3190 Loan Disb 122,580.89
Nov 25, 2019 IDA-D3190 Loan Disb 164,650.33
Jul 24, 2019 IDA-D3190 Loan Disb 53,128.49
Apr 27, 2018 IDA-H8830 Loan Disb 84,532.95
Mar 23, 2018 IDA-H8830 Loan Disb 122,258.94
Nov 26, 2018 IDA-D3190 Loan Disb 400,000.00
Oct 17, 2017 IDA-H8830 Loan Disb 69,801.66
Oct 17, 2017 IDA-H8830 Loan Disb 86,842.24
Oct 17, 2017 IDA-H8830 Loan Disb 54,173.52
Oct 18, 2017 IDA-H8830 Loan Disb 79,769.77
Oct 23, 2017 IDA-H8830 Loan Disb 66,934.81
Aug 18, 2014 IDA-H8830 Loan Disb 45,592.28
Mar 21, 2014 IDA-H8830 Loan Disb 142,706.16
Mar 4, 2014 IDA-H8830 Loan Disb 400,000.00
Nov 19, 2014 IDA-H8830 Loan Disb 98,361.06
Dec 17, 2015 IDA-H8830 Loan Disb 17,386.35
Dec 17, 2015 IDA-H8830 Loan Disb 37,026.67
Dec 17, 2015 IDA-H8830 Loan Disb 28,532.55
Dec 17, 2015 IDA-H8830 Loan Disb 90,822.41
Dec 30, 2015 IDA-H8830 Loan Disb 36,000.00
Feb 16, 2016 IDA-H8830 Loan Disb 75,534.02
Dec 22, 2015 IDA-H8830 Loan Disb 127,579.57
Apr 1, 2016 IDA-H8830 Loan Disb 86,726.09
Mar 30, 2016 IDA-H8830 Loan Disb 126,990.58
Jun 13, 2016 IDA-H8830 Loan Disb 72,900.96
Aug 17, 2016 IDA-H8830 Loan Disb 63,412.50
Aug 19, 2016 IDA-H8830 Loan Disb 152,901.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2022-12-07
Financial Management Moderately Satisfactory 2022-12-07
Progress towards achievement of PDO Satisfactory 2022-12-07
Project Management Moderately Satisfactory 2022-12-07
Monitoring and Evaluation Satisfactory 2022-12-07
Overall Implementation Progress (IP) Satisfactory 2022-12-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-30-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-31-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: Successful recruitment of General Manager, Operations Manager, Corporate Services ManagerValueNo positions filledGeneral Manager, Operations Manager, Corporate SerGeneral Manager, Operations Manager, Corporate Ser
    DateNovember 1, 2013July 31, 2022May 23, 2018
    Comment
  • Indicator Two: Establishment of a Register of Inspectors (ROI)ValueNo ROIUpdated ROI in place.
    DateNovember 1, 2013July 31, 2022
    Comment
  • Indicator Four: PASO addresses at least 80% of the GASOS functions for a Level 2 RSOOValue34.0080.000.00
    DateOctober 31, 2021December 31, 2022
    Comment
  • Indicator Three: Recommended Annual Work Program Implemented by PASO MembersValue12.5052.2060.00
    DateNovember 1, 2013June 30, 2022December 3, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component A: Intermediate Results Indicator One: Revised governance structure (technical and financial committee composition), as per PASO ConstitutionValuePASO ConstitutionUpdated PASO Constitution approved by PASO Council
    DateAugust 1, 2013July 31, 2022
    Comment
  • Component B: Intermediate Results Indicator One: Adherence to Agreed Annual Work PlansValue43.8052.2060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Component C: Intermediate Results Indicator One: Establishment of Quality Assurance SystemValueNo Quality Assurance SystemQuality Assurance System in use.
    DateAugust 1, 2013July 31, 2022
    Comment
  • Component D: Supporting Regional Aviation InfrastructureValueNo VSATVSAT operating
    DateJanuary 2, 2017July 31, 2022
    Comment
  • Component A: Intermediate Results Indicator Two: Revised financing mechanism for sustainabilityValueExisting funding mechanism inadequateSustainable Financing Mechanism in place
    DateAugust 1, 2013July 31, 2022
    Comment
  • Component C: Intermediate Results Indicator Two: Modernization of communication technologyValueInadequate ICT system in useUpgraded ICT system in use
    DateAugust 1, 2013July 31, 2022
    Comment
  • Annual Work Plan Implemented - KiribatiValue130.0045.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Project-supported organization(s) publish reports on effect of collaboration on project/program/policies (Yes/No)ValueNoYes
    DateJune 1, 2018July 31, 2022
    Comment
  • Annual Work Plan Implemented - Cook IslandsValue0.00100.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - NauruValue0.0013.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - NiueValue0.0016.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - Papua New GuineaValue0.0037.0060.00
    DateJanuary 1, 2013June 30, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - SamoaValue54.0049.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - Solomon IslandsValue24.0059.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - TongaValue62.00100.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - TuvaluValue0.003.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Annual Work Plan Implemented - VanuatuValue27.00100.0060.00
    DateJanuary 1, 2013December 31, 2022December 3, 2021
    Comment
  • Beneficiaries of job-focused interventionsValue0.000.000.00
    DateJune 1, 2018December 31, 2022
    Comment
  • Beneficiaries of job-focused interventions - FemaleValue0.000.000.00
    DateJune 1, 2018May 1, 2018
    Comment