Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 338.80 |
P145174
Active
Ana Mercado , Adina Voda
ROMANIA
Romania
July 17, 2013
(as of board presentation)
March 28, 2014
January 22, 2015
US$ 338.80 million
Ministry of Health
2014
US$ 338.80 million
B
May 10, 2024
June 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 338.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 338.80 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 338.80 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 338.80 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 6, 2016 | IBRD-83620 | Loan Disb | 797,540.06 |
Mar 6, 2017 | IBRD-83620 | Loan Disb | 3,949,397.50 |
Mar 2, 2015 | IBRD-83620 | Fee Charges | 701,531.25 |
Mar 1, 2024 | IBRD-83620 | Int Charges | 4,430,670.00 |
Mar 1, 2024 | IBRD-92530 | Int Charges | 200,813.98 |
Jun 24, 2024 | IBRD-83620 | Loan Disb | 1,983,658.60 |
Jun 6, 2024 | IBRD-83620 | Loan Disb | 13,553,433.00 |
Jun 21, 2023 | IBRD-83620 | Loan Disb | 6,109,883.00 |
Sep 1, 2023 | IBRD-83620 | Int Charges | 3,710,453.80 |
Sep 1, 2023 | IBRD-92530 | Int Charges | 205,034.00 |
Sep 27, 2023 | IBRD-83620 | Loan Disb | 2,418,406.00 |
Mar 1, 2023 | IBRD-92530 | Int Charges | 198,418.17 |
May 21, 2018 | IBRD-83620 | Loan Disb | 8,651,071.00 |
Nov 16, 2018 | IBRD-83620 | Loan Disb | 32,439,526.00 |
Mar 1, 2017 | IBRD-83620 | Int Charges | 1,279.13 |
Sep 1, 2017 | IBRD-83620 | Int Charges | 10,581.93 |
Jul 18, 2017 | IBRD-83620 | Loan Disb | 5,967,436.00 |
Jul 6, 2017 | IBRD-83620 | Loan Disb | 1,171,867.90 |
Jun 4, 2021 | IBRD-92530 | Loan Commitment | 176,000,000.00 |
Mar 28, 2014 | IBRD-83620 | Loan Commitment | 338,800,000.00 |
Feb 2, 2024 | IBRD-92530 | Loan Disb | 6,860,532.50 |
Jan 30, 2024 | IBRD-83620 | Loan Disb | 7,852,612.50 |
Mar 1, 2023 | IBRD-83620 | Int Charges | 1,626,439.00 |
Mar 17, 2023 | IBRD-83620 | Loan Disb | 3,820,564.50 |
Feb 22, 2022 | IBRD-83620 | Loan Disb | 5,112,406.00 |
Apr 11, 2022 | IBRD-83620 | Loan Disb | 3,843,065.50 |
Mar 1, 2022 | IBRD-83620 | Int Charges | 164,655.56 |
Mar 1, 2022 | IBRD-92530 | Int Charges | 233,088.52 |
Nov 22, 2022 | IBRD-83620 | Loan Disb | 5,823,206.50 |
Feb 9, 2022 | IBRD-92530 | Fee Charges | 428,606.25 |
Sep 1, 2022 | IBRD-83620 | Int Charges | 175.56 |
Sep 1, 2022 | IBRD-83620 | Int Charges | 151,068.05 |
Sep 1, 2022 | IBRD-92530 | Int Charges | 189,400.30 |
Sep 19, 2022 | IBRD-83620 | Loan Disb | 1,477,519.80 |
Mar 1, 2021 | IBRD-83620 | Int Charges | 183,206.98 |
Dec 28, 2020 | IBRD-83620 | Loan Disb | 11,138,744.00 |
Mar 16, 2021 | IBRD-83620 | Loan Disb | 16,220,911.00 |
Jun 21, 2021 | IBRD-83620 | Loan Disb | 7,443,410.00 |
Sep 1, 2021 | IBRD-83620 | Int Charges | 171,097.48 |
Jun 24, 2022 | IBRD-83620 | Loan Disb | 4,239,228.00 |
Jun 25, 2020 | IBRD-83620 | Loan Disb | 5,437,582.50 |
Oct 20, 2020 | IBRD-83620 | Loan Disb | 19,017,710.00 |
Sep 1, 2020 | IBRD-83620 | Int Charges | 180,206.11 |
Feb 22, 2019 | IBRD-83620 | Loan Disb | 5,182,842.00 |
Mar 1, 2019 | IBRD-83620 | Int Charges | 109,201.21 |
Mar 1, 2019 | IBRD-83620 | Int Charges | 1,090.67 |
Jun 13, 2019 | IBRD-83620 | Loan Disb | 9,132,233.00 |
Nov 25, 2019 | IBRD-83620 | Loan Disb | 6,624,880.00 |
Aug 16, 2019 | IBRD-83620 | Loan Disb | 5,986,514.50 |
Sep 1, 2019 | IBRD-83620 | Int Charges | 402.33 |
Sep 1, 2019 | IBRD-83620 | Int Charges | 176,762.08 |
Oct 29, 2019 | IBRD-83620 | Loan Disb | 7,629,053.00 |
Mar 10, 2020 | IBRD-83620 | Loan Disb | 8,035,599.00 |
Mar 1, 2020 | IBRD-83620 | Int Charges | 1,241.20 |
Mar 1, 2020 | IBRD-83620 | Int Charges | 126,834.92 |
Mar 1, 2018 | IBRD-83620 | Int Charges | 3,941.28 |
Mar 1, 2018 | IBRD-83620 | Int Charges | 24,769.15 |
Apr 11, 2018 | IBRD-83620 | Loan Disb | 12,424,972.00 |
Jul 16, 2018 | IBRD-83620 | Loan Disb | 2,204,615.80 |
Sep 1, 2018 | IBRD-83620 | Int Charges | 52,471.51 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2024-10-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-10-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-29 |
Procurement | Moderately Satisfactory | 2024-10-29 |
Project Management | Moderately Satisfactory | 2024-10-29 |
Financial Management | Satisfactory | 2024-10-29 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average number of modern and safe radiotherapy unit available per 1 million population | Value | 1.40 | 3.83 | 2.20 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Advanced Surveillance and Treatment Unit of Critical Cardiac Patients (USTACC) mortality rate | Value | 6.85 | 4.94 | 5.83 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Percentage of diagnosed COVID-19 cases treated per approved protocol | Value | 0.00 | 98.75 | 80.00 |
Date | January 1, 2020 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of burn centers for the treatment of severe burns completed | Value | 0.00 | 0.00 | 2.00 |
Date | March 31, 2014 | December 31, 2023 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average waiting time (days) of radiotherapy treatment (LINAC) from prescription to treatment at Public Radiotherapy Centers | Value | 60-90 | 16.1 | <45 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of hospitals with functional emergency telemedicine system | Value | 38.00 | 38.00 | 120.00 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Comprehensive communication campaign implemented (Cumulative) | Value | 0.00 | 2.00 | 2.00 |
Date | July 10, 2015 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of Cardiology Care Unit (USTACC) equipped according to the national regulations | Value | 0.00 | 13.00 | 11.00 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of contracts signed for construction works for burn centers for the treatment of severe burns | Value | 0.00 | 3.00 | 3.00 |
Date | December 19, 2013 | January 15, 2024 | June 30, 2026 | |
Comment |
Number of burn centers for the treatment of severe burns equipped | Value | 0.00 | 0.00 | 2.00 |
Date | December 31, 2020 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of health professionals trained (burn centers, radiotherapy, emergency, intensive care) | Value | 0.00 | 117.00 | 75.00 |
Date | December 19, 2013 | December 31, 2023 | June 30, 2026 | |
Comment |
First phase of Grigore Alexandrescu Bucure?ti Burn Center completed | Value | 0.00 | 0.00 | 1.00 |
Date | February 27, 2023 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of health workers trained in HTA | Value | 0.00 | 34.00 | 18.00 |
Date | December 19, 2013 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of designated laboratories with COVID-19 diagnostic equipment, test kits, and reagents | Value | 0.00 | 104.00 | 50.00 |
Date | January 1, 2020 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of regional pathology and cytology laboratories fully operational | Value | 0.00 | 0.00 | 6.00 |
Date | December 19, 2013 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of international evidence-based standards and protocols implemented on selected public health services | Value | 0.00 | 45.00 | 6.00 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Activation of public health Emergency Operations Centre or a coordination mechanism for COVID-19 | Value | No | Yes | Yes |
Date | January 1, 2020 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of mobile units for cancer screening fully functional for campaining activities | Value | 0.00 | 8.00 | 8.00 |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |
Number of women using mobile cancer screening units and cancer screening centers (cumulative) | Value | 0.00 | 102950.00 | 24000.00 |
Date | December 31, 2019 | December 31, 2023 | June 30, 2026 | |
Comment |
Development of annual action plan to improve patients' satisfaction based on patients' satisfaction survey with hospital services | Value | No | No | Yes |
Date | July 11, 2018 | December 31, 2023 | June 30, 2026 | |
Comment |