Development Objective

The overall objective of the proposed project (TAJSTAT-II) is to further improve the capacity of statistical system of Tajikistan to produce and disseminate relevant, reliable and timely statistics in a cost-effective manner that are in line with internationalstandards and will be responsive to user needs. The project will build on the achievements of the previous TAJSTAT project to sustain the progress.

Key Details

Project Details

  • P145185

  • Closed

  • Alisher Rajabov

  • Government of the Republic of Tajikistan

  • Tajikistan

  • September 26, 2014

  • (as of board presentation)

    September 26, 2014

  • May 29, 2015

  • US$ 2.75 million

  • Agency on Statistics under the President of the Republic of Tajikistan (TajStat)

  • Europe and Central Asia

  • 2015

  • US$ 2.50 million

  • C

  • October 5, 2023

  • June 30, 2018

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.25
Program to Support Statistical Capacity Building in ECA 2.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.50
Total Project Cost** 2.75

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Moderable 2018-05-18
Progress towards achievement of PDO Satisfactory 2018-05-18
Overall Implementation Progress (IP) Satisfactory 2018-05-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Statistical capacity of the state statistical system according to the score published on the World Bank Bulletin BoardValueThe overall statistical capacity score is 71 in 207575
    DateDecember 31, 2013June 30, 2018June 30, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Strengthened relationships with relevant policy-making bodies through meetings and high-level seminars to improve understanding of the role of official statisticsValueNo dedicated seminars or workshops to improve undeOn average 3-5 seminar/meetings to be organized anMore than 5 seminars/meetings are being organized
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improved implementation of the Law on Statistics.ValueThe score 1.5 is established based on the U.S. Centhe score will go up by 1 point over the life of tThe target is to have a score of 2.5, while the sc
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Optimized data collection programs and redistributed functions between the AS departments with a clear structureValueThe score 1.5 is established based on the U.S. CenThe score will go up by 0.25 on average per year oThe score was assessed to 2.25 at the end of the p
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Develop professional knowledge and training for staff to support NSDS objectives. Conduct employee satisfaction surveyValueThe score 1.5 is established based on the U.S. CenThe score will go up by 0.25 on average per year oThe score is 2.25 and thus end target has been ach
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • TajStat core staff has obtained and uses latest methodological skills in classification, standards, sampling and seasonal adjustmentsValueThe score 1.5 is established based on the U.S. CenThe score will go up by 0.25 on average per year oThe score reached 2.25 by the end of the project a
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Data quality assurance framework and quality assurance working group are established and functioningValueThere is no data quality assurance group.Fully functioning data quality assurance frameworkData-quality assurance working group has been esta
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improved quality, access, and use of poverty and employment data through improvement to and use of the HBS and LFSValueNo poverty rate has been published since 2009 or L2016: Poverty rates reported in a quarterly movingTajStat produces quarterly poverty estimates and s
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improve quality, access, and use of gender disaggregated dataValue2013-14: Limited gender-disaggregated statistics2016: The list of gender-disaggregated indicator iIt is assessed that the list of gender disaggregat
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improve statistical reporting forms and prepare for "electronic reporting" to reduce burden on respondentsValueNumber of current reporting forms in a year:Reduce the respondent burden by 10 percent by the The target under this result indicator was to have
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improved tracking of user feedback and higher user satisfactionValueUser satisfaction surveys are introduced.User satisfaction surveys conducted at least annuaUser satisfaction surveys have been institutionali
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Develop integrated and harmonized statistical information sources for NSS and standards for exchange of statistical data (SDMX)ValueIntegrated and harmonized statistical information The SDMX is implemented.SA has fully implemented SDMX standards and is rea
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Organize training and workshops for users of statistics and establish feedback mechanism to measure satisfaction with disseminated informationValueUser-friendly feedback system does not existOn average 2-3 trainings/workshops to be held everMore than 3 trainings/workshops/seminars are being
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Improved dissemination and access to statistics, metadata and quality reports according to the SDDS of IMF standardsValueNo reporting and dissemination is done according t2016: Adopt and implement the steps to fully complSignificant steps have been taken to comply with I
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • HBS DDI produced and NADA server covering all AS's surveys micro- and metadata is available for use by the AS staffValueADP trainings held, most surveys documented, howevHBS DDI produced and NADA server covering all AS'sMost survey and census (not only of HBS) meta- and
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • IT capacity (soft ware and hardware) for operations, printing facility and other equipment are adequate and maintainedValueCurrent state of the IT capacity needs improvementModern and adequate IT environment established, prThe IT capacity of the Agency has been significant
    DateJune 30, 2015June 30, 2018June 30, 2018
    Comment
  • Automated database processing and reporting are establishedValueNo automated database processing and reporting.2016: Prepare automated database processing and reThe new website of the Agency was developed with t
    DateJune 30, 2015June 30, 2018June 30, 2018