Financier | Commitments |
---|---|
IDA Grant | 6.06 |
P145310
Closed
Christopher Bennett
N/A
August 24, 2013
(as of board presentation)
November 1, 2013
N/A
US$ 6.06 million
N/A
2014
US$ 6.06 million
B
July 15, 2021
June 15, 2023
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 6.06 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 6.06 |
IBRD + IDA Commitment | 6.06 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 6.06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Non-rural | Value | 0.00 | 0.00 | 7.40 |
Date | May 23, 2013 | May 23, 2013 | June 30, 2015 | |
Comment | Investments have not commenced. |
Roads in good and fair condition as a share of total classified roads | Value | 50.00 | 50.00 | 100.00 |
Date | May 23, 2013 | May 23, 2013 | June 30, 2015 | |
Comment | Estimate based on road condition survey. | Investments have not commenced. |
Roads rehabilitated, Rural | Value | 0.00 | 0.00 | 8.00 |
Date | May 23, 2013 | May 23, 2013 | June 30, 2015 | |
Comment | Investments have not commenced. |
Size of the total classified network | Value | 15.40 | 0.00 | 15.40 |
Date | May 23, 2013 | May 23, 2013 | June 30, 2015 | |
Comment |
Indicator One: ICAO certification of safety and security at project airports | Value | FUN currently not certified | FUN currently not certified | Certification of airports in accordance with agree |
Date | December 13, 2011 | May 23, 2013 | June 30, 2016 | |
Comment | Investments have not commenced. Design work nearing completion and major procurements to start later in 2013. Project on track tomeet target. |
Indicator Two: Resolution of safety concerns at participating airports reaches global ICAO average | Value | 95.00 | 95.00 | 49.00 |
Date | December 13, 2011 | May 23, 2013 | June 30, 2016 | |
Comment | Baseline value assumed based on Tonga | Investments have not commenced but project on track to meet target. Design work nearing completion and major procurements to startlater in 2013. |
Indicator Three: Modernization of air traffic management | Value | No VSAT or ADS-B | No VSAT or ADS-B | VSAT and ADS-B operational |
Date | December 13, 2011 | May 23, 2013 | June 30, 2014 | |
Comment | VSAT design consultant recruitment in final stages. Preliminary design of ADS-B prepared. Project on track to meet target. |
Indicator Four: Implementation of a regional safety levy for international passengers | Value | No levy | No levy | AU$5 collected from each departing international p |
Date | December 13, 2011 | May 23, 2013 | June 30, 2014 | |
Comment | Implementation is overdue. Plan for implementing levy being submitted to cabinet for their urgent attention. TFSU will help withpracticalities of implementing the levy. | Target date for implementation changed to 2014 from 2013. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A - Intermediate Result indicator Five: Number of kilometers of paved roads improved | Value | 0.00 | 0.00 | 15.40 |
Date | May 23, 2013 | May 23, 2013 | June 30, 2015 | |
Comment | Investments have not commenced. |
Component A: Intermediate Result indicator Two: Rehabilitation of Funafuti runway | Value | 0.00 | 10.00 | 100.00 |
Date | December 13, 2011 | May 23, 2013 | June 30, 2014 | |
Comment | Investments have not commenced. Design finalized and bidding documents under preparation. Anticipate bidding late 2013 once Tongadesigns are completed. |
Component A: Intermediate Result indicator One: Navigation and safety aids fully operational | Value | 0.00 | 10.00 | 100.00 |
Date | December 13, 2011 | May 23, 2013 | June 30, 2015 | |
Comment | Investments have not commenced. Design report submitted. Waiting for finalization of Kiribati and Tonga designs to startprocurement. Project on track to meet target. |
Component A: Intermediate Result indicator Three: Achievement of Fire Standards | Value | N/A | Not achieved. | Category 5 |
Date | December 13, 2011 | May 23, 2013 | June 30, 2014 | |
Comment | Ordering of fire uniforms and other gear under way. GoTv now looking to procure a refurbished fire tender with funding from NewZealand. |
Component A: Intermediate Result indicator Four: Funafuti terminal and control tower upgrade | Value | 0.00 | 10.00 | 100.00 |
Date | December 13, 2011 | May 23, 2013 | June 30, 2015 | |
Comment | Conceptual terminal design agreed on. Detailed design now commencing.To ensure adequate site distance control tower now to beseparate building. Detailed design will commence after restructuring. Project on track to meet target. |
Component B: Intermediate Result indicator One: Successful implementation of agreed training plan | Value | No training plan | No training plan | Training plan completed |
Date | December 13, 2011 | May 23, 2013 | June 30, 2016 | |
Comment | Training Needs Assessment not satisfactorily completed by consultant so waiting on final version acceptable to fully commencetraining program. In the interim, key training has been done. |