Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 0.30 |
P145434
Closed
Joern Huenteler , Imtiaz Hizkil
Ministry of Electricity and Energy
Yemen, Republic of
April 16, 2013
(as of board presentation)
April 16, 2013
N/A
US$ 0.30 million
N/A
2013
US$ 0.30 million
N/A
Not Applicable
September 23, 2015
BANK APPROVED
October 18, 2022
Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 0.30 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.30 |
Total Project Cost** | 0.30 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Unsatisfactory | 2015-07-08 |
Procurement | Moderately Satisfactory | 2015-07-08 |
Financial Management | Moderately Unsatisfactory | 2015-07-08 |
Monitoring and Evaluation | Moderately Satisfactory | 2015-07-08 |
Project Management | Unsatisfactory | 2015-07-08 |
Overall Implementation Progress (IP) | Unsatisfactory | 2015-07-08 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Investment plan for developing renewable energies in Yemen is finalized. | Value | No | No | Yes |
Date | September 3, 2013 | June 25, 2014 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SREP funding for investment plan secured | Value | No | No | Yes |
Date | September 3, 2013 | June 25, 2014 | June 30, 2015 | |
Comment |