Financier | Commitments |
---|---|
IDA Grant | 3.00 |
P145488
Closed
Lucy Pan
Ministry of Finance and Economic Development
November 22, 2013
(as of board presentation)
November 22, 2013
January 31, 2014
US$ 3.00 million
Ministry of Finance and Economic Development
2014
US$ 3.00 million
N/A
August 20, 2020
June 30, 2014
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 3.00 |
IBRD + IDA Commitment | 3.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 3.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 22, 2013 | IDA-H8890 | Loan Commitment | 3,000,000.00 |
Apr 7, 2014 | IDA-H8890 | Loan Disb | 3,083,420.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2014-04-20 |
Monitoring and Evaluation | Satisfactory | 2014-04-20 |
Overall Implementation Progress (IP) | Satisfactory | 2014-04-20 |
Program Management | Satisfactory | 2014-04-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2017 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Not Applicable |
Implementing Agency | Not Applicable |
INDICATOR | ICR REVIEW: 06-15-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Modest | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Management of revenue records | Value | Full reconciliation not available | Treasury records do not deviate by more than 10 pe | |
Date | December 31, 2012 | December 31, 2015 | ||
Comment |
Increased budget allocation to primary and secondary education (including vocational) | Value | AUD 3.1 million | Increase on average by at least 5 percent per annu | |
Date | December 31, 2012 | December 31, 2015 | ||
Comment | Estimate |
Variance in composition of expenditure | Value | Average 2010-12 variance > 10% | Average 2013-15 variance < 10% | |
Date | December 31, 2012 | December 31, 2015 | ||
Comment | Calculated in accordance with PEFA guidelines for PEFA Indicator II, excluding one-off lumpy items. |
Increased budget allocation to primary and secondary health | Value | AUD 2.3 million | Increase on average by at least 5 percent per annu | |
Date | December 31, 2012 | December 31, 2015 | ||
Comment | Estimate |
Share of newly approved projects implemented in line with the outer island plans for community development | Value | n/a | > 50 percent. | |
Date | December 31, 2012 | December 31, 2015 | ||
Comment |