Skip to Main Navigation

China Contaminated Site Management Project

Abstract*

The project development objective of the Contaminated Site Management Project for China is to improve the country’s capacity for managing site contamination, and demonstrate environmentally sound identification and cleanup of sites contaminated with Persistent Organic Pollutants (POPs) and other hazardous chemicals. The project is comprised of three components. Component 1, capacity development for prevention and control of site contamination included...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve the country's capacity for managing site contamination, and demonstrate environmentally sound identification and cleanup of sites contaminated with POPs and other hazardous chemicals.

Key Details

Project Details

  • P145533

  • Closed

  • Qing Wang

  • PEOPLE'S REPUBLIC OF CHINA

  • China

  • July 11, 2013

  • (as of board presentation)

    April 30, 2015

  • September 18, 2015

  • US$ 75.00 million

  • Foreign Environmental Cooperation Center of Ministry of Ecology and Environment

  • East Asia and Pacific

  • 2015

  • US$ 15.00 million

  • A

  • Not Applicable

  • November 30, 2023

  • TBD

  • BANK APPROVED

  • July 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 60.00
Global Environment Facility (GEF) 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 15.00
Total Project Cost** 75.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Satisfactory 2023-06-09
Procurement Satisfactory 2023-06-09
Counterpart Funding Moderately Satisfactory 2023-06-09
Project Management Satisfactory 2023-06-09
Financial Management Satisfactory 2023-06-09
Monitoring and Evaluation Satisfactory 2023-06-09
Overall Implementation Progress (IP) Moderately Satisfactory 2023-06-09

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-06-2024
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-11-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1. Selected priority technical guidelines (TG) and policy recommendations (PRs) for prevention and control of site contamination atthe national and local levels developed or issuedValueExisting TG for site cleanup (control of site cont100% achieved
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 3. Contaminated land managed or dump sites closed under the projectValue0.00100.000.01
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 2. Training materials published and on-line training courses integrated into MEP staff training systemValueNo training system for prevention and control of s100% achievedAnnual training plan implemented
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 4. National database of POPs contaminated sites establishedValueNo database for contaminated sites100% achieved
    DateJanuary 1, 2015November 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 5. Number of people trained on prevention and control of site contaminationValue022,518, including 400 (Liaoning) new people traineAs per annual training plan
    DateDecember 31, 2014November 30, 2023
    Comment
  • 9. POPs&pops waste destroyed, disposed or contained in environmentally sound mannerValue0.00423388.00875.00
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 6. Public Awareness activities implementedValue01. Public participation was conducted for all projPublic awareness activities initiated
    DateDecember 31, 2014November 30, 2023
    Comment
  • 10. Number of people positively affected by site cleanupsValue0191,575750
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 7. Feasibility Study for Knowledge and Remediation Center in Chongqing preparedValueNo feasibility study100% completed.
    DateJanuary 1, 2015November 30, 2023
    Comment
  • - Of which femaleValue095,787
    DateJanuary 1, 2015November 30, 2023
    Comment
  • 8. Regional Soil and Groundwater Contamination Prevention and Warning System at the Changshou Industrial Park establishedValueNo warning system100% Completed - Warning system established and fu
    DateJanuary 1, 2015November 30, 2023
    Comment
  • Information platform for contaminated site management and redevelopment at the local levelValueNo related information platform in Tongzhou DistriPlatform established and functional
    DateJanuary 1, 2015November 30, 2023
    Comment