Skip to Main Navigation

NATURAL RESOURCES MANAGEMENT IN A CHANGING CLIMATE IN MALI

Abstract*

The objective of the Natural Resources Management in a Changing Climate Project is to expand the adoption of sustainable land and water management practices in the target area in Mali. There are four components to the project, the first component being Knowledge management, Governance and Communication. The second component is the Scaling-up Sustainable land management practices. Through knowledge consolidation or creation and dissemination, promotion...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to expand the adoption of sustainable land and water management practices in the target area in Mali.

Key Details

Project Details

  • P145799

  • Closed

  • Emeran Menang Evouna , Mirko Serkovic

  • Ministry of Environment and Sanitation

  • Mali

  • September 20, 2013

  • (as of board presentation)

    December 6, 2013

  • March 24, 2014

  • US$ 13.00 million

  • Agence de l'Environnement et du Developpement Durable - AEDD

  • Western and Central Africa

  • 2014

  • US$ 12.00 million

  • B

  • June 4, 2024

  • September 30, 2019

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GLOBAL ENVIRONMENT - Associated IDA Fund 12.00
Borrower/Recipient 2.00
IDA Grant 12.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 12.00
IBRD + IDA Commitment 12.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 13.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 12, 2017 IDA-H8900 Loan Disb 98,472.18
Dec 6, 2013 IDA-H8900 Loan Commitment 12,000,000.00
Nov 17, 2015 IDA-H8900 Loan Disb 35,564.58
Jun 8, 2015 IDA-H8900 Loan Disb 129,349.58
Jun 8, 2015 IDA-H8900 Loan Disb 55,101.01
Apr 30, 2018 IDA-H8900 Loan Disb 367,057.16
Apr 18, 2018 IDA-H8900 Loan Disb 176,589.44
Apr 9, 2018 IDA-H8900 Loan Disb 152,199.19
Jun 6, 2017 IDA-H8900 Loan Disb 556,628.75
Jun 23, 2017 IDA-H8900 Loan Disb 96,254.46
Jun 23, 2017 IDA-H8900 Loan Disb 621,104.75
May 3, 2017 IDA-H8900 Loan Disb 148,904.80
Apr 25, 2017 IDA-H8900 Loan Disb 248,555.62
Jun 1, 2017 IDA-H8900 Loan Disb 236,886.55
Apr 25, 2017 IDA-H8900 Loan Disb 225,904.77
Dec 27, 2016 IDA-H8900 Loan Disb 143,060.10
Aug 9, 2016 IDA-H8900 Loan Disb 102,221.84
Oct 20, 2016 IDA-H8900 Loan Disb 9,321.51
Dec 1, 2016 IDA-H8900 Loan Disb 320,135.30
Jun 24, 2016 IDA-H8900 Loan Disb 99,166.85
Sep 21, 2016 IDA-H8900 Loan Disb 245,930.08
Aug 19, 2016 IDA-H8900 Loan Disb 26,690.42
Jan 6, 2017 IDA-H8900 Loan Disb 281,088.06
Jan 25, 2016 IDA-H8900 Loan Disb 4,556.45
Nov 4, 2015 IDA-H8900 Loan Disb 10,374.31
Feb 1, 2016 IDA-H8900 Loan Disb 16,161.18
Dec 7, 2015 IDA-H8900 Loan Disb 45,868.25
Feb 19, 2016 IDA-H8900 Loan Disb 54,451.92
Feb 19, 2016 IDA-H8900 Loan Disb 87,074.55
Apr 7, 2016 IDA-H8900 Loan Disb 521,467.06
Apr 6, 2016 IDA-H8900 Loan Disb 103,521.86
Jun 15, 2016 IDA-H8900 Loan Disb 623,079.56
Jun 30, 2014 IDA-H8900 Loan Disb 416,201.06
Jun 5, 2015 IDA-H8900 Loan Disb 100,800.51
May 11, 2015 IDA-H8900 Loan Disb 67,490.24
Apr 13, 2015 IDA-H8900 Loan Disb 160,838.02
May 7, 2015 IDA-H8900 Loan Disb 107,329.36
Nov 17, 2015 IDA-H8900 Loan Disb 47,802.47
Nov 17, 2015 IDA-H8900 Loan Disb 23,256.79
Mar 27, 2020 IDA-H8900 Loan Cancel 121,691.86
Jul 31, 2019 IDA-H8900 Loan Disb 226,716.53
Jul 31, 2019 IDA-H8900 Loan Disb 368,557.78
Mar 24, 2020 IDA-H8900 Loan Disb -98,959.73
Mar 27, 2020 IDA-H8900 Loan Disb -388.40
Mar 22, 2019 IDA-H8900 Loan Disb 123,279.87
Aug 21, 2019 IDA-H8900 Loan Disb 185,969.94
Dec 7, 2017 IDA-H8900 Loan Disb 92,533.25
Jan 16, 2018 IDA-H8900 Loan Disb 292,257.40
Jun 11, 2018 IDA-H8900 Loan Disb 76,169.87
May 9, 2018 IDA-H8900 Loan Disb 374,683.72
Jun 21, 2018 IDA-H8900 Loan Disb 279,656.88
Aug 23, 2018 IDA-H8900 Loan Disb 259,397.16
Nov 21, 2018 IDA-H8900 Loan Disb 245,091.31
Jan 9, 2019 IDA-H8900 Loan Disb 111,656.32
Jan 23, 2019 IDA-H8900 Loan Disb 170,208.77
Oct 2, 2018 IDA-H8900 Loan Disb 207,179.66
Oct 5, 2018 IDA-H8900 Loan Disb 301,028.44
Oct 25, 2018 IDA-H8900 Loan Disb 99,883.81
Feb 28, 2019 IDA-H8900 Loan Disb 129,454.09
Aug 23, 2017 IDA-H8900 Loan Disb 105,076.27
Oct 2, 2017 IDA-H8900 Loan Disb 83,273.95
Feb 14, 2018 IDA-H8900 Loan Disb 282,343.12
Jan 24, 2018 IDA-H8900 Loan Disb 47,729.47
Jan 24, 2018 IDA-H8900 Loan Disb 32,566.86
Jan 24, 2018 IDA-H8900 Loan Disb 47,669.22
Jan 24, 2018 IDA-H8900 Loan Disb 143,482.84

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-03-18
Monitoring and Evaluation Satisfactory 2020-03-18
Overall Implementation Progress (IP) Satisfactory 2020-03-18
Procurement Moderately Satisfactory 2020-03-18
Financial Management Moderately Satisfactory 2020-03-18
Counterpart Funding Satisfactory 2020-03-18
Project Management Satisfactory 2020-03-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-15-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-30-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land area under sustainable land and water management practices in targeted areasValue0.003667.003000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Changes (increase) in vegetation cover in targeted areas, compared to baselineValue0.001.300.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Direct project beneficiariesValue0.0018332.0015000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Female beneficiariesValue0.0068.010.00
    DateOctober 18, 2013January 16, 2018
    Comment
  • Households with access to alternative livelihood activities related to sustainable land and water management practices supported bythe projectValue0.002708.002000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Land users adopting sustainable land management practices as a result of the project ( LDCF,LD3)Value0.001652.001600.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total vegetative land areas created / rehabilitated by local communities (BD2, CCM5, SFM1)Value0.002450.001600.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Messages on SLWM and adaptation to CC disseminated through accessible mediaValue0.0017435.0015000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Safeguard instruments (ESMF, PMP, RPF and PF) are implemented in a satisfactory manner)ValueYesYes
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Number of Communes which Development Plan (PDSEC) integrate SLWM and adaptation to CC issuesValue0.0014.000.00
    DateOctober 18, 2013September 30, 2019
    Comment
  • Effectiveness of biodiversity management in targeted areas (BD2)Value41.0048.000.00
    DateOctober 18, 2013September 30, 2019
    Comment
  • Alternative livelihood activities supported by the project which those benefitting female and other vulnerable groups (percentage)(LDCF, SFM, CCM5, BD2)Value0.00658.00500.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Technical and financial management progress reports are prepared and timely submittedValueYesYes
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Number of Local conventions or any other Agreements on SLWM and NRM approved, disseminated and implementedValue0.0015.000.00
    DateOctober 18, 2013September 30, 2019
    Comment
  • Govt institutions provided w/ capacity buildg to improve mgt of forest resourcesValue0.003.000.00
    DateOctober 18, 2013September 30, 2019
    Comment
  • Number of sensitization sessions organized on climate hazards and adaptation options( number of radio messages)Value0.009976.0010000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Pastoral corridor management plans developed in participatory manner (#)Value0.0014.0014.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Number of dissemination sessions on SLWM, NRM and climate risks held with producer organizationsValue0.0057.0050.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Lands under SLWM practices (Farmlands, rangelands) - SFM1, LD3, and LDCFValue0.000.000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment
  • Land users adopting sustainable land mgt. practices as a result of the projectValue0.000.000.00
    DateOctober 18, 2013September 30, 2019September 30, 2019
    Comment