Mocha Wind Park Project

Abstract*

The development objective of the Mocha Wind Park Project for Yemen is to increase the supply of cost-effective renewable wind electricity. The project has two components. The first component physical investment will support the construction of a wind farm at Mocha of approximately 60 megawatt (MW) generation capacity. This component will initially be implemented by a project management unit (PMU) established under the Ministry of Electricity and Energy...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the Project is to increase the supply of cost-effective renewable wind electricity.

Key Details

Project Details

  • P146055

  • Closed

  • Joern Huenteler

  • Ministry of Planning and International Cooperation

  • Yemen, Republic of

  • October 17, 2013

  • (as of board presentation)

    March 7, 2014

  • August 21, 2014

  • US$ 125.00 million

  • B

  • Not Applicable

  • January 17, 2017

  • Yes

  • BANK APPROVED

  • October 18, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
SAUDI ARABIA: Saudi Fund for Development 20.00
IDA Grant 20.00
OPEC FUND 20.00
Arab Fund for Economic and Social Development 65.00
Borrower/Recipient 19.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount 105.00
Total Project Cost** 144.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 29, 2016 IDA-H9180 Loan Cancel 17,421,170.00
Mar 7, 2014 IDA-H9180 Loan Commitment 20,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2017-01-04
Counterpart Funding Unsatisfactory 2017-01-04
Financial Management Moderately Unsatisfactory 2017-01-04
Procurement Moderately Unsatisfactory 2017-01-04
Monitoring and Evaluation Unsatisfactory 2017-01-04
Project Management Unsatisfactory 2017-01-04
Overall Implementation Progress (IP) Moderately Unsatisfactory 2017-01-04

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.000.00920000.00
    DateMarch 1, 2014December 22, 2016December 31, 2018
    Comment
  • Generation Capacity of Renewable Energy (other than hydropower) constructedValue0.000.0060.00
    DateMarch 1, 2014December 22, 2016December 31, 2017
    Comment
  • Female beneficiariesValue0.000.00460000.00
    DateMarch 1, 2014December 22, 2016December 31, 2018
    Comment
  • Generation Capacity of Renewable Energy constructed – WindValue0.000.0060.00
    DateMarch 1, 2014December 22, 2016December 31, 2017
    Comment
  • Economic Competitiveness of electricity generated by wind powerValue0.200.000.12
    DateMarch 1, 2014December 22, 2016March 1, 2018
    Comment
  • Electricity generated from wind powerValue0.000.00180.00
    DateMarch 1, 2014December 22, 2016December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Progress in procuring engineering consultantValueNoNoYes
    DateMarch 3, 2014December 22, 2016June 30, 2019
    Comment
  • Procurement ProgressValue0.000.00100.00
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • Construction ProgressValue0.000.00100.00
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • SPC created and operationalValueNoNoYes
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • Wind capacity AvailabilityValue0.000.0097.00
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • Number of Staff trainedValue0.000.030 Man-month
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • Wind Measurement masts installedValue0.000.003.00
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment
  • Consulting services for market development performedValueNoNoYes
    DateMarch 1, 2014December 22, 2016June 30, 2019
    Comment