Development Objective

The Project Development Objective is to strengthen the management of national water resources and increase the yield from Corumana dam to augment water supply for the Greater Maputo Metropolitan Area.

Key Details

Project Details

  • P146098

  • Closed

  • Shelley Mcmillan

  • N/A

  • Mozambique

  • September 27, 2013

  • (as of board presentation)

    September 27, 2013

  • N/A

  • US$ 32.00 million

  • A

  • Not Applicable

  • June 30, 2020

  • Yes

  • BANK APPROVED

  • P107350

  • August 23, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit from CRW 32.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 32.00
IBRD + IDA Commitment 32.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 32.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Incremental reservoir yield available from Corumana Dam for GMMAValue0016800000
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Improved Safety monitoring systtem for Corumana dam functionningValueNoNoYes
    DateJanuary 31, 2012August 15, 2013December 15, 2015
    Comment
  • Dykes and levees rehabilitated to withstand 1:50 year flooding in the limpopo and Incomati river BasinsValue0.000.0075.00
    DateAugust 15, 2013December 31, 2017
    Comment
  • Storage capacity Corumana DamValue720000000.00720000000.001240000000.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Macarretane barrage on the Limpopo River has functioning hydro-mechanical works, gate control system, and reinforced foundationsValueNoYes
    DateAugust 15, 2013December 31, 2017
    CommentComment
  • Water Licence for Maputo Water Suplly GrantedValueNoNoYes
    DateJanuary 31, 2012August 15, 2013December 15, 2015
    Comment
  • % of the river basins covered by water resources management plansValue5.005.0019.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • % of hydro-climatic stations operational and reportingValue150.00150.00325.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Environmental management plan audited annuallyValueNoNoYes
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Female beneficiariesValue0.000.00813267.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Flood management studies integrating infrastructure planning applied in government decision makingValueNoNoYes
    DateJanuary 31, 2012August 15, 2013December 15, 2015
    CommentLack of studies developed and appliedStudies inform decision making.
  • Hydro-met stations in Limpopo and Incomati River basins upgraded to monitor extreme eventsValueNoNoYes
    DateJanuary 31, 2012October 2, 2012December 15, 2015
    Comment
  • Direct project beneficiariesValue0.000.001452000.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    CommentCurrently, only a handful of hydro-met stations have the capacity to monitor extreme events
  • OLD Version of Indicator: People in project areas with access to Improved Water SourcesValue0.00435.00435.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Number of agreements for international waterways reviewed and updatedValue0.001.001.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Improved cost recovery of ARAsValue1.401.401.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    Comment
  • Integrated Flood Management Decision Support System operating for southern Mozambique (Limpopo and Incomati River basins).Value0.000.001.00
    DateJanuary 31, 2012August 15, 2013December 15, 2017
    CommentLack of integrated flood management decision support systemOperating effectively in wet season
  • # of people provided with improved sanitationValue0.000.00435.00
    DateJanuary 31, 2012August 15, 2013December 31, 2017
    Comment
  • Investment studies for additional dam projects completedValue0.000.005.00
    DateJanuary 31, 2012August 15, 2013December 31, 2017
    Comment
  • National water storage capacityValue77474.0077474.0078594.00
    DateJanuary 31, 2012August 15, 2013December 31, 2017
    Comment
  • Number of other water service providers that the project is supportingValue1.001.003.00
    DateJanuary 31, 2012August 15, 2013December 31, 2017
    Comment