<p>The PDO is to support the improvement of service delivery in schools, health centers and communes, for rural households in selected districts. This will be achieved by local government and service providers engaging with communities in the ISAF process (access toinformation, open budgets, citizen monitoring) to improve performance and responsiveness.</p>

Key Details

Project Details

  • P146160

  • Closed

  • Erik Johnson

  • Save the Children, International,World Vision International

  • Cambodia

  • December 15, 2014

  • (as of board presentation)

    September 1, 2015

  • November 20, 2015

  • US$ 4.90 million

  • Save the Children, Cambodia,World Vision International

  • East Asia and Pacific

  • 2016

  • US$ 4.90 million

  • C

  • September 8, 2022

  • March 31, 2019

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Japan Social Development Fund 4.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 4.90
Total Project Cost** 4.90

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2018-08-15
Overall Low 2018-08-15
Overall Implementation Progress (IP) Satisfactory 2018-08-15

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved performance of primary schoolsValue24.100.0033.90
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Improved performance of health centersValue46.600.0056.70
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Improved performance of commune councilsValue56.200.0062.00
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Increased participation of citizens in the activities of local public service providersValue30.200.0028.30
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Increased voice of citizens in their engagement with service providersValue24.200.0023.30
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Increased participation of female citizens in the activities of local public service providers (female)Value27.800.0025.40
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment
  • Increased voice of female citizens in their engagement with service providers (female)Value13.700.0014.30
    DateFebruary 28, 2017February 28, 2019March 29, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of citizens participating in SAF process able to cite standards for school, health center or commune services (information awareness)Value0.0050.0064.00
    DateDecember 31, 2015March 29, 2019March 9, 2018
    Comment
  • % of citizens participating in SAF process able to cite expenditure changes/patterns for school, health center and commune budgets (budget awareness)Value0.0020.0066.00
    DateJune 30, 2015March 29, 2019March 9, 2018
    Comment
  • % of local NGO staff in target districts demonstrating capacity to facilitate SAF (capacity building)Value0.0075.0041.00
    DateJune 30, 2015March 29, 2019March 9, 2018
    Comment
  • % of Community Accountability Facilitators (CAFs) (women/men) demonstrating capacity to facilitate SAF. (capacity building)Value0.0075.0070.00
    DateJune 30, 2015March 29, 2019March 9, 2018
    Comment
  • Percentage of JAAP actions completed or ongoingValue0.0065.0067.00
    DateNovember 2, 2015March 29, 2019March 9, 2018
    Comment
  • Stages reached in the execution of the M&E plan.Value1.004.003.00
    DateOctober 30, 2015March 29, 2019July 27, 2018
    Comment