Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 42.00 |
P146460
Closed
Emanuela Monteiro , Silpa Kaza
JAMAICA
September 20, 2013
(as of board presentation)
March 14, 2014
August 11, 2014
US$ 42.00 million
Jamaica Social Investment Fund
2014
US$ 42.00 million
B
October 28, 2021
May 1, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 42.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 42.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 42.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 42.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IBRD-83560 | Int Charges | 1,117,862.50 |
Aug 15, 2024 | IBRD-83560 | Loan Repay | 871,457.20 |
Feb 15, 2024 | IBRD-83560 | Loan Repay | 871,457.20 |
Feb 15, 2024 | IBRD-83560 | Int Charges | 10,410.27 |
Feb 15, 2024 | IBRD-83560 | Int Charges | 1,143,049.40 |
Mar 14, 2014 | IBRD-83560 | Loan Commitment | 42,000,000.00 |
Feb 15, 2023 | IBRD-83560 | Int Charges | 60,626.91 |
Feb 15, 2023 | IBRD-83560 | Int Charges | 845,633.70 |
Feb 15, 2023 | IBRD-83560 | Loan Repay | 871,457.20 |
Aug 15, 2023 | IBRD-83560 | Loan Repay | 871,457.20 |
Aug 15, 2023 | IBRD-83560 | Int Charges | 38,452.56 |
Aug 15, 2023 | IBRD-83560 | Int Charges | 1,013,032.06 |
Feb 15, 2022 | IBRD-83560 | Int Charges | -408.95 |
Feb 15, 2022 | IBRD-83560 | Int Charges | -160,962.20 |
Apr 21, 2017 | IBRD-83560 | Loan Disb | 110,483.87 |
May 16, 2017 | IBRD-83560 | Loan Disb | 1,746,401.00 |
Nov 20, 2017 | IBRD-83560 | Loan Disb | 1,508,923.00 |
Jul 18, 2017 | IBRD-83560 | Loan Disb | 1,597,983.80 |
Aug 15, 2017 | IBRD-83560 | Int Charges | 258.17 |
Aug 15, 2017 | IBRD-83560 | Int Charges | 62,569.25 |
Feb 8, 2018 | IBRD-83560 | Loan Disb | 1,237,651.00 |
Oct 30, 2014 | IBRD-83560 | Loan Disb | 500,000.00 |
Aug 11, 2014 | IBRD-83560 | Loan Disb | 105,000.00 |
Aug 11, 2014 | IBRD-83560 | Fee Charges | 105,000.00 |
Feb 15, 2015 | IBRD-83560 | Int Charges | 9.21 |
Feb 15, 2015 | IBRD-83560 | Int Charges | 1,690.44 |
Jul 17, 2015 | IBRD-83560 | Loan Disb | 403,441.30 |
Aug 15, 2015 | IBRD-83560 | Int Charges | 2,768.02 |
Nov 23, 2015 | IBRD-83560 | Loan Disb | 1,349,114.00 |
Feb 15, 2016 | IBRD-83560 | Int Charges | 295.76 |
Feb 15, 2016 | IBRD-83560 | Int Charges | 8,883.33 |
Aug 15, 2016 | IBRD-83560 | Int Charges | 22,033.78 |
May 13, 2016 | IBRD-83560 | Loan Disb | 1,336,395.20 |
Aug 15, 2019 | IBRD-83560 | Int Charges | 10,234.58 |
Aug 15, 2019 | IBRD-83560 | Int Charges | 423,158.70 |
Nov 18, 2019 | IBRD-83560 | Loan Disb | 4,000,000.00 |
Aug 15, 2018 | IBRD-83560 | Int Charges | 507.77 |
Aug 15, 2018 | IBRD-83560 | Int Charges | 190,743.45 |
Oct 1, 2018 | IBRD-83560 | Loan Disb | 2,500,000.00 |
Jan 11, 2019 | IBRD-83560 | Loan Disb | 3,300,000.00 |
Feb 15, 2019 | IBRD-83560 | Int Charges | 292,637.72 |
Jul 16, 2019 | IBRD-83560 | Loan Disb | 7,000,000.00 |
Apr 26, 2018 | IBRD-83560 | Loan Disb | 3,826,067.80 |
Feb 15, 2018 | IBRD-83560 | Int Charges | 103,188.55 |
Feb 15, 2018 | IBRD-83560 | Int Charges | 2,460.90 |
Aug 20, 2018 | IBRD-83560 | Loan Disb | 677,888.00 |
Feb 2, 2017 | IBRD-83560 | Loan Disb | 395,000.00 |
Nov 17, 2016 | IBRD-83560 | Loan Disb | 1,000,000.00 |
Mar 24, 2017 | IBRD-83560 | Loan Disb | 311,000.00 |
Feb 15, 2017 | IBRD-83560 | Int Charges | 38,698.14 |
Jun 3, 2020 | IBRD-83560 | Loan Disb | 1,700,000.00 |
Aug 15, 2020 | IBRD-83560 | Int Charges | 448,337.75 |
Aug 15, 2020 | IBRD-83560 | Loan Repay | 809,745.00 |
Oct 2, 2020 | IBRD-83560 | Loan Disb | 2,070,325.20 |
Feb 15, 2020 | IBRD-83560 | Int Charges | 20,066.68 |
Feb 15, 2020 | IBRD-83560 | Int Charges | 488,414.80 |
Feb 15, 2020 | IBRD-83560 | Loan Repay | 773,705.00 |
Apr 29, 2019 | IBRD-83560 | Loan Disb | 4,292,008.00 |
Feb 14, 2022 | IBRD-83560 | Loan Disb | -161,371.16 |
Feb 15, 2022 | IBRD-83560 | Int Charges | 160,962.20 |
Feb 15, 2022 | IBRD-83560 | Int Charges | 408.95 |
Aug 15, 2022 | IBRD-83560 | Int Charges | 259,169.44 |
Aug 15, 2022 | IBRD-83560 | Loan Repay | 871,457.20 |
Aug 15, 2021 | IBRD-83560 | Int Charges | 44.55 |
Aug 15, 2021 | IBRD-83560 | Int Charges | 180,383.08 |
Aug 15, 2021 | IBRD-83560 | Loan Repay | 855,740.75 |
Aug 31, 2021 | IBRD-83560 | Loan Disb | 200,000.00 |
Mar 11, 2022 | IBRD-83560 | Loan Disb | -2,157.41 |
Mar 11, 2022 | IBRD-83560 | Loan Cancel | 288,089.53 |
Feb 15, 2022 | IBRD-83560 | Int Charges | 408.95 |
Feb 15, 2022 | IBRD-83560 | Int Charges | 160,962.20 |
Feb 15, 2022 | IBRD-83560 | Int Charges | 14,461.98 |
Feb 15, 2022 | IBRD-83560 | Loan Repay | 875,253.06 |
Feb 15, 2021 | IBRD-83560 | Loan Repay | 854,671.06 |
Feb 15, 2021 | IBRD-83560 | Int Charges | 206,478.20 |
Jan 14, 2021 | IBRD-83560 | Loan Disb | 48,181.78 |
Jul 22, 2021 | IBRD-83560 | Loan Disb | 659,575.06 |
Aug 15, 2024 | IBRD-83560 | Int Charges | 6,419.10 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2021-04-30 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-04-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-04-30 |
Procurement | Satisfactory | 2021-04-30 |
Project Management | Satisfactory | 2021-04-30 |
Financial Management | Satisfactory | 2021-04-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-29-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased access to quality services and improved basic infrastructure for residents in project areas | Value | 0.00 | 89000.00 | 89000.00 |
Date | April 14, 2014 | May 1, 2021 | February 4, 2020 | |
Comment |
Increased perception of public safety for residents in project areas | Value | 0.00 | 75.58 | 0.00 |
Date | February 6, 2016 | May 1, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Persons who obtained civil registration documents | Value | 0.00 | 6917.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Requests for Crime Observatory data for research, planning, decision-making and service delivery | Value | 20.00 | 291.00 | 254.00 |
Date | April 14, 2014 | May 1, 2021 | February 4, 2020 | |
Comment |
Local government employees and CBOs trained in project related urban management, and public safety | Value | 0.00 | 279.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Number of people in urban areas provided with access to regular solid waste collection under the project | Value | 0.00 | 89000.00 | 71000.00 |
Date | August 14, 2014 | May 1, 2021 | February 4, 2020 | |
Comment |
Persons who participated in educational programs | Value | 0.00 | 13795.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Solid waste skips installed in communities | Value | 0.00 | 55.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Persons who participated in employment programs or activities | Value | 0.00 | 7514.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
People with access to electricity by legal household connections | Value | 9131.00 | 12335.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Persons who obtained formal certifications relating to skills development | Value | 0.00 | 1124.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Number of community mediators certified by the project | Value | 0.00 | 19.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Paved road surfaces and rehabilitated/ constructed drainage | Value | 0.00 | 47.40 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Number of schools indicating capacity for reporting on critical incidents | Value | 0.00 | 3.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Schools with rehabilitated facilities | Value | 0.00 | 17.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
Households with zinc fence replaced with permanent fencing | Value | 0.00 | 3072.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
People provided with access to improved water sources | Value | 0.00 | 13004.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |
People provided with access to improved sanitation services | Value | 0.00 | 1384.00 | 0.00 |
Date | April 14, 2014 | May 1, 2021 | ||
Comment |