Community Development and Safety Nets Project Additional Financing

Development Objective

The proposed Project Development Objective is to provide poor communities with greater access to basic socio-economic infrastructures and social safety nets.

Key Details

Project Details

  • P146598

  • Closed

  • Gbetoho Boko

  • N/A

  • Togo

  • December 24, 2013

  • (as of board presentation)

    March 7, 2014

  • N/A

  • US$ 12.10 million

  • B

  • Not Applicable

  • July 31, 2017

  • Yes

  • BANK APPROVED

  • P127200

  • January 17, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 12.10
Borrower/Recipient 2.10

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 12.10
IBRD + IDA Commitment 12.10
Lending Instrument
Grant Amount N/A
Total Project Cost** 14.20

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries from LIPWValue0.000.003340.00
    DateJuly 15, 2012August 10, 2012December 31, 2015
    Comment
  • Beneficiaries receiving assistance for income generating activitiesValue750.000.002250.00
    DateDecember 31, 2012August 10, 2012December 31, 2015
    Comment
  • Beneficiaries of Safety Nets programs (number)Value0.003474.0053000.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto align original indicator with the Bank's core indicator
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value0.000.008000.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentIncludes JSDF financing. Indicator revised to align original indicator with the Bank's core indicator
  • Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)Value0.003474.0010000.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto align original indicator with the Bank's core indicator
  • Beneficiaries of Safety Nets programs – School feeding programs (number)Value0.000.0035000.00
    DateNovember 20, 2013December 1, 2013September 30, 2016
    Commentnew component under Additional Financing
  • Beneficiaries of Labor Market programs (number)Value0.001506.002250.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto align original indicator with the Bank's core indicator
  • Beneficiaries of Labor Market programs - Supporting entrepreneurship (number)Value0.001506.002250.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto align original indicators with the Bank's core indicators
  • Direct project beneficiariesValue0.0016180.00125250.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Comment
  • Community subprojects operating one year after completionValue0.000.0080.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto reflect new closing date
  • Households receiving cash transfers on scheduleValue0.000.0070.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto reflect new closing date
  • Female beneficiariesValue0.000.0050.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Comment
  • Students enrolled in rehabilited/constructed schoolsValue0.004450.0030000.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentCalculated on the basis of the following assumptions: 320 infrastructures built of which 50% are schools, 3 classrooms per schooland 50 students per classroom, 33% student turnover in classrooms built per year
  • Beneficiaries with access to an improved water sourceValue0.006750.0040000.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentCalculated on the basis of the following assumptions: 320 infrastructures built of which 50 are water, and about 800 beneficiariesper water source
  • Beneficiaries receiving cash transfersValue0.000.003000.00
    DateJuly 15, 2012August 10, 2012December 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Classrooms built or rehabilitatedValue0.000.000.00
    DateJuly 15, 2012August 10, 2012December 31, 2015
    Comment
  • health facilities constructed/renovated and/or equipedValue0.000.000.00
    DateJuly 15, 2012August 10, 2012December 31, 2015
    Comment
  • Improved community water points constructed or rehabilitatedValue0.000.000.00
    DateJuly 15, 2012August 10, 2012December 31, 2015
    Comment
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.Value0.0089.00500.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentRevised to align original indicator with the Bank's core indicator and to provide target value which was missing from originalPAD.Calculated on the basis of the following assumptions: 320 infrastructures built of which 52% are schools, 3 classrooms perschool
  • Improved community water points constructed or rehabilitated under the projectValue0.009.0050.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentRevised to align original indicator with the Bank's core indicator and to provide target value which was missing from originalPAD.Calculated on the basis of the following assumptions: 320 subprojects of which 16% are water points
  • Health facilities constructed, renovated, and/or equipped (number)Value0.003.0020.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentRevised to align original indicator with the Bank's core indicator and to provide target value which was missing from originalPAD.Calculated on the basis of the following assumptions: 320 subprojects, of which about 6% are health facilities
  • Meals provided to students in schools targeted for school feedingValue0.000.0012000000.00
    DateDecember 1, 2013December 1, 2013September 30, 2016
    Comment
  • Schools benefitting from school feeding programValue0.000.00150.00
    DateDecember 1, 2013December 1, 2013September 30, 2016
    Comment
  • Percent of schools benefitting from school feeding that are in the poorest 20% of cantons in their region (excluding schools in villages targeted by the Impact Evaluation)Value0.000.0090.00
    DateDecember 1, 2013December 1, 2013September 30, 2016
    Comment
  • Person days of work provided through this projectValue0.00138960.00133600.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    Comment
  • Female participation in labor intensive public worksValue0.004985.0040.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    Comment
  • Young people (aged less than 35) employedValue0.0059.8170.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    Comment
  • Registered households who are receiving the cash transfersValue0.000.00100.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto reflect new closing date
  • Public works schemes completed with satisfactory technical qualityValue80.000.0090.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    Comment
  • Communal infrastructures rehabilitated through the public worksValue0.0042.000.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    CommentTBC
  • Basic socio economic infrastructure built/rehabilitated/maintainedValue0.0038.00320.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    CommentEstimated based on assumptions of average cost of sub-projects
  • Basic socio economic infrastructure assessed as having satisfactory technical qualityValue0.000.0080.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto reflect new closing date
  • Income generating activities subprojectsValue0.0057.00150.00
    DateJuly 15, 2012December 1, 2013December 31, 2015
    Comment
  • Beneficiaries complying with the requirements to participate in soft conditionsValue0.000.0095.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentto reflect new closing date
  • Maximum percentage of project funds used for project managementValue17.000.0017.00
    DateJuly 15, 2012December 1, 2013September 30, 2016
    Commentreduced in light of economies of scale due to additional financing