Uttar Pradesh Pro-Poor Tourism Development Project

Abstract*

The development objective of the Uttar Pradesh Pro-Poor Tourism Development Project for India is to increase tourism‐related benefits for local communities in targeted destinations. The project comprises of four components. The first component, destination planning and governance aims to test new approaches and establish the institutional structures, policies, and coordination mechanisms necessary for bringing together the public and private sectors...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to increase tourism-related benefits for local communities in targeted destinations

Key Details

Project Details

  • P146936

  • Closed

  • Stefania Abakerli B

  • State Government of Uttar Pradesh

  • India

  • November 4, 2014

  • (as of board presentation)

    December 20, 2017

  • March 15, 2018

  • US$ 57.14 million

  • Department of Tourism, Government of Uttar Pradesh

  • South Asia

  • 2018

  • US$ 40.00 million

  • B

  • Not Applicable

  • March 31, 2024

  • Yes

  • BANK APPROVED

  • May 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00
Borrower/Recipient 17.14

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 57.14

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 6, 2023 IBRD-88110 Loan Disb 2,076,486.20
Dec 15, 2023 IBRD-88110 Int Charges 22,206.65
Dec 15, 2023 IBRD-88110 Int Charges 529,222.00
Dec 15, 2023 IBRD-88110 Loan Repay 658,047.30
Oct 21, 2022 IBRD-88110 Loan Disb 1,936,751.60
Dec 15, 2022 IBRD-88110 Int Charges 106.62
Dec 15, 2022 IBRD-88110 Int Charges 338.78
Dec 15, 2022 IBRD-88110 Int Charges 27,289.89
Dec 15, 2022 IBRD-88110 Int Charges 24,905.11
Dec 15, 2022 IBRD-88110 Int Charges 217,951.80
Jan 31, 2023 IBRD-88110 Loan Disb 348,032.03
Feb 15, 2023 IBRD-88110 Loan Disb 838,838.25
Jun 15, 2024 IBRD-88110 Int Charges 127.99
Jun 15, 2024 IBRD-88110 Int Charges 14,721.80
Jun 15, 2024 IBRD-88110 Int Charges 6,444.19
Jun 15, 2024 IBRD-88110 Int Charges 718,488.20
Jun 15, 2024 IBRD-88110 Loan Repay 950,144.50
Aug 6, 2024 IBRD-88110 Loan Disb 2,040,503.10
Jul 31, 2024 IBRD-88110 Loan Disb 1,791,106.50
Dec 20, 2017 IBRD-88110 Loan Commitment 40,000,000.00
May 2, 2024 IBRD-88110 Loan Disb 2,538,847.00
Jan 25, 2024 IBRD-88110 Loan Disb 2,570,376.80
Mar 22, 2024 IBRD-88110 Loan Disb 2,655,566.20
Jul 31, 2023 IBRD-88110 Loan Disb 519,377.84
Jun 15, 2023 IBRD-88110 Int Charges 729.61
Jun 15, 2023 IBRD-88110 Loan Repay 603,842.06
Mar 15, 2018 IBRD-88110 Loan Disb 100,000.00
Mar 15, 2018 IBRD-88110 Fee Charges 100,000.00
Apr 16, 2018 IBRD-88110 Loan Disb 432,797.94
May 1, 2018 IBRD-88110 Loan Disb 711,255.06
Jun 15, 2018 IBRD-88110 Int Charges 29,402.92
Jun 15, 2018 IBRD-88110 Int Charges 618.45
May 1, 2019 IBRD-88110 Loan Disb 1,362,653.50
Jun 15, 2019 IBRD-88110 Int Charges 1,234.87
Jun 15, 2019 IBRD-88110 Int Charges 45,704.90
Jun 15, 2019 IBRD-88110 Int Charges 54,425.05
Jun 15, 2019 IBRD-88110 Int Charges 104.15
Dec 2, 2019 IBRD-88110 Loan Disb 362,289.70
Aug 8, 2018 IBRD-88110 Loan Disb 586,289.00
Jan 31, 2019 IBRD-88110 Loan Disb 868,229.40
Dec 15, 2018 IBRD-88110 Int Charges 31,741.33
Dec 15, 2018 IBRD-88110 Int Charges 26,706.61
Dec 15, 2018 IBRD-88110 Int Charges 3,500.07
Nov 16, 2018 IBRD-88110 Loan Disb 524,359.25
Dec 15, 2018 IBRD-88110 Int Charges 397.09
Dec 15, 2018 IBRD-88110 Int Charges 16,159.14
Dec 15, 2018 IBRD-88110 Int Charges 55.00
Jun 15, 2020 IBRD-88110 Int Charges 32.25
Jun 15, 2020 IBRD-88110 Int Charges 362.84
Jun 15, 2020 IBRD-88110 Int Charges 42,674.34
Jun 15, 2020 IBRD-88110 Int Charges 73,544.66
Jul 31, 2019 IBRD-88110 Loan Disb 148,072.31
Jun 15, 2021 IBRD-88110 Int Charges 42,663.81
Nov 18, 2020 IBRD-88110 Loan Disb 606,805.06
Aug 7, 2020 IBRD-88110 Loan Disb 510,935.20
Dec 15, 2020 IBRD-88110 Int Charges 3,105.54
Dec 15, 2020 IBRD-88110 Int Charges 40,635.66
Dec 15, 2020 IBRD-88110 Int Charges 41,765.38
Dec 15, 2020 IBRD-88110 Int Charges 327.18
Dec 15, 2019 IBRD-88110 Int Charges 5,694.90
Dec 15, 2019 IBRD-88110 Int Charges 44,218.10
Dec 15, 2019 IBRD-88110 Int Charges 72,098.14
Dec 15, 2019 IBRD-88110 Int Charges 420.00
Feb 5, 2020 IBRD-88110 Loan Disb 714,859.20
May 7, 2020 IBRD-88110 Loan Disb 1,228,162.20
Jun 15, 2021 IBRD-88110 Int Charges 38,602.90
Jun 15, 2021 IBRD-88110 Int Charges 393.25
Aug 18, 2021 IBRD-88110 Loan Disb 638,654.75
Jan 12, 2021 IBRD-88110 Loan Disb 858,527.80
Nov 8, 2021 IBRD-88110 Loan Disb 446,195.56
Jun 15, 2022 IBRD-88110 Int Charges 61,348.30
Jun 15, 2022 IBRD-88110 Int Charges 113.07
Jun 15, 2022 IBRD-88110 Int Charges 290.49
Jun 15, 2022 IBRD-88110 Int Charges 27,227.51
Jun 15, 2021 IBRD-88110 Int Charges 111.92
May 18, 2021 IBRD-88110 Loan Disb 920,176.50
Feb 10, 2022 IBRD-88110 Loan Disb 1,108,203.00
May 20, 2022 IBRD-88110 Loan Disb 598,720.75
Aug 5, 2022 IBRD-88110 Loan Disb 469,246.72
Dec 15, 2021 IBRD-88110 Int Charges 503.44
Dec 15, 2021 IBRD-88110 Int Charges 37,050.06
Dec 15, 2021 IBRD-88110 Int Charges 46,302.19
Dec 15, 2021 IBRD-88110 Int Charges 176.46
Oct 8, 2021 IBRD-88110 Loan Cancel 4,580,000.00
Jun 15, 2023 IBRD-88110 Int Charges 30,639.28
Jun 15, 2023 IBRD-88110 Int Charges 24,106.67
Jun 15, 2023 IBRD-88110 Int Charges 433,359.70
May 18, 2023 IBRD-88110 Loan Disb 892,217.50
Dec 15, 2023 IBRD-88110 Int Charges 171.10
Dec 15, 2023 IBRD-88110 Int Charges 12,480.21

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-04-02
Procurement Moderately Satisfactory 2024-04-02
Progress towards achievement of PDO Satisfactory 2024-04-02
Financial Management Satisfactory 2024-04-02
Monitoring and Evaluation Satisfactory 2024-04-02
Overall Implementation Progress (IP) Moderately Satisfactory 2024-04-02
Counterpart Funding Moderately Satisfactory 2024-04-02

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-23-2024
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-17-2025PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with improved urban living conditionsValue0.0015861.008000.00
    DateSeptember 1, 2015March 29, 2024December 20, 2021
    Comment
  • Individuals, professionals and small businesses in the project destinations with increased annual incomeValue0.003895.002000.00
    DateDecember 12, 2017March 29, 2024December 20, 2021
    Comment
  • Increase in average duration of stay of tourists in project areasValue0.251.580.00
    DateJune 30, 2014March 29, 2024
    Comment
  • Increase in average daily tourist expenditure in project destinations (day tourist)Value6.8015.600.00
    DateJune 30, 2014March 29, 2024
    Comment
  • Number of households in subproject areas with improved conditions (e.g., access to basic services), disaggregated by genderValue0.002919.002000.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment
  • Increase in average daily tourist expenditure in project destinations (overnight tourists)Value13.800.000.00
    DateJune 30, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of subproject areas declared Open Defecation Free (ODF)Value0.003.003.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment
  • Number of jobs created within the tourism value chain, especially for women, in project destinations.Value0.002861.002500.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment
  • Number of community consultations held in project destinationsValue0.009824.004000.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment
  • Number of local entrepreneurs or small businesses in project destinations supported with improved business development capacities, infrastructure and/or tools, disaggregated by gender and ageValue0.007007.002500.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment
  • Increase in numbers of visitors in project destinations (domestic)Value43600000.0059689960.0027000000.00
    DateJune 30, 2014March 29, 2024December 20, 2021
    Comment