Financier | Commitments |
---|---|
IDA Credit | 11.89 |
P147250
Closed
Artessa Saldivar-Sali
Co-operative Republic of Guyana
April 12, 2014
(as of board presentation)
June 4, 2014
November 25, 2014
US$ 11.89 million
Ministry of Agriculture,Agriculture Sector Development Unit (ASDU), Ministry of Agriculture
2014
US$ 11.89 million
B
January 31, 2024
December 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 11.89 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 11.89 |
IBRD + IDA Commitment | 11.89 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 11.89 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 1, 2024 | IDA-67860 | Int Charges | 1,740.92 |
Jun 1, 2024 | IDA-67860 | Int Charges | 1,740.92 |
Mar 11, 2024 | IDA-67860 | Loan Disb | 1,200,496.00 |
Jan 5, 2015 | IDA-54740 | Loan Disb | 3,000.01 |
Apr 29, 2015 | IDA-54740 | Loan Disb | 942,050.00 |
Dec 10, 2015 | IDA-54740 | Loan Disb | 1,715,578.50 |
Dec 1, 2015 | IDA-54740 | Int Charges | 626.38 |
Dec 1, 2015 | IDA-54740 | Int Charges | 626.38 |
Dec 1, 2015 | IDA-54740 | Int Charges | 1,043.97 |
Dec 1, 2015 | IDA-54740 | Int Charges | 3,485.03 |
Jun 1, 2024 | IDA-54740 | Loan Repay | 168,155.77 |
Jun 1, 2024 | IDA-54740 | Int Charges | 32,541.77 |
Jun 1, 2024 | IDA-54740 | Int Charges | 32,541.77 |
Jun 1, 2024 | IDA-54740 | Int Charges | 3,328.41 |
Jun 1, 2024 | IDA-54740 | Int Charges | 54,236.37 |
Jun 1, 2023 | IDA-54740 | Int Charges | 8,105.12 |
Jun 1, 2023 | IDA-54740 | Loan Repay | 168,973.95 |
Jun 1, 2023 | IDA-54740 | Int Charges | 33,967.48 |
Jun 1, 2023 | IDA-54740 | Int Charges | 33,967.48 |
Jun 1, 2023 | IDA-54740 | Int Charges | 56,612.38 |
Dec 1, 2023 | IDA-54740 | Int Charges | 52,301.22 |
Dec 1, 2023 | IDA-54740 | Loan Repay | 3,069.07 |
Dec 1, 2023 | IDA-54740 | Loan Repay | 166,194.56 |
Dec 1, 2023 | IDA-54740 | Int Charges | 33,390.94 |
Dec 1, 2023 | IDA-54740 | Int Charges | 33,390.94 |
Dec 1, 2022 | IDA-54740 | Loan Repay | 6,176.28 |
Dec 1, 2022 | IDA-54740 | Loan Repay | 161,638.97 |
Dec 1, 2022 | IDA-54740 | Int Charges | 34,363.81 |
Dec 1, 2022 | IDA-54740 | Int Charges | 34,363.81 |
Dec 1, 2022 | IDA-54740 | Loan Repay | 0.01 |
Dec 1, 2022 | IDA-54740 | Int Charges | -0.01 |
Dec 1, 2022 | IDA-54740 | Int Charges | -0.01 |
Dec 1, 2022 | IDA-54740 | Int Charges | 49,223.53 |
Jun 1, 2022 | IDA-54740 | Int Charges | 3.56 |
Jun 1, 2022 | IDA-54740 | Int Charges | 3.56 |
Jun 1, 2022 | IDA-54740 | Int Charges | 59,570.58 |
Jun 1, 2022 | IDA-54740 | Int Charges | 5.95 |
Jun 1, 2022 | IDA-54740 | Int Charges | 35,742.36 |
Jun 1, 2022 | IDA-54740 | Int Charges | 35,742.36 |
Dec 1, 2015 | IDA-54740 | Int Charges | 3,485.03 |
Dec 1, 2015 | IDA-54740 | Int Charges | 5,808.38 |
Jun 18, 2024 | IDA-67860 | Loan Disb | 4,933,595.50 |
Jun 1, 2024 | IDA-67860 | Int Charges | 70,259.91 |
Jun 1, 2024 | IDA-67860 | Int Charges | 70,259.91 |
Dec 1, 2023 | IDA-67860 | Int Charges | 55,824.11 |
Dec 1, 2023 | IDA-67860 | Int Charges | 55,824.11 |
Dec 1, 2023 | IDA-67860 | Int Charges | 536.79 |
Dec 1, 2023 | IDA-67860 | Int Charges | 536.79 |
Nov 7, 2023 | IDA-67860 | Loan Disb | 2,000,000.00 |
Jun 22, 2023 | IDA-67860 | Loan Disb | 1,878,554.60 |
Jun 1, 2023 | IDA-67860 | Int Charges | 3,202.15 |
Jun 1, 2023 | IDA-67860 | Int Charges | 3,202.15 |
Jun 1, 2023 | IDA-67860 | Int Charges | 43,613.48 |
Jun 1, 2023 | IDA-67860 | Int Charges | 43,613.48 |
Sep 12, 2023 | IDA-67860 | Loan Disb | 1,518,245.80 |
Feb 3, 2023 | IDA-67860 | Loan Disb | 3,705,680.00 |
Nov 1, 2022 | IDA-67860 | Loan Disb | 4,101,400.00 |
Dec 1, 2022 | IDA-67860 | Int Charges | 16,900.98 |
Dec 1, 2022 | IDA-67860 | Int Charges | 16,900.98 |
Dec 1, 2022 | IDA-67860 | Int Charges | 174.54 |
Dec 1, 2022 | IDA-67860 | Int Charges | 174.54 |
Feb 4, 2022 | IDA-67860 | Loan Disb | 791,314.00 |
Jun 1, 2022 | IDA-67860 | Int Charges | 129.22 |
Jun 8, 2022 | IDA-67860 | Loan Disb | 2,345,200.00 |
Dec 1, 2021 | IDA-67860 | Int Charges | 3,422.11 |
Dec 1, 2021 | IDA-67860 | Int Charges | 3,422.11 |
Jun 1, 2022 | IDA-67860 | Int Charges | 7,408.15 |
Jun 1, 2022 | IDA-67860 | Int Charges | 7,408.15 |
Aug 9, 2022 | IDA-67860 | Loan Disb | 469,985.00 |
Dec 1, 2021 | IDA-67860 | Int Charges | 977.65 |
Dec 1, 2021 | IDA-67860 | Int Charges | 977.65 |
Jun 1, 2022 | IDA-67860 | Int Charges | 129.22 |
Nov 18, 2021 | IDA-67860 | Loan Disb | 635,638.25 |
Apr 9, 2021 | IDA-67860 | Loan Disb | 917,872.75 |
Dec 1, 2020 | IDA-54740 | Int Charges | 39,900.57 |
Dec 1, 2020 | IDA-54740 | Int Charges | 39,900.57 |
Dec 1, 2020 | IDA-54740 | Int Charges | 62,762.29 |
Dec 1, 2020 | IDA-54740 | Int Charges | 1,137.43 |
Dec 1, 2020 | IDA-54740 | Loan Repay | 181,554.45 |
Jun 1, 2022 | IDA-54740 | Loan Repay | 2,267.01 |
Jun 1, 2022 | IDA-54740 | Loan Repay | 169,141.22 |
Jun 1, 2021 | IDA-54740 | Int Charges | 3,780.53 |
Jun 1, 2021 | IDA-54740 | Loan Repay | 183,591.06 |
Jun 1, 2021 | IDA-54740 | Int Charges | 39,659.66 |
Jun 1, 2021 | IDA-54740 | Int Charges | 39,659.66 |
Jun 1, 2021 | IDA-54740 | Int Charges | 60,336.36 |
Dec 2, 2021 | IDA-54740 | Int Charges | 5,585.54 |
Dec 2, 2021 | IDA-54740 | Loan Repay | 177,934.80 |
Dec 2, 2021 | IDA-54740 | Int Charges | 37,770.49 |
Dec 2, 2021 | IDA-54740 | Int Charges | 37,770.49 |
Dec 2, 2021 | IDA-54740 | Int Charges | 62,950.85 |
Nov 19, 2020 | IDA-67860 | Loan Commitment | 26,000,000.00 |
Jun 4, 2014 | IDA-54740 | Loan Commitment | 11,890,000.00 |
Jun 1, 2018 | IDA-54740 | Int Charges | 33,621.71 |
Jun 1, 2018 | IDA-54740 | Int Charges | 33,621.71 |
Jun 1, 2018 | IDA-54740 | Int Charges | 56,036.18 |
Jun 1, 2017 | IDA-54740 | Int Charges | 11,992.42 |
Jun 1, 2017 | IDA-54740 | Int Charges | 11,992.42 |
Jun 1, 2017 | IDA-54740 | Int Charges | 811.13 |
Jun 1, 2017 | IDA-54740 | Int Charges | 811.13 |
Jun 1, 2017 | IDA-54740 | Int Charges | 20,650.66 |
Mar 1, 2017 | IDA-54740 | Loan Disb | 1,181,239.80 |
Dec 1, 2017 | IDA-54740 | Int Charges | 705.45 |
Dec 1, 2017 | IDA-54740 | Int Charges | 30,511.64 |
Dec 1, 2017 | IDA-54740 | Int Charges | 30,511.64 |
Dec 1, 2017 | IDA-54740 | Int Charges | 50,544.99 |
Dec 30, 2016 | IDA-54740 | Loan Disb | 189,307.61 |
Dec 1, 2016 | IDA-54740 | Int Charges | 116.97 |
Dec 1, 2016 | IDA-54740 | Int Charges | 116.97 |
Dec 1, 2016 | IDA-54740 | Int Charges | 9,573.50 |
Dec 1, 2016 | IDA-54740 | Int Charges | 9,573.50 |
Dec 1, 2016 | IDA-54740 | Int Charges | 16,150.72 |
Jun 1, 2016 | IDA-54740 | Int Charges | 16,200.57 |
Jun 1, 2016 | IDA-54740 | Int Charges | 210.60 |
Jun 1, 2016 | IDA-54740 | Int Charges | 210.60 |
Jun 1, 2016 | IDA-54740 | Int Charges | 9,509.78 |
Jun 1, 2016 | IDA-54740 | Int Charges | 9,509.78 |
Jun 21, 2017 | IDA-54740 | Loan Disb | 4,357,241.00 |
Dec 1, 2019 | IDA-54740 | Int Charges | 39,642.31 |
Dec 1, 2019 | IDA-54740 | Int Charges | 39,642.31 |
Dec 1, 2019 | IDA-54740 | Loan Repay | 810.79 |
Dec 1, 2019 | IDA-54740 | Loan Repay | 173,616.16 |
Dec 1, 2019 | IDA-54740 | Int Charges | 63,850.44 |
Jun 1, 2020 | IDA-54740 | Int Charges | 2,217.39 |
Jun 1, 2020 | IDA-54740 | Loan Repay | 174,217.31 |
Jun 1, 2020 | IDA-54740 | Int Charges | 38,941.33 |
Jun 1, 2020 | IDA-54740 | Int Charges | 38,941.33 |
Jun 1, 2020 | IDA-54740 | Int Charges | 63,810.84 |
Dec 1, 2018 | IDA-54740 | Int Charges | 65,940.90 |
Dec 1, 2018 | IDA-54740 | Int Charges | 2,300.53 |
Dec 1, 2018 | IDA-54740 | Int Charges | 2,300.53 |
Dec 1, 2018 | IDA-54740 | Int Charges | 37,264.04 |
Dec 1, 2018 | IDA-54740 | Int Charges | 37,264.04 |
Jun 10, 2019 | IDA-54740 | Loan Disb | 116.81 |
Jun 1, 2019 | IDA-54740 | Int Charges | 957.25 |
Jun 1, 2019 | IDA-54740 | Int Charges | 957.25 |
Jun 1, 2019 | IDA-54740 | Int Charges | 38,820.95 |
Jun 1, 2019 | IDA-54740 | Int Charges | 38,820.95 |
Jun 1, 2019 | IDA-54740 | Int Charges | 66,296.94 |
Feb 21, 2018 | IDA-54740 | Loan Disb | 620,984.80 |
Jun 12, 2018 | IDA-54740 | Loan Disb | 1,682,961.90 |
Jun 1, 2018 | IDA-54740 | Int Charges | 307.55 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-10-07 |
Monitoring and Evaluation | Satisfactory | 2024-10-07 |
Overall Implementation Progress (IP) | Satisfactory | 2024-10-07 |
Overall Safeguards Rating | Satisfactory | 2024-10-07 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-07 |
Procurement | Moderately Satisfactory | 2024-10-07 |
Project Management | Satisfactory | 2024-10-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Area with improved protection against breach of EDWC dams | Value | 13000.00 | 13000.00 | 32000.00 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
Area provided with new/improved irrigation or drainage services | Value | 7864.00 | 7864.00 | 13379.00 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people benefiting from reduced flood risk/protected from flooding | Value | 90000.00 | 90000.00 | 150000.00 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
Expanded meteorological, hydrological monitoring network installed and active | Value | Yes | Yes | Yes |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Adoption of operational procedures and surveillance systems for the EDWC dams | Value | No | Yes | Yes |
Date | March 2, 2020 | June 14, 2023 | December 31, 2024 | |
Comment |
Female beneficiaries | Value | 51.00 | 0.00 | 51.00 |
Date | August 31, 2014 | June 12, 2018 | January 31, 2019 | |
Comment |
Length of dam upgraded | Value | 4.00 | 4.00 | 12.90 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
Application of new methodology for dam rehabilitation | Value | No | Yes | Yes |
Date | March 2, 2020 | June 16, 2023 | December 31, 2024 | |
Comment |
Water users provided with new/improved irrigation and drainage services (number) | Value | 47638.00 | 47638.00 | 97638.00 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
Number of staff at NDIA trained to climate resilient flood modeling | Value | 0.00 | 0.00 | 20.00 |
Date | March 2, 2020 | June 14, 2023 | December 31, 2024 | |
Comment |
Water users provided with irrigation and drainage services - female (number) | Value | 24010.00 | 24010.00 | 40000.00 |
Date | March 2, 2020 | June 3, 2022 | December 31, 2024 | |
Comment |
Increased drainage capacity (Cubic meters per socond) | Value | 8.00 | 8.00 | 14.00 |
Date | March 2, 2020 | January 31, 2024 | December 31, 2024 | |
Comment |
Adoption of dam safety measures including procedures for emergency preparedness in case of dam breach | Value | Yes | Yes | Yes |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Number of key consultations for citizen feedback during design and implementation of key drainage infrastructure | Value | 0.00 | 4.00 | 3.00 |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Percentage of addressed grievances related to project activities | Value | 0.00 | 100.00 | 100.00 |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Gender considerations are included in infrastructure design | Value | No | Yes | Yes |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Percentage of female participants in consultation activities during project implementation | Value | 0.00 | 50.00 | 50.00 |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |
Priority drainage Interventions at Liliendaal and Ogle basins have been determined | Value | No | Yes | Yes |
Date | March 2, 2020 | November 22, 2022 | December 31, 2024 | |
Comment |