Enhancing Public Management for Service Delivery in Rio de Janeiro

Abstract*

The objective of the Enhancing Public Management for Service Delivery in Rio de Janeiro Development Policy Operation for Brazil is to assist the Government of Rio de Janeiro (GORJ) in its efforts to enhance public management for the delivery of key public services for vulnerable populations by instituting new policies and regulations to improve: the medium term planning and monitoring of public expenditures (Policy Area 1); the accessibility, quality...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Assist the Government of Rio de Janeiro (GORJ) in its efforts to enhance public management for the delivery of key public services for vulnerable populations by instituting new policies and regulations to improve: the medium term planning and monitoring of publicexpenditures (Policy Area 1); the accessibility, quality and affordability of urban mobility services for the poor (Policy Area 2);and the availability of targeted social services aimed at reducing domestic and gender based violence (Policy Area 3). This objective directly contributes to the poverty reduction and shared prosperity agendas, insofar as financially-sustainable and targeted urban mobility and social support services benefiting the poor and other populations at risk, such as women, enable more equitable access to economic and social opportunities, allowing the benefits of growth to be shared more widely.

Key Details

Project Details

  • P147695

  • Closed

  • Daniel Pulido

  • State of Rio de Janeiro

  • Brazil

  • November 21, 2013

  • (as of board presentation)

    November 21, 2013

  • December 6, 2013

  • US$ 500.00 million

  • Casa Civil (Office of the Chief of Staff),Secretariat of Finance (SEFAZ),State Secretariat of Social Welfare and Human Rights (SEASDH),State Secretariat of Transportation (SETRANS)

  • Latin America and Caribbean

  • 2014

  • US$ 500.00 million

  • N/A

  • Not Applicable

  • January 31, 2016

  • BANK APPROVED

  • November 1, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 500.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 500.00
IDA Commitment N/A
IBRD + IDA Commitment 500.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 500.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 11, 2013 IBRD-83070 Loan Disb 500,000,000.00
Aug 15, 2015 IBRD-83070 Int Charges 2,287,639.00
Feb 15, 2015 IBRD-83070 Int Charges 2,121,111.00
Aug 15, 2014 IBRD-83070 Int Charges 2,011,111.10
Aug 15, 2024 IBRD-83070 Int Charges 91,889.32
Nov 21, 2013 IBRD-83070 Loan Commitment 500,000,000.00
Feb 15, 2016 IBRD-83070 Int Charges 2,734,444.50
Aug 15, 2024 IBRD-83070 Int Charges 15,898,792.00
Aug 15, 2024 IBRD-83070 Loan Repay 15,625,000.00
Feb 15, 2024 IBRD-83070 Int Charges 145,395.34
Feb 15, 2024 IBRD-83070 Int Charges 16,362,738.00
Feb 15, 2024 IBRD-83070 Loan Repay 15,625,000.00
Feb 15, 2023 IBRD-83070 Int Charges 11,529,900.00
Feb 15, 2023 IBRD-83070 Int Charges 807,437.25
Aug 15, 2023 IBRD-83070 Int Charges 524,286.38
Aug 15, 2023 IBRD-83070 Int Charges 14,148,540.00
Aug 15, 2022 IBRD-83070 Int Charges 3,451,689.20
Mar 4, 2022 IBRD-83070 Int Charges 2,274,444.50
Aug 31, 2021 IBRD-83070 Int Charges 2,337,916.80
Feb 25, 2021 IBRD-83070 Int Charges 2,657,777.80
Aug 27, 2020 IBRD-83070 Int Charges 6,041,389.00
Feb 28, 2020 IBRD-83070 Int Charges 6,951,111.00
Aug 27, 2019 IBRD-83070 Int Charges 8,647,778.00
Mar 8, 2019 IBRD-83070 Int Charges 8,152,222.00
Aug 23, 2018 IBRD-83070 Int Charges 6,837,778.00
Sep 13, 2017 IBRD-83070 Int Charges 4,977,500.00
Mar 7, 2018 IBRD-83070 Int Charges 5,392,222.00
Mar 15, 2017 IBRD-83070 Int Charges 4,625,555.50
Sep 12, 2016 IBRD-83070 Int Charges 3,614,722.20
Dec 9, 2013 IBRD-83070 Fee Charges 1,250,000.00
Feb 15, 2014 IBRD-83070 Int Charges 751,666.70

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2016-01-29
Progress towards achievement of PDO Moderately Unsatisfactory 2016-01-29
Program Management Moderately Satisfactory 2016-01-29
Overall Implementation Progress (IP) Moderately Satisfactory 2016-01-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2017
OutcomesUnsatisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyUnsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-29-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Maintenance of the number of events (occurrences and non conformities) in which the operational risk policy procedures were not complied with within already achieved satisfactory levels since loan sigValue0.000.000.00
    Date
    Comment
  • Reduction in the percentage of payments made after 30 daysValue3.609.203.00
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • Reduction in the gap between actual and estimated current revenues, measured as a share of the estimated revenuesValue6.602.305.00
    DateDecember 31, 2014December 31, 2014
    Comment
  • Publication in the internet of revenue estimates documents for the 2014 budgetValueNoYesYes
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • Annual Budget directive issued for the 2015 budget cycleValueNoYesYes
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • All PPP-related bidding documents, contracts and supporting analysis are published on a dedicated website in a timely mannerValueNoYesYes
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • Permanent Committee for the implementation of the PDTU, involving relevant government and civil society actors, meets at least four(4) times in its first year of existence and presents strategy for tValue0.004.004.00
    DateSeptember 30, 2013December 18, 2015December 31, 2014
    Comment
  • No transport project outside of the PDTU (i.e. not endorsed by PDTU) will be undertaken by the GoRJ.ValueNoYesYes
    DateSeptember 30, 2013October 15, 2015December 31, 2014
    Comment
  • Reduction in the number of times in a year that the actual monthly cash balance has remained below the minimum threshold (set at 1.5 times the payroll amount)Value3.001.002.00
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • A comprehensive report including current and prospective long-term commitments and liabilities associated to PPPs is published as scheduledValueNoYesYes
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • At least one (1) multimodal integration project is completedValue0.001.001.00
    DateSeptember 30, 2013November 10, 2014December 31, 2014
    Comment
  • State prepares guidelines for the development of bicycle-public transit integration projects to be implemented by metropolitan municipalities and at least one (1) of these projects is implemented withValue0.002.001.00
    DateSeptember 30, 2013November 10, 2014December 31, 2014
    Comment
  • The concession bidding documents will identify the bus lines to be sectioned or eliminated in order to prioritize integration with mass transit modes (name, current code, and in the cases of sectioninValue0.000.0019.00
    DateDecember 31, 2013October 16, 2015January 31, 2016
    Comment
  • Inter-municipal bus lines in the RJMR (previously provided under permission regime) are in operation under new concession agreements incorporating performance monitoringValue0.000.0050.00
    DateDecember 31, 2013October 16, 2015December 31, 2014
    Comment
  • • Service reliability, fleet modernization and vehicle occupation requirements are properly monitored and enforced on inter-municipal bus concessions in operation (percentage of compliance)Value0.000.0080.00
    DateOctober 16, 2015December 31, 2014
    Comment
  • • New operations contract awarded for the Teleferico System incorporates performance monitoring, availability-based remuneration, and incentives for maximizing ancillary revenue; and results in a reduValue0.0014.005.00
    DateDecember 31, 2013December 18, 2015December 31, 2014
    Comment
  • • Number of women benefiting from increased access to information and to social and legal services as per the provisions of the “Lei Maria da Penha” within the Supervia and Teleférico systemsValue0.0074300.0050000.00
    DateDecember 31, 2013December 18, 2015January 31, 2016
    Comment
  • • Increase in the number of women benefiting from the integration of the Supervia and Teleférico systems to the “Casa Lilas”Value0.000.001000.00
    DateDecember 31, 2013October 16, 2015January 31, 2016
    Comment
  • OccurencesValue52.0016.0048.00
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment
  • Non-conformitiesValue12.008.0011.00
    DateDecember 31, 2012December 31, 2015December 31, 2014
    Comment