Financier | Commitments |
---|---|
Local Communities | 13.90 |
IDA Credit | 165.00 |
Borrower/Recipient | 5.00 |
P147827
Active
Amelia Midgley
Democratic Socialist Republic of Sri Lanka
October 31, 2014
(as of board presentation)
June 24, 2015
December 7, 2015
US$ 183.90 million
National Water Supply and Drainage Board,Ministry of Water Supply
2015
US$ 165.00 million
B
April 21, 2024
June 30, 2025
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Local Communities | 13.90 |
IDA Credit | 165.00 |
Borrower/Recipient | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 165.00 |
IBRD + IDA Commitment | 165.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 183.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2023 | IDA-56850 | Int Charges | 788,474.70 |
Oct 30, 2023 | IDA-56850 | Loan Disb | 40,982.79 |
Dec 23, 2022 | IDA-56850 | Loan Disb | 94,425.13 |
Dec 1, 2022 | IDA-56850 | Loan Disb | 271,878.06 |
Sep 14, 2022 | IDA-56850 | Loan Disb | 57,577.37 |
Dec 15, 2022 | IDA-56850 | Loan Repay | 2,464,004.20 |
Dec 15, 2022 | IDA-56850 | Loan Repay | 113,907.75 |
Dec 15, 2022 | IDA-56850 | Int Charges | 503,924.38 |
Dec 15, 2022 | IDA-56850 | Int Charges | 503,924.38 |
Dec 15, 2022 | IDA-56850 | Int Charges | 1,562,422.10 |
Apr 21, 2023 | IDA-56850 | Loan Disb | 9,000,000.00 |
Apr 11, 2023 | IDA-56850 | Loan Disb | 69,868.20 |
Jul 14, 2023 | IDA-56850 | Loan Disb | 173,768.61 |
Mar 17, 2023 | IDA-56850 | Loan Disb | 18,673.39 |
Jul 25, 2023 | IDA-56850 | Loan Disb | 239,970.17 |
Aug 19, 2022 | IDA-56850 | Loan Disb | 252,882.38 |
Aug 12, 2022 | IDA-56850 | Loan Disb | 17,942.12 |
Aug 12, 2022 | IDA-56850 | Loan Disb | 12,640.19 |
Feb 11, 2022 | IDA-56850 | Loan Disb | 5,000,000.00 |
Aug 12, 2022 | IDA-56850 | Loan Disb | 6,057.75 |
Aug 11, 2022 | IDA-56850 | Loan Disb | 7,270.76 |
Aug 16, 2022 | IDA-56850 | Loan Disb | 7,837.87 |
Aug 26, 2022 | IDA-56850 | Loan Disb | 42,023.10 |
Aug 2, 2022 | IDA-56850 | Loan Disb | 23,189.57 |
Aug 25, 2022 | IDA-56850 | Loan Disb | 145,468.06 |
Aug 25, 2022 | IDA-56850 | Loan Disb | 6,530.97 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 26,201.82 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 43,109.64 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 6,307.52 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 12,606.98 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 66,137.91 |
Aug 29, 2022 | IDA-56850 | Loan Disb | 58,879.22 |
Dec 15, 2021 | IDA-56850 | Int Charges | 494,529.72 |
Dec 15, 2021 | IDA-56850 | Int Charges | 494,529.72 |
Dec 27, 2023 | IDA-56850 | Loan Disb | 78,522.79 |
Oct 12, 2023 | IDA-56850 | Loan Disb | 41,588.54 |
Dec 15, 2023 | IDA-56850 | Loan Disb | 107,763.40 |
Dec 21, 2023 | IDA-56850 | Loan Disb | 160,706.83 |
Jan 17, 2024 | IDA-56850 | Loan Disb | 71,475.71 |
Dec 27, 2023 | IDA-56850 | Loan Disb | 37,444.22 |
Feb 7, 2024 | IDA-56850 | Loan Disb | 13,509.60 |
Apr 30, 2024 | IDA-56850 | Loan Cancel | 3,261.44 |
Jun 15, 2024 | IDA-56850 | Int Charges | 90,805.17 |
Jun 15, 2024 | IDA-56850 | Loan Repay | 2,552,361.80 |
Jun 15, 2024 | IDA-56850 | Int Charges | 512,960.53 |
Jun 15, 2024 | IDA-56850 | Int Charges | 512,960.53 |
Mar 7, 2016 | IDA-56850 | Loan Disb | 9,600,000.00 |
Jun 15, 2019 | IDA-56850 | Int Charges | 509,648.03 |
Dec 15, 2017 | IDA-56850 | Int Charges | 104,385.33 |
Dec 15, 2017 | IDA-56850 | Int Charges | 104,385.33 |
Jun 15, 2018 | IDA-56850 | Int Charges | 34,486.01 |
May 25, 2018 | IDA-56850 | Loan Disb | 21,400,000.00 |
Jun 15, 2018 | IDA-56850 | Int Charges | 177,948.00 |
Jun 15, 2018 | IDA-56850 | Int Charges | 177,948.00 |
Jun 15, 2018 | IDA-56850 | Int Charges | 287,839.78 |
Dec 15, 2018 | IDA-56850 | Int Charges | 8,541.62 |
Dec 15, 2018 | IDA-56850 | Int Charges | 243,266.50 |
Dec 15, 2018 | IDA-56850 | Int Charges | 243,266.50 |
Jun 15, 2017 | IDA-56850 | Int Charges | 41,500.71 |
Jun 15, 2017 | IDA-56850 | Int Charges | 49,851.14 |
Jun 15, 2017 | IDA-56850 | Int Charges | 2,690.56 |
Jun 15, 2017 | IDA-56850 | Int Charges | 2,690.56 |
Jun 15, 2017 | IDA-56850 | Int Charges | 41,500.71 |
Nov 15, 2017 | IDA-56850 | Loan Disb | 20,800,000.00 |
Dec 15, 2017 | IDA-56850 | Int Charges | 139,415.98 |
Dec 15, 2017 | IDA-56850 | Int Charges | 24,349.60 |
Jun 15, 2016 | IDA-56850 | Int Charges | 19,873.31 |
Jun 15, 2016 | IDA-56850 | Int Charges | 19,873.31 |
Jun 15, 2016 | IDA-56850 | Int Charges | 33,098.82 |
Dec 15, 2016 | IDA-56850 | Int Charges | 57,962.74 |
Dec 15, 2016 | IDA-56850 | Int Charges | 34,777.63 |
Dec 15, 2016 | IDA-56850 | Int Charges | 22.27 |
Dec 15, 2016 | IDA-56850 | Int Charges | 34,777.63 |
May 17, 2017 | IDA-56850 | Loan Disb | 14,200,000.00 |
Dec 15, 2021 | IDA-56850 | Int Charges | 824,216.25 |
Dec 15, 2021 | IDA-56850 | Int Charges | 46,274.58 |
Dec 15, 2021 | IDA-56850 | Loan Repay | 2,705,237.80 |
May 6, 2021 | IDA-56850 | Loan Disb | 8,000,000.00 |
Nov 9, 2021 | IDA-56850 | Loan Disb | 4,000,000.00 |
Jun 15, 2022 | IDA-56850 | Loan Repay | 36,707.04 |
Jun 15, 2024 | IDA-56850 | Int Charges | 851,129.00 |
Sep 18, 2023 | IDA-56850 | Loan Disb | 416,353.38 |
Jul 21, 2023 | IDA-56850 | Loan Disb | 41,653.76 |
Jun 15, 2023 | IDA-56850 | Int Charges | 847,252.60 |
Jun 28, 2023 | IDA-56850 | Loan Disb | 125,786.90 |
Aug 31, 2023 | IDA-56850 | Loan Disb | 41,891.85 |
Feb 15, 2022 | IBRD-92550 | Int Charges | 28,421.92 |
Feb 15, 2022 | IBRD-92550 | Int Charges | 388.67 |
Aug 19, 2022 | IBRD-92550 | Loan Disb | 42,834.59 |
Aug 15, 2022 | IBRD-92550 | Int Charges | 24,196.65 |
Aug 29, 2022 | IBRD-92550 | Loan Disb | 26,842.71 |
May 2, 2022 | IBRD-92550 | Loan Disb | 5,000,000.00 |
Sep 9, 2021 | IBRD-92550 | Loan Disb | 100,000.00 |
Sep 9, 2021 | IBRD-92550 | Fee Charges | 100,000.00 |
Jun 10, 2021 | IBRD-92550 | Loan Commitment | 40,000,000.00 |
Jun 24, 2015 | IDA-56850 | Loan Commitment | 165,000,000.00 |
Feb 15, 2024 | IBRD-92550 | Int Charges | 4,764.94 |
Feb 15, 2024 | IBRD-92550 | Int Charges | 24,138.00 |
Jun 18, 2024 | IBRD-92550 | Loan Disb | 3,000,000.00 |
Aug 15, 2024 | IBRD-92550 | Int Charges | 942.62 |
Aug 22, 2024 | IBRD-92550 | Loan Disb | 105,929.53 |
Aug 15, 2024 | IBRD-92550 | Int Charges | 1,053,161.10 |
Aug 15, 2024 | IBRD-92550 | Int Charges | 27,159.19 |
Aug 15, 2024 | IBRD-92550 | Int Charges | 8,635.37 |
Aug 21, 2024 | IBRD-92550 | Loan Disb | 1,500,000.00 |
Feb 9, 2024 | IBRD-92550 | Loan Disb | 9,000,000.00 |
Aug 2, 2024 | IBRD-92550 | Loan Disb | 167,205.40 |
Feb 15, 2024 | IBRD-92550 | Int Charges | 657,316.30 |
Jan 18, 2024 | IBRD-92550 | Loan Disb | 3,000,000.00 |
Feb 17, 2023 | IBRD-92550 | Loan Disb | 26,758.58 |
May 26, 2023 | IBRD-92550 | Loan Disb | 165,665.69 |
Aug 15, 2023 | IBRD-92550 | Int Charges | 7,593.65 |
Aug 15, 2023 | IBRD-92550 | Int Charges | 31,114.27 |
Aug 15, 2023 | IBRD-92550 | Int Charges | 426,962.88 |
Aug 15, 2023 | IBRD-92550 | Int Charges | 84.74 |
Dec 22, 2022 | IBRD-92550 | Loan Disb | 224,946.69 |
Apr 28, 2023 | IBRD-92550 | Loan Disb | 160,959.64 |
Apr 21, 2023 | IBRD-92550 | Loan Disb | 14,000,000.00 |
Feb 15, 2023 | IBRD-92550 | Int Charges | 8,229.91 |
Feb 15, 2023 | IBRD-92550 | Int Charges | 43,493.03 |
Feb 15, 2023 | IBRD-92550 | Int Charges | 125,252.95 |
Aug 16, 2022 | IBRD-92550 | Loan Disb | 27,271.61 |
Aug 15, 2022 | IBRD-92550 | Int Charges | 45,869.19 |
Aug 30, 2022 | IBRD-92550 | Loan Disb | 60,705.22 |
Aug 30, 2022 | IBRD-92550 | Loan Disb | 133,222.98 |
Nov 28, 2022 | IBRD-92550 | Loan Disb | 116,558.33 |
Dec 15, 2018 | IDA-56850 | Int Charges | 405,444.16 |
Feb 11, 2019 | IDA-56850 | Loan Disb | 24,000,000.00 |
Jun 15, 2019 | IDA-56850 | Int Charges | 8,989.02 |
Jun 15, 2019 | IDA-56850 | Int Charges | 8,989.02 |
Jun 15, 2019 | IDA-56850 | Int Charges | 296,799.80 |
Jun 15, 2019 | IDA-56850 | Int Charges | 296,799.80 |
Jun 15, 2023 | IDA-56850 | Int Charges | 198,521.95 |
Jun 15, 2023 | IDA-56850 | Loan Repay | 2,585,311.80 |
Jun 15, 2023 | IDA-56850 | Int Charges | 508,351.56 |
Jun 15, 2023 | IDA-56850 | Int Charges | 508,351.56 |
Jun 28, 2023 | IDA-56850 | Loan Disb | 68,973.53 |
Jun 27, 2023 | IDA-56850 | Loan Disb | 17,476.71 |
May 30, 2023 | IDA-56850 | Loan Disb | 222,545.52 |
Dec 15, 2023 | IDA-56850 | Loan Repay | 2,562,656.20 |
Dec 15, 2023 | IDA-56850 | Loan Repay | 34,588.04 |
Oct 19, 2023 | IDA-56850 | Loan Disb | 16,603.06 |
Dec 15, 2023 | IDA-56850 | Int Charges | 528,526.00 |
Dec 15, 2023 | IDA-56850 | Int Charges | 528,526.00 |
Aug 17, 2021 | IDA-56850 | Loan Disb | 5,000,000.00 |
Jun 15, 2022 | IDA-56850 | Loan Repay | 2,543,161.50 |
Jun 15, 2022 | IDA-56850 | Int Charges | 493,897.06 |
Jun 15, 2022 | IDA-56850 | Int Charges | 493,897.06 |
Jun 15, 2022 | IDA-56850 | Int Charges | 1,725,347.10 |
May 17, 2022 | IDA-56850 | Loan Disb | 4,000,000.00 |
Jun 15, 2020 | IDA-56850 | Int Charges | 346,454.84 |
Jun 15, 2020 | IDA-56850 | Int Charges | 346,454.84 |
Jun 15, 2020 | IDA-56850 | Int Charges | 566,886.40 |
Jun 15, 2020 | IDA-56850 | Int Charges | 8,564.23 |
Sep 4, 2020 | IDA-56850 | Loan Disb | 6,000,000.00 |
Oct 16, 2020 | IDA-56850 | Loan Disb | 10,000,000.00 |
Dec 15, 2020 | IDA-56850 | Int Charges | 10,986.24 |
Dec 15, 2020 | IDA-56850 | Loan Repay | 2,785,511.00 |
Dec 15, 2020 | IDA-56850 | Int Charges | 411,451.72 |
Dec 15, 2020 | IDA-56850 | Int Charges | 411,451.72 |
Dec 15, 2020 | IDA-56850 | Int Charges | 581,324.25 |
Feb 16, 2021 | IDA-56850 | Loan Disb | 10,000,000.00 |
Jun 15, 2021 | IDA-56850 | Int Charges | 104,514.99 |
Jun 15, 2021 | IDA-56850 | Loan Repay | 2,787,816.20 |
Jun 15, 2021 | IDA-56850 | Int Charges | 468,325.62 |
Jun 15, 2021 | IDA-56850 | Int Charges | 468,325.62 |
Jun 15, 2021 | IDA-56850 | Int Charges | 732,855.60 |
Feb 11, 2020 | IDA-56850 | Loan Disb | 5,000,000.00 |
Dec 15, 2019 | IDA-56850 | Int Charges | 4,232.42 |
Dec 15, 2019 | IDA-56850 | Int Charges | 4,232.42 |
Dec 15, 2019 | IDA-56850 | Int Charges | 329,629.84 |
Dec 15, 2019 | IDA-56850 | Int Charges | 329,629.84 |
Dec 15, 2019 | IDA-56850 | Int Charges | 547,843.44 |
Jun 8, 2020 | IDA-56850 | Loan Disb | 5,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2025-03-10 |
Procurement | Satisfactory | 2025-03-10 |
Financial Management | Satisfactory | 2025-03-10 |
Progress towards achievement of PDO | Satisfactory | 2025-03-10 |
Monitoring and Evaluation | Satisfactory | 2025-03-10 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 504171.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Rural M&E system established, populated and used in decision making | Value | 0.00 | 100.00 | 0.00 |
Date | June 24, 2015 | June 30, 2021 | ||
Comment |
Fully functioning CBOs | Value | 0.00 | 100.00 | 0.00 |
Date | June 24, 2015 | June 30, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 52.37 | 0.00 |
Date | June 24, 2015 | |||
Comment |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 102248.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People in urban areas provided with access to improved water source - Female | Value | 0.00 | 51124.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 309883.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People in rural areas provided with access to improved water sources - Female | Value | 0.00 | 173535.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 153773.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People in rural and estates areas provided with access to improved sanitation facilities - Female | Value | 0.00 | 77578.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Proportion of grievances registered related to project delivery that have been redressed | Value | 0.00 | 100.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
New piped household water connections resulting from project intervention (Estates) | Value | 0.00 | 4355.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 44155.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to Improved Sanitation (Rural) | Value | 0.00 | 54548.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to Improved Sanitation - Rural Female | Value | 0.00 | 27274.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to Improved Sanitation - Estates | Value | 0.00 | 7185.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to Improved Sanitation - Estates Female | Value | 0.00 | 3593.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People trained to improve hygiene behavior/sanitation practices under the proj | Value | 0.00 | 135833.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People trained to improve hygiene behavior/sanitation practices - female | Value | 0.00 | 76066.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People trained in improved hygiene behavior or sanitation practices (Estates) | Value | 0.00 | 18584.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People in Estates trained in improved hygiene behavior - Female | Value | 0.00 | 13009.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Households gaining access to safe disposal of fecal sludge in urban areas contributing to reductions in GHG emissions | Value | 0.00 | 10500.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Number of other water service providers that the project is supporting | Value | 0.00 | 2855.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
People provided with access to improved sanitation outside water supply service areas | Value | 0.00 | 92040.00 | 0.00 |
Date | February 25, 2019 | December 31, 2021 | ||
Comment |
Schools provided with access to improved sanitation | Value | 0.00 | 31.00 | 0.00 |
Date | February 25, 2019 | December 31, 2021 | ||
Comment |
Sanitation units for differently abled beneficiaries and indigenous communities | Value | 0.00 | 286.00 | 0.00 |
Date | February 25, 2019 | December 31, 2021 | ||
Comment |
New CBOs established under additional financing with at least one woman in a leadership position | Value | 0.00 | 0.00 | 0.00 |
Date | May 13, 2021 | December 31, 2021 | ||
Comment |
Number of CBOs visited and evaluated by DNCWS | Value | 0.00 | 1402.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
Comprehensive sector program prepared and approved by Ministry | Value | 0.00 | 1.00 | 0.00 |
Date | September 30, 2015 | December 31, 2021 | ||
Comment |
New piped household water connections that are resulting from the project intervention (Urban) | Value | 0.00 | 25562.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
DNCWS organizational structure designed and approved by Ministry | Value | 0.00 | 0.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |
New piped household water connections that are resulting from the project intervention (Rural) | Value | 0.00 | 27872.00 | 0.00 |
Date | June 24, 2015 | December 31, 2021 | ||
Comment |