Abstract*

The development objectives of the Water Supply and Sanitation Improvement Project for Sri Lanka are to increase access to piped water services and improved sanitation in selected districts; and to strengthen the capacity of associated institutions. There are four components to the project, the first component being water supply and sanitation infrastructure. This component will finance infrastructure investments to support expansion of piped water...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objectives of the project are to increase access to piped water services and improved sanitation in selected Districts; and to strengthen the capacity of associated institutions, and in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

Key Details

Project Details

  • P147827

  • Active

  • Amelia Midgley

  • Democratic Socialist Republic of Sri Lanka

  • Sri Lanka

  • October 31, 2014

  • (as of board presentation)

    June 24, 2015

  • December 7, 2015

  • US$ 183.90 million

  • National Water Supply and Drainage Board,Ministry of Water Supply

  • South Asia

  • 2015

  • US$ 165.00 million

  • B

  • April 21, 2024

  • June 30, 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Communities 13.90
IDA Credit 165.00
Borrower/Recipient 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 165.00
IBRD + IDA Commitment 165.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 183.90

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2023 IDA-56850 Int Charges 788,474.70
Oct 30, 2023 IDA-56850 Loan Disb 40,982.79
Dec 23, 2022 IDA-56850 Loan Disb 94,425.13
Dec 1, 2022 IDA-56850 Loan Disb 271,878.06
Sep 14, 2022 IDA-56850 Loan Disb 57,577.37
Dec 15, 2022 IDA-56850 Loan Repay 2,464,004.20
Dec 15, 2022 IDA-56850 Loan Repay 113,907.75
Dec 15, 2022 IDA-56850 Int Charges 503,924.38
Dec 15, 2022 IDA-56850 Int Charges 503,924.38
Dec 15, 2022 IDA-56850 Int Charges 1,562,422.10
Apr 21, 2023 IDA-56850 Loan Disb 9,000,000.00
Apr 11, 2023 IDA-56850 Loan Disb 69,868.20
Jul 14, 2023 IDA-56850 Loan Disb 173,768.61
Mar 17, 2023 IDA-56850 Loan Disb 18,673.39
Jul 25, 2023 IDA-56850 Loan Disb 239,970.17
Aug 19, 2022 IDA-56850 Loan Disb 252,882.38
Aug 12, 2022 IDA-56850 Loan Disb 17,942.12
Aug 12, 2022 IDA-56850 Loan Disb 12,640.19
Feb 11, 2022 IDA-56850 Loan Disb 5,000,000.00
Aug 12, 2022 IDA-56850 Loan Disb 6,057.75
Aug 11, 2022 IDA-56850 Loan Disb 7,270.76
Aug 16, 2022 IDA-56850 Loan Disb 7,837.87
Aug 26, 2022 IDA-56850 Loan Disb 42,023.10
Aug 2, 2022 IDA-56850 Loan Disb 23,189.57
Aug 25, 2022 IDA-56850 Loan Disb 145,468.06
Aug 25, 2022 IDA-56850 Loan Disb 6,530.97
Aug 29, 2022 IDA-56850 Loan Disb 26,201.82
Aug 29, 2022 IDA-56850 Loan Disb 43,109.64
Aug 29, 2022 IDA-56850 Loan Disb 6,307.52
Aug 29, 2022 IDA-56850 Loan Disb 12,606.98
Aug 29, 2022 IDA-56850 Loan Disb 66,137.91
Aug 29, 2022 IDA-56850 Loan Disb 58,879.22
Dec 15, 2021 IDA-56850 Int Charges 494,529.72
Dec 15, 2021 IDA-56850 Int Charges 494,529.72
Dec 27, 2023 IDA-56850 Loan Disb 78,522.79
Oct 12, 2023 IDA-56850 Loan Disb 41,588.54
Dec 15, 2023 IDA-56850 Loan Disb 107,763.40
Dec 21, 2023 IDA-56850 Loan Disb 160,706.83
Jan 17, 2024 IDA-56850 Loan Disb 71,475.71
Dec 27, 2023 IDA-56850 Loan Disb 37,444.22
Feb 7, 2024 IDA-56850 Loan Disb 13,509.60
Apr 30, 2024 IDA-56850 Loan Cancel 3,261.44
Jun 15, 2024 IDA-56850 Int Charges 90,805.17
Jun 15, 2024 IDA-56850 Loan Repay 2,552,361.80
Jun 15, 2024 IDA-56850 Int Charges 512,960.53
Jun 15, 2024 IDA-56850 Int Charges 512,960.53
Mar 7, 2016 IDA-56850 Loan Disb 9,600,000.00
Jun 15, 2019 IDA-56850 Int Charges 509,648.03
Dec 15, 2017 IDA-56850 Int Charges 104,385.33
Dec 15, 2017 IDA-56850 Int Charges 104,385.33
Jun 15, 2018 IDA-56850 Int Charges 34,486.01
May 25, 2018 IDA-56850 Loan Disb 21,400,000.00
Jun 15, 2018 IDA-56850 Int Charges 177,948.00
Jun 15, 2018 IDA-56850 Int Charges 177,948.00
Jun 15, 2018 IDA-56850 Int Charges 287,839.78
Dec 15, 2018 IDA-56850 Int Charges 8,541.62
Dec 15, 2018 IDA-56850 Int Charges 243,266.50
Dec 15, 2018 IDA-56850 Int Charges 243,266.50
Jun 15, 2017 IDA-56850 Int Charges 41,500.71
Jun 15, 2017 IDA-56850 Int Charges 49,851.14
Jun 15, 2017 IDA-56850 Int Charges 2,690.56
Jun 15, 2017 IDA-56850 Int Charges 2,690.56
Jun 15, 2017 IDA-56850 Int Charges 41,500.71
Nov 15, 2017 IDA-56850 Loan Disb 20,800,000.00
Dec 15, 2017 IDA-56850 Int Charges 139,415.98
Dec 15, 2017 IDA-56850 Int Charges 24,349.60
Jun 15, 2016 IDA-56850 Int Charges 19,873.31
Jun 15, 2016 IDA-56850 Int Charges 19,873.31
Jun 15, 2016 IDA-56850 Int Charges 33,098.82
Dec 15, 2016 IDA-56850 Int Charges 57,962.74
Dec 15, 2016 IDA-56850 Int Charges 34,777.63
Dec 15, 2016 IDA-56850 Int Charges 22.27
Dec 15, 2016 IDA-56850 Int Charges 34,777.63
May 17, 2017 IDA-56850 Loan Disb 14,200,000.00
Dec 15, 2021 IDA-56850 Int Charges 824,216.25
Dec 15, 2021 IDA-56850 Int Charges 46,274.58
Dec 15, 2021 IDA-56850 Loan Repay 2,705,237.80
May 6, 2021 IDA-56850 Loan Disb 8,000,000.00
Nov 9, 2021 IDA-56850 Loan Disb 4,000,000.00
Jun 15, 2022 IDA-56850 Loan Repay 36,707.04
Jun 15, 2024 IDA-56850 Int Charges 851,129.00
Sep 18, 2023 IDA-56850 Loan Disb 416,353.38
Jul 21, 2023 IDA-56850 Loan Disb 41,653.76
Jun 15, 2023 IDA-56850 Int Charges 847,252.60
Jun 28, 2023 IDA-56850 Loan Disb 125,786.90
Aug 31, 2023 IDA-56850 Loan Disb 41,891.85
Feb 15, 2022 IBRD-92550 Int Charges 28,421.92
Feb 15, 2022 IBRD-92550 Int Charges 388.67
Aug 19, 2022 IBRD-92550 Loan Disb 42,834.59
Aug 15, 2022 IBRD-92550 Int Charges 24,196.65
Aug 29, 2022 IBRD-92550 Loan Disb 26,842.71
May 2, 2022 IBRD-92550 Loan Disb 5,000,000.00
Sep 9, 2021 IBRD-92550 Loan Disb 100,000.00
Sep 9, 2021 IBRD-92550 Fee Charges 100,000.00
Jun 10, 2021 IBRD-92550 Loan Commitment 40,000,000.00
Jun 24, 2015 IDA-56850 Loan Commitment 165,000,000.00
Feb 15, 2024 IBRD-92550 Int Charges 4,764.94
Feb 15, 2024 IBRD-92550 Int Charges 24,138.00
Jun 18, 2024 IBRD-92550 Loan Disb 3,000,000.00
Aug 15, 2024 IBRD-92550 Int Charges 942.62
Aug 22, 2024 IBRD-92550 Loan Disb 105,929.53
Aug 15, 2024 IBRD-92550 Int Charges 1,053,161.10
Aug 15, 2024 IBRD-92550 Int Charges 27,159.19
Aug 15, 2024 IBRD-92550 Int Charges 8,635.37
Aug 21, 2024 IBRD-92550 Loan Disb 1,500,000.00
Feb 9, 2024 IBRD-92550 Loan Disb 9,000,000.00
Aug 2, 2024 IBRD-92550 Loan Disb 167,205.40
Feb 15, 2024 IBRD-92550 Int Charges 657,316.30
Jan 18, 2024 IBRD-92550 Loan Disb 3,000,000.00
Feb 17, 2023 IBRD-92550 Loan Disb 26,758.58
May 26, 2023 IBRD-92550 Loan Disb 165,665.69
Aug 15, 2023 IBRD-92550 Int Charges 7,593.65
Aug 15, 2023 IBRD-92550 Int Charges 31,114.27
Aug 15, 2023 IBRD-92550 Int Charges 426,962.88
Aug 15, 2023 IBRD-92550 Int Charges 84.74
Dec 22, 2022 IBRD-92550 Loan Disb 224,946.69
Apr 28, 2023 IBRD-92550 Loan Disb 160,959.64
Apr 21, 2023 IBRD-92550 Loan Disb 14,000,000.00
Feb 15, 2023 IBRD-92550 Int Charges 8,229.91
Feb 15, 2023 IBRD-92550 Int Charges 43,493.03
Feb 15, 2023 IBRD-92550 Int Charges 125,252.95
Aug 16, 2022 IBRD-92550 Loan Disb 27,271.61
Aug 15, 2022 IBRD-92550 Int Charges 45,869.19
Aug 30, 2022 IBRD-92550 Loan Disb 60,705.22
Aug 30, 2022 IBRD-92550 Loan Disb 133,222.98
Nov 28, 2022 IBRD-92550 Loan Disb 116,558.33
Dec 15, 2018 IDA-56850 Int Charges 405,444.16
Feb 11, 2019 IDA-56850 Loan Disb 24,000,000.00
Jun 15, 2019 IDA-56850 Int Charges 8,989.02
Jun 15, 2019 IDA-56850 Int Charges 8,989.02
Jun 15, 2019 IDA-56850 Int Charges 296,799.80
Jun 15, 2019 IDA-56850 Int Charges 296,799.80
Jun 15, 2023 IDA-56850 Int Charges 198,521.95
Jun 15, 2023 IDA-56850 Loan Repay 2,585,311.80
Jun 15, 2023 IDA-56850 Int Charges 508,351.56
Jun 15, 2023 IDA-56850 Int Charges 508,351.56
Jun 28, 2023 IDA-56850 Loan Disb 68,973.53
Jun 27, 2023 IDA-56850 Loan Disb 17,476.71
May 30, 2023 IDA-56850 Loan Disb 222,545.52
Dec 15, 2023 IDA-56850 Loan Repay 2,562,656.20
Dec 15, 2023 IDA-56850 Loan Repay 34,588.04
Oct 19, 2023 IDA-56850 Loan Disb 16,603.06
Dec 15, 2023 IDA-56850 Int Charges 528,526.00
Dec 15, 2023 IDA-56850 Int Charges 528,526.00
Aug 17, 2021 IDA-56850 Loan Disb 5,000,000.00
Jun 15, 2022 IDA-56850 Loan Repay 2,543,161.50
Jun 15, 2022 IDA-56850 Int Charges 493,897.06
Jun 15, 2022 IDA-56850 Int Charges 493,897.06
Jun 15, 2022 IDA-56850 Int Charges 1,725,347.10
May 17, 2022 IDA-56850 Loan Disb 4,000,000.00
Jun 15, 2020 IDA-56850 Int Charges 346,454.84
Jun 15, 2020 IDA-56850 Int Charges 346,454.84
Jun 15, 2020 IDA-56850 Int Charges 566,886.40
Jun 15, 2020 IDA-56850 Int Charges 8,564.23
Sep 4, 2020 IDA-56850 Loan Disb 6,000,000.00
Oct 16, 2020 IDA-56850 Loan Disb 10,000,000.00
Dec 15, 2020 IDA-56850 Int Charges 10,986.24
Dec 15, 2020 IDA-56850 Loan Repay 2,785,511.00
Dec 15, 2020 IDA-56850 Int Charges 411,451.72
Dec 15, 2020 IDA-56850 Int Charges 411,451.72
Dec 15, 2020 IDA-56850 Int Charges 581,324.25
Feb 16, 2021 IDA-56850 Loan Disb 10,000,000.00
Jun 15, 2021 IDA-56850 Int Charges 104,514.99
Jun 15, 2021 IDA-56850 Loan Repay 2,787,816.20
Jun 15, 2021 IDA-56850 Int Charges 468,325.62
Jun 15, 2021 IDA-56850 Int Charges 468,325.62
Jun 15, 2021 IDA-56850 Int Charges 732,855.60
Feb 11, 2020 IDA-56850 Loan Disb 5,000,000.00
Dec 15, 2019 IDA-56850 Int Charges 4,232.42
Dec 15, 2019 IDA-56850 Int Charges 4,232.42
Dec 15, 2019 IDA-56850 Int Charges 329,629.84
Dec 15, 2019 IDA-56850 Int Charges 329,629.84
Dec 15, 2019 IDA-56850 Int Charges 547,843.44
Jun 8, 2020 IDA-56850 Loan Disb 5,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2025-03-10
Procurement Satisfactory 2025-03-10
Financial Management Satisfactory 2025-03-10
Progress towards achievement of PDO Satisfactory 2025-03-10
Monitoring and Evaluation Satisfactory 2025-03-10
Overall Implementation Progress (IP) Satisfactory 2025-03-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00504171.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Rural M&E system established, populated and used in decision makingValue0.00100.000.00
    DateJune 24, 2015June 30, 2021
    Comment
  • Fully functioning CBOsValue0.00100.000.00
    DateJune 24, 2015June 30, 2021
    Comment
  • Female beneficiariesValue0.0052.370.00
    DateJune 24, 2015
    Comment
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.00102248.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People in urban areas provided with access to improved water source - FemaleValue0.0051124.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.00309883.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People in rural areas provided with access to improved water sources - FemaleValue0.00173535.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to "improved sanitation facilities” under the proj.Value0.00153773.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People in rural and estates areas provided with access to improved sanitation facilities - FemaleValue0.0077578.000.00
    DateJune 24, 2015December 31, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Proportion of grievances registered related to project delivery that have been redressedValue0.00100.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • New piped household water connections resulting from project intervention (Estates)Value0.004355.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Piped household water connections that are benefiting from rehabilitation works undertaken by the projectValue0.0044155.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to Improved Sanitation (Rural)Value0.0054548.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to Improved Sanitation - Rural FemaleValue0.0027274.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to Improved Sanitation - EstatesValue0.007185.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to Improved Sanitation - Estates FemaleValue0.003593.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People trained to improve hygiene behavior/sanitation practices under the projValue0.00135833.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People trained to improve hygiene behavior/sanitation practices - femaleValue0.0076066.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People trained in improved hygiene behavior or sanitation practices (Estates)Value0.0018584.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People in Estates trained in improved hygiene behavior - FemaleValue0.0013009.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Households gaining access to safe disposal of fecal sludge in urban areas contributing to reductions in GHG emissionsValue0.0010500.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Number of other water service providers that the project is supportingValue0.002855.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • People provided with access to improved sanitation outside water supply service areasValue0.0092040.000.00
    DateFebruary 25, 2019December 31, 2021
    Comment
  • Schools provided with access to improved sanitationValue0.0031.000.00
    DateFebruary 25, 2019December 31, 2021
    Comment
  • Sanitation units for differently abled beneficiaries and indigenous communitiesValue0.00286.000.00
    DateFebruary 25, 2019December 31, 2021
    Comment
  • New CBOs established under additional financing with at least one woman in a leadership positionValue0.000.000.00
    DateMay 13, 2021December 31, 2021
    Comment
  • Number of CBOs visited and evaluated by DNCWSValue0.001402.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • Comprehensive sector program prepared and approved by MinistryValue0.001.000.00
    DateSeptember 30, 2015December 31, 2021
    Comment
  • New piped household water connections that are resulting from the project intervention (Urban)Value0.0025562.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • DNCWS organizational structure designed and approved by MinistryValue0.000.000.00
    DateJune 24, 2015December 31, 2021
    Comment
  • New piped household water connections that are resulting from the project intervention (Rural)Value0.0027872.000.00
    DateJune 24, 2015December 31, 2021
    Comment