Financier | Commitments |
---|---|
Borrower/Recipient | 170.00 |
International Bank for Reconstruction and Development | 400.00 |
P147864
Closed
Dipan Bose , Reenu Aneja
INDIA
November 22, 2013
(as of board presentation)
March 29, 2019
January 7, 2020
US$ 570.00 million
Transport Department,UP Police Traffic Directorate,UP-PWD
2019
US$ 400.00 million
A
Not Applicable
April 30, 2024
Yes
BANK APPROVED
April 8, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 170.00 |
International Bank for Reconstruction and Development | 400.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 570.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 15, 2024 | IBRD-89400 | Int Charges | 201.15 |
Feb 26, 2020 | IBRD-89400 | Loan Disb | 10,207,208.00 |
Jun 15, 2024 | IBRD-89400 | Int Charges | 73,736.73 |
Jun 15, 2024 | IBRD-89400 | Int Charges | 4,304,505.50 |
Feb 6, 2024 | IBRD-89400 | Loan Cancel | 203,501,488.00 |
Mar 29, 2019 | IBRD-89400 | Loan Commitment | 400,000,000.00 |
Dec 6, 2023 | IBRD-89400 | Loan Disb | 3,263,120.00 |
Dec 15, 2023 | IBRD-89400 | Int Charges | 65,441.48 |
Dec 15, 2023 | IBRD-89400 | Int Charges | 258,962.69 |
Dec 15, 2023 | IBRD-89400 | Int Charges | 3,961,676.50 |
Dec 15, 2022 | IBRD-89400 | Int Charges | 261,925.90 |
Dec 15, 2022 | IBRD-89400 | Int Charges | 2,369,989.20 |
Feb 24, 2023 | IBRD-89400 | Loan Disb | 1,287,493.10 |
Jun 15, 2023 | IBRD-89400 | Int Charges | 68.38 |
Jun 15, 2023 | IBRD-89400 | Int Charges | 156,918.06 |
Jun 15, 2023 | IBRD-89400 | Int Charges | 258,373.75 |
Jun 15, 2023 | IBRD-89400 | Int Charges | 3,457,195.50 |
Dec 15, 2021 | IBRD-89400 | Int Charges | 1,703.99 |
Dec 15, 2021 | IBRD-89400 | Int Charges | 6,243.22 |
Dec 15, 2021 | IBRD-89400 | Int Charges | 289,582.70 |
Dec 15, 2021 | IBRD-89400 | Int Charges | 541,642.10 |
Nov 18, 2022 | IBRD-89400 | Loan Disb | 369,824.12 |
Dec 8, 2021 | IBRD-89400 | Loan Disb | 8,026,486.00 |
Jun 27, 2022 | IBRD-89400 | Loan Disb | 9,163,012.00 |
Mar 3, 2022 | IBRD-89400 | Loan Disb | 4,582,855.50 |
Jun 15, 2022 | IBRD-89400 | Int Charges | 384.83 |
Jun 15, 2022 | IBRD-89400 | Int Charges | 1,300.73 |
Jun 15, 2022 | IBRD-89400 | Int Charges | 273,684.38 |
Jun 15, 2022 | IBRD-89400 | Int Charges | 686,821.00 |
Dec 2, 2020 | IBRD-89400 | Loan Disb | 12,269,055.00 |
Jul 22, 2021 | IBRD-89400 | Loan Disb | 5,667,817.50 |
Jun 15, 2021 | IBRD-89400 | Int Charges | 412,812.06 |
Jun 15, 2021 | IBRD-89400 | Int Charges | 161,573.69 |
Jun 15, 2021 | IBRD-89400 | Int Charges | 136,954.56 |
Jun 15, 2021 | IBRD-89400 | Int Charges | 5,803.94 |
Jun 15, 2021 | IBRD-89400 | Int Charges | 22,539.63 |
Mar 31, 2021 | IBRD-89400 | Loan Disb | 6,160,765.00 |
Jun 1, 2021 | IBRD-89400 | Loan Disb | 17,770,178.00 |
Oct 19, 2020 | IBRD-89400 | Loan Cancel | 70,000,000.00 |
Dec 15, 2020 | IBRD-89400 | Int Charges | 13,838.32 |
Dec 15, 2020 | IBRD-89400 | Int Charges | 417,807.62 |
Dec 15, 2020 | IBRD-89400 | Int Charges | 286,870.53 |
Dec 15, 2020 | IBRD-89400 | Int Charges | 1,342.83 |
Jan 19, 2021 | IBRD-89400 | Loan Disb | 9,230,648.00 |
Jun 1, 2020 | IBRD-89400 | Loan Disb | 14,042,175.00 |
Jun 15, 2020 | IBRD-89400 | Int Charges | 493,327.88 |
Jun 15, 2020 | IBRD-89400 | Int Charges | 216,555.69 |
Sep 30, 2020 | IBRD-89400 | Loan Disb | 9,625,828.00 |
Jan 7, 2020 | IBRD-89400 | Loan Disb | 1,000,000.00 |
Jan 7, 2020 | IBRD-89400 | Fee Charges | 1,000,000.00 |
Feb 26, 2020 | IBRD-89400 | Loan Disb | 13,832,050.00 |
Jun 15, 2024 | IBRD-89400 | Int Charges | 29,490.18 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Unsatisfactory | 2024-02-06 |
Overall Implementation Progress (IP) | Unsatisfactory | 2024-02-06 |
Procurement | Unsatisfactory | 2024-02-06 |
Progress towards achievement of PDO | Unsatisfactory | 2024-02-06 |
Counterpart Funding | Satisfactory | 2024-02-06 |
Project Management | Moderately Unsatisfactory | 2024-02-06 |
Monitoring and Evaluation | Satisfactory | 2024-02-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2024 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction of average travel time for cars on civil works corridors | Value | SH42 Hamirpur -Rath -133SH42 Garautha Chirgaon - | SH42 Hamirpur -Rath - 68.5SH42 Garautha Chirgaon | |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
Improved Road Users Perception (RUSS) Index on civil works corridors | Value | survey to be done in 2019 | An average of above 95 percent response recorded a | |
Date | March 20, 2019 | December 7, 2022 | ||
Comment |
UP Highway Police in place doing general deterrence-based enforcement on pilot corridors | Value | No | No | |
Date | November 6, 2018 | December 7, 2022 | ||
Comment |
Reduced number of fatalities on Highway Police pilot corridors (NH25 and NH2) | Value | 0.00 | 0.00 | 0.00 |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
Crash data from UPCDAS is publicly available and used for analysis and planning interventions | Value | No | Yes | |
Date | November 6, 2018 | December 7, 2022 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Non-rural | Value | 0.00 | 258.00 | 0.00 |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
RAMS operationalized and used for annual maintenance planning | Value | RAMS is not used for annual planning | RAMS in use. | i. Data in pilot district collectedii. Module for |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
UP Highway Police established, equipped and trained | Value | UP Highway Police does not exist | UP Highway Police does not exist. | UPHP created, pilot rolled out |
Date | November 13, 2018 | December 31, 2021 | ||
Comment |
Satisfactory post-construction road safety audit | Value | No | Yes | |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
Improved Driving Behaviors (Use of helmets and seatbelts ) on Highway Police Pilot Corridors | Value | To be collected in 2019 | To be collected | |
Date | November 13, 2018 | December 31, 2021 | ||
Comment |
Women employed for routine maintenance under EPC contracts | Value | 0.00 | 13.00 | 0.00 |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
RS Cell at Transport Department staffed and supporting implementation of the state RS policy | Value | RS Cell established but not staffed | RS Cell established and staffed | |
Date | November 13, 2018 | December 31, 2021 | ||
Comment |
Assessment of gender actions conducted | Value | No | No | |
Date | November 13, 2018 | December 7, 2022 | ||
Comment |
Road safety engineering improvement program implemented on CRN | Value | Program not yet started | Program not yet started. | |
Date | November 13, 2018 | December 31, 2021 | ||
Comment |