Financier | Commitments |
---|---|
Indonesia - AUSAID TF for Insfrastructure Support | 1.25 |
P147893
Closed
Thalyta Yuwono , Elisabeth Goller
Ministry of Finance
February 28, 2014
(as of board presentation)
March 26, 2014
N/A
US$ 1.25 million
Bappenas
2014
US$ 1.25 million
C
Not Applicable
September 30, 2016
BANK APPROVED
August 15, 2024
Financier | Commitments |
---|---|
Indonesia - AUSAID TF for Insfrastructure Support | 1.25 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.25 |
Total Project Cost** | 1.25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Completed Feasibility Analysis as a basis for Reference Design | Value | No written CGS adoption | Market analysis and Alternative analysis, or the P | CGS's written adoption of the completed Feasibilit |
Date | February 3, 2014 | March 29, 2017 | September 30, 2016 | |
Comment |
Full Completed Feasibility Report as a basis for tendering the follow on investment | Value | No written acceptance of the institutional framewo | The completed report of Phase 1 has been submitted | CGS's written acceptance of the institutional fram |
Date | February 3, 2014 | September 29, 2016 | September 30, 2016 | |
Comment |
Recommended institutional framework and related actions and decisions by CGS to execute the plans | Value | No institutional framework is designed for this RE | Surabaya has sent acceptance letter to Bappenas fo | CGS' written acceptance of institutional framework |
Date | February 3, 2014 | September 29, 2016 | September 30, 2016 | |
Comment |
Completed feasibility report, satisfactory to the CGS as a basis for tendering the desired follow on investment and the preparationthereof. | Value | No | No | Yes |
Date | February 3, 2014 | March 29, 2017 | March 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Successful tender of Feasibility Study | Value | start of tender process | Firm consultant have been mobilized and has submit | Contract signed by the consultant |
Date | February 3, 2014 | February 25, 2016 | February 25, 2016 | |
Comment |
Successful Completion of Feasibility Report Phase 1 | Value | Start of consultant contract and mobilization of c | Phase 1 report consist of Market Assessment and Al | Completion of Phase 1 report submitted to Bappenas |
Date | February 25, 2016 | September 29, 2016 | April 15, 2016 | |
Comment |
Successful Completion of Feasibility Report Phase 2 | Value | Approval from Steering Committee to continue with | The GOI requested to close this activity following | Completion and submission of Feasibility Report Ph |
Date | February 3, 2016 | March 29, 2017 | March 31, 2017 | |
Comment |