Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
P148017
Closed
Fatima El Kadiri El Yamani
Kingdom of Morocco
November 5, 2014
(as of board presentation)
April 24, 2015
September 21, 2015
US$ 100.00 million
Ministry of Health
2015
US$ 100.00 million
N/A
September 7, 2023
September 30, 2021
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2021 | IBRD-85070 | Int Charges | 356,358.97 |
Jul 15, 2021 | IBRD-85070 | Int Charges | 379,107.53 |
Jul 15, 2021 | IBRD-85070 | Loan Repay | 1,857,700.40 |
Jul 15, 2021 | IBRD-85070 | Loan Repay | 616,100.00 |
Oct 15, 2021 | IBRD-91470 | Int Charges | 401,585.62 |
Oct 15, 2021 | IBRD-91470 | Int Charges | 18,681.34 |
Nov 12, 2021 | IBRD-85070 | Loan Disb | -68,318,056.00 |
Nov 12, 2021 | IBRD-85070 | Loan Disb | 68,318,056.00 |
Nov 12, 2021 | IBRD-85070 | Loan Disb | -68,705,888.00 |
Nov 12, 2021 | IBRD-85070 | Loan Disb | 68,318,056.00 |
Jan 15, 2021 | IBRD-85070 | Int Charges | 386,686.56 |
Jan 15, 2021 | IBRD-85070 | Loan Repay | 1,507,630.00 |
Jan 15, 2021 | IBRD-85070 | Loan Repay | 616,100.00 |
Jan 15, 2021 | IBRD-85070 | Int Charges | 1,207.30 |
Mar 16, 2021 | IBRD-85070 | Loan Disb | 13,019,974.00 |
Mar 5, 2021 | IBRD-91470 | Loan Disb | 11,312,500.00 |
Jan 19, 2021 | IBRD-91470 | Loan Disb | 13,100,000.00 |
Jan 19, 2021 | IBRD-85070 | Loan Disb | 290,685.10 |
Jan 15, 2021 | IBRD-85070 | Int Charges | 11,803.40 |
Jan 15, 2021 | IBRD-85070 | Int Charges | 16,732.72 |
Jan 15, 2021 | IBRD-85070 | Int Charges | 342,378.20 |
Apr 15, 2021 | IBRD-91470 | Loan Disb | -24,412,500.00 |
Apr 15, 2021 | IBRD-91470 | Loan Disb | 24,412,500.00 |
Jun 18, 2020 | IBRD-85070 | Loan Disb | 6,546,266.50 |
Sep 8, 2020 | IBRD-91470 | Loan Disb | 7,812,500.00 |
Oct 15, 2020 | IBRD-91470 | Loan Disb | -10,587,500.00 |
Aug 26, 2020 | IBRD-91470 | Loan Disb | 2,687,500.00 |
Oct 15, 2020 | IBRD-91470 | Loan Disb | 10,587,500.00 |
Jul 15, 2020 | IBRD-85070 | Int Charges | 23,478.23 |
Jul 15, 2020 | IBRD-85070 | Int Charges | 717,470.56 |
Jul 15, 2020 | IBRD-85070 | Int Charges | 394,142.40 |
Jul 15, 2020 | IBRD-85070 | Loan Repay | 1,339,391.00 |
Jul 15, 2020 | IBRD-85070 | Loan Repay | 616,100.00 |
Aug 14, 2020 | IBRD-91470 | Loan Disb | 87,500.00 |
Aug 14, 2020 | IBRD-91470 | Fee Charges | 87,500.00 |
Jan 15, 2020 | IBRD-85070 | Int Charges | 841,693.80 |
Jan 15, 2020 | IBRD-85070 | Int Charges | 405,262.50 |
Jan 15, 2020 | IBRD-85070 | Loan Repay | 1,339,391.00 |
Mar 11, 2019 | IBRD-85070 | Loan Disb | 17,380,624.00 |
Jan 15, 2018 | IBRD-85070 | Int Charges | 79,109.52 |
Jan 15, 2018 | IBRD-85070 | Int Charges | 92,869.26 |
Jan 15, 2018 | IBRD-85070 | Int Charges | 400,212.47 |
Jul 15, 2018 | IBRD-85070 | Int Charges | 37,698.19 |
Jul 15, 2018 | IBRD-85070 | Int Charges | 60,134.58 |
Jul 15, 2018 | IBRD-85070 | Int Charges | 348,340.75 |
Jul 15, 2018 | IBRD-85070 | Int Charges | 401,475.00 |
Jul 15, 2018 | IBRD-85070 | Int Charges | 4,734.31 |
Jan 15, 2017 | IBRD-85070 | Int Charges | 93,967.67 |
Jan 15, 2017 | IBRD-85070 | Int Charges | 218,103.88 |
Jul 15, 2017 | IBRD-85070 | Int Charges | 92,669.54 |
Jul 15, 2017 | IBRD-85070 | Loan Disb | -25,250,000.00 |
Jul 15, 2017 | IBRD-85070 | Loan Disb | 25,250,000.00 |
Aug 29, 2017 | IBRD-85070 | Loan Disb | 10,883,470.00 |
Jul 15, 2017 | IBRD-85070 | Int Charges | 262,789.38 |
Dec 1, 2017 | IBRD-85070 | Loan Disb | 15,360,182.00 |
Sep 21, 2015 | IBRD-85070 | Loan Disb | 250,000.00 |
Sep 21, 2015 | IBRD-85070 | Fee Charges | 250,000.00 |
Jan 15, 2016 | IBRD-85070 | Int Charges | 894.18 |
Jan 15, 2016 | IBRD-85070 | Int Charges | 93,610.84 |
Feb 4, 2016 | IBRD-85070 | Loan Disb | 25,000,000.00 |
Jul 15, 2016 | IBRD-85070 | Int Charges | 96,342.20 |
Jul 15, 2016 | IBRD-85070 | Int Charges | 174,058.77 |
Apr 15, 2021 | IBRD-91470 | Int Charges | 45,376.94 |
Apr 15, 2021 | IBRD-91470 | Int Charges | 127,050.00 |
Oct 15, 2021 | IBRD-91470 | Int Charges | 127,050.00 |
Jul 15, 2021 | IBRD-85070 | Int Charges | 5,358.64 |
Jan 15, 2020 | IBRD-85070 | Loan Repay | 616,100.00 |
Jan 15, 2020 | IBRD-85070 | Int Charges | 25,019.98 |
Jul 15, 2019 | IBRD-85070 | Int Charges | 31,164.65 |
Jul 15, 2019 | IBRD-85070 | Int Charges | 912,937.40 |
Jul 15, 2019 | IBRD-85070 | Int Charges | 406,525.03 |
Oct 19, 2018 | IBRD-85070 | Loan Disb | 11,268,797.00 |
Jan 15, 2019 | IBRD-85070 | Int Charges | 54,339.12 |
Jan 15, 2019 | IBRD-85070 | Int Charges | 533,544.56 |
Jan 15, 2019 | IBRD-85070 | Int Charges | 403,999.97 |
Jan 15, 2024 | IBRD-85070 | Int Charges | 330,219.47 |
Jan 15, 2024 | IBRD-85070 | Loan Repay | 616,100.00 |
Jan 15, 2024 | IBRD-85070 | Int Charges | 282,809.88 |
Jan 15, 2024 | IBRD-85070 | Loan Repay | 1,765,823.80 |
Jul 15, 2024 | IBRD-85070 | Int Charges | 324,148.90 |
Jul 15, 2024 | IBRD-85070 | Loan Repay | 1,760,096.50 |
Jul 15, 2024 | IBRD-85070 | Int Charges | 290,297.56 |
Jun 16, 2020 | IBRD-91470 | Loan Commitment | 35,000,000.00 |
Apr 24, 2015 | IBRD-85070 | Loan Commitment | 100,000,000.00 |
Jul 15, 2024 | IBRD-85070 | Loan Repay | 616,100.00 |
Apr 15, 2023 | IBRD-91470 | Int Charges | 127,050.00 |
Apr 15, 2023 | IBRD-91470 | Int Charges | 401,585.62 |
Jan 15, 2023 | IBRD-85070 | Int Charges | 0.02 |
Jan 15, 2023 | IBRD-85070 | Int Charges | -0.02 |
Jan 15, 2023 | IBRD-85070 | Int Charges | 311,894.12 |
Jan 15, 2023 | IBRD-85070 | Loan Repay | 1,744,286.20 |
Jan 15, 2023 | IBRD-85070 | Int Charges | 350,242.75 |
Jan 15, 2023 | IBRD-85070 | Loan Repay | 616,100.00 |
Jul 15, 2023 | IBRD-85070 | Int Charges | 333,949.90 |
Jul 15, 2023 | IBRD-85070 | Loan Repay | 616,100.00 |
Jul 15, 2023 | IBRD-85070 | Int Charges | 309,285.75 |
Jul 15, 2023 | IBRD-85070 | Loan Repay | 1,810,108.40 |
Oct 15, 2023 | IBRD-91470 | Int Charges | 127,050.00 |
Oct 15, 2023 | IBRD-91470 | Int Charges | 401,585.62 |
Apr 15, 2024 | IBRD-91470 | Int Charges | 127,050.00 |
Apr 15, 2024 | IBRD-91470 | Int Charges | 401,585.62 |
Apr 15, 2022 | IBRD-91470 | Int Charges | 127,050.00 |
Apr 15, 2022 | IBRD-91470 | Int Charges | 401,585.62 |
Jul 15, 2022 | IBRD-85070 | Loan Repay | 616,100.00 |
Jul 15, 2022 | IBRD-85070 | Int Charges | 298,303.56 |
Jul 15, 2022 | IBRD-85070 | Loan Repay | 1,619,400.20 |
Jul 15, 2022 | IBRD-85070 | Int Charges | 361,362.84 |
Jan 15, 2022 | IBRD-85070 | Int Charges | 224,439.25 |
Jan 15, 2022 | IBRD-85070 | Int Charges | 370,266.00 |
Jan 15, 2022 | IBRD-85070 | Loan Repay | 616,100.00 |
Jan 15, 2022 | IBRD-85070 | Int Charges | 126,757.67 |
Jan 15, 2022 | IBRD-85070 | Loan Repay | 1,847,617.40 |
Oct 15, 2022 | IBRD-91470 | Int Charges | 127,050.00 |
Oct 15, 2022 | IBRD-91470 | Int Charges | 401,585.62 |
Jul 15, 2022 | IBRD-85070 | Int Charges | -298,303.56 |
Jul 15, 2022 | IBRD-85070 | Loan Repay | -1,619,400.20 |
Jul 15, 2022 | IBRD-85070 | Int Charges | 294,898.03 |
Jul 15, 2022 | IBRD-85070 | Loan Repay | 1,622,805.80 |
Apr 15, 2021 | IBRD-91470 | Int Charges | 18,703.19 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2021-05-04 |
Overall Implementation Progress (IP) | Satisfactory | 2021-05-04 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-05-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2022 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in number of pregnant women receiving antenatal care during a visit to a rural ESSP in the Program Area | Value | 161829 | 189178 | 5.83% increase from baseline |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
Number of Polymerase Chain Reaction (PCR) tests conducted to diagnose COVID-19 | Value | 94.00 | 2364454.00 | 629000.00 |
Date | March 20, 2020 | September 30, 2021 | December 31, 2020 | |
Comment |
Increase in number of deliveries of rural women attended by skilled health personnel in public health facilities in the Program Area | Value | 180812 | 181372 | 181734 |
Date | December 31, 2014 | September 30, 2021 | June 9, 2022 | |
Comment |
Number health care facilities designated COVID-19 facilities and equipped as per MoH guidelines | Value | 0.00 | 72.00 | 50.00 |
Date | March 20, 2020 | September 30, 2021 | December 31, 2020 | |
Comment |
Increase in number of new visits of children under 5 to a rural ESSP in the Program Area for curative care | Value | 1013436 | 1078295 | 5.00% increase from baseline |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
Increase in number of patients with diabetes diagnosed and treated at a rural ESSP in the Program Area | Value | 136238 | 225474 | 17.63% increase from baseline |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in number of visits to rural ESSPs in the Program Area | Value | 3794877 | 4098247 | 4.30% increase from baseline |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
% of rural health centers with delivery services (CSCAs) in the Program Area that participate in the main biennial quality assessment (concours qualité) | Value | 13% | 43.4 | NA |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
Number of designated laboratories with COVID-19 diagnostic capacities established per MoH guidelines | Value | 2 | 111 | 111 |
Date | March 20, 2020 | September 30, 2021 | December 31, 2020 | |
Comment |
Number of patients with hypertension diagnosed and treated in rural ESSPs | Value | 180000.00 | 312326.00 | 287000.00 |
Date | December 31, 2014 | September 30, 2021 | December 31, 2020 | |
Comment |
Number of resuscitation units established as per MoH guidelines | Value | 0 | 0 | 55 |
Date | March 20, 2020 | September 30, 2021 | December 31, 2020 | |
Comment |
Establishment of a comprehensive GRM | Value | GRM not established | Pilot GRM evaluated Implementation Manual reviewed | Roll out of the comprehensive GRM |
Date | December 31, 2014 | September 30, 2021 | December 31, 2018 | |
Comment |
Definition of an HR incentive mechanism in rural ESSPs | Value | Diagnostic not completed | diagnostic study completed | Implementation mechanism defined, including target |
Date | December 31, 2014 | September 30, 2021 | June 30, 2020 | |
Comment |
Establishment of an HMIS in the Program Area | Value | HMIS not established | he SMIPF-SC has been operationalized in the 100% o | The SMIPF-SC has been operationalized in the 100% |
Date | December 31, 2014 | September 30, 2021 | June 30, 2020 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services | Value | 0.00 | 181372.00 | 193939.00 |
Date | December 31, 2014 | September 30, 2021 | June 30, 2020 | |
Comment |
Number of deliveries attended by skilled health personnel | Value | 0.00 | 181372.00 | 193939.00 |
Date | December 31, 2014 | September 30, 2021 | June 30, 2020 | |
Comment |