Financier | Commitments |
---|---|
UN Children's Fund | 1.00 |
Education for All Supervising Entity | 37.80 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 12.00 |
Ebola Recovery and Reconstruction MPF | 1.00 |
P148127
Closed
Karine M. Pezzani , Assane Dieng
Republic of Guinea
August 24, 2014
(as of board presentation)
July 10, 2015
October 19, 2015
US$ 51.80 million
Ministry of National Education and Literacy
2016
US$ 51.80 million
B
July 17, 2024
August 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
UN Children's Fund | 1.00 |
Education for All Supervising Entity | 37.80 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 12.00 |
Ebola Recovery and Reconstruction MPF | 1.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 51.80 |
Total Project Cost** | 51.80 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2019-06-13 |
Progress towards achievement of PDO | Moderately Satisfactory | 2019-06-13 |
Procurement | Satisfactory | 2019-06-13 |
Monitoring and Evaluation | Moderately Satisfactory | 2019-06-13 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2019-06-13 |
Project Management | Moderately Satisfactory | 2019-06-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-26-2020 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-17-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Enrollment capacity of new classrooms (once completed and equipped) at the lower secondary level resulting from project interventions | Value | 0.00 | 11520.00 | 5000.00 |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Number of words per minute measured in EGRA sub-test 8a in CP2 (experimental schools) | Value | 7.00 | 22.00 | 0.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Analytical reports (using collected data) available and disclosed | Value | 0.00 | 5.00 | 5.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Beneficiaries in NAFA centers (cumulative) | Value | 0.00 | 13054.00 | 13000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Additional enrollment in Literacy campaign (project areas) | Value | 0.00 | 97000.00 | 97000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Of which female | Value | 0.00 | 9489.00 | 10400.00 |
Date | April 30, 2015 | August 31, 2019 | August 30, 2019 | |
Comment |
Of which female | Value | 0.00 | 67900.00 | 67900.00 |
Date | April 30, 2015 | June 7, 2019 | August 31, 2019 | |
Comment |
Primary schools in which the conditions of water points are below standards | Value | 77.00 | 71.00 | 66.00 |
Date | April 1, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Gross enrollment rate at the primary level | Value | 83.70 | 90.60 | 0.00 |
Date | April 1, 2015 | August 31, 2019 | ||
Comment |
Gross enrollment rate at the primary level, girls | Value | 74.90 | 82.30 | 0.00 |
Date | April 1, 2015 | August 31, 2019 | ||
Comment |
Enrollment capacity of new classrooms (delivered and equipped) at the primary level resulting from project interventions | Value | 0.00 | 17150.00 | 4200.00 |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 2747514.00 | 2450000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Female beneficiaries | Value | 0.00 | 45.00 | 45.00 |
Date | April 30, 2015 | November 27, 2018 | ||
Comment |
Primary schools in which the conditions of latrines are below standards | Value | 30.00 | 21.00 | 20.00 |
Date | April 1, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of additional classrooms built by project interventions | Value | 0.00 | 582.00 | 580.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Tools for statistical analysis of EMIS data designed and disseminated | Value | No | Yes | Yes |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Beneficiary of decentralized grants | Value | 0.00 | 7727.00 | 7580.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Staff affectation following procedures | Value | 91.00 | 95.00 | 95.00 |
Date | January 1, 2017 | August 31, 2019 | August 31, 2019 | |
Comment |
Primary | Value | 0.00 | 402.00 | 400.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Schools | Value | 0.00 | 7256.00 | 7115.00 |
Date | April 30, 2015 | June 7, 2019 | August 31, 2019 | |
Comment |
DRH, DGSPDE and SNFPP database has been harmonized | Value | No | Yes | |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Lower secondary | Value | 0.00 | 180.00 | 180.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
DPE/DCE/IRE/DSEE | Value | 0.00 | 471.00 | 465.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Number of standalone latrines built by project interventions | Value | 0.00 | 233.00 | 233.00 |
Date | April 1, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
MEN-A, Civil service Ministry, and Ministry of Finance teachers database has been harmonized | Value | No | No | |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Teaching and Learning Materials produced and distributed | Value | 0.00 | 9069225.00 | 3520000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Number of standalone water points built by project interventions | Value | 0.00 | 565.00 | 403.00 |
Date | April 1, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Renewed School Mapping used | Value | No | Yes | Yes |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Preschool | Value | 0.00 | 52000.00 | 50000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
NAFA centers renewed | Value | 0.00 | 226.00 | 121.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
A Skills Transfer Plan is established, being implemented, and regularly monitored. | Value | No | Yes | |
Date | April 30, 2015 | August 31, 2019 | ||
Comment |
Primary | Value | 0.00 | 8042240.00 | 3000000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Lower secondary | Value | 0.00 | 974985.00 | 470000.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Number of teachers trained | Value | 0.00 | 17430.00 | 10131.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Number of Primary school teachers trained | Value | 0.00 | 11552.00 | 8424.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
Number of Lower secondary school teachers trained | Value | 0.00 | 1740.00 | 1740.00 |
Date | April 30, 2015 | August 31, 2019 | August 31, 2019 | |
Comment |
School performance appraisal system established and communicated to schools and deconcentrated levels of MEPU-A, and data collection for baseline completed | Value | No | Yes | |
Date | May 30, 2014 | August 31, 2019 | ||
Comment |