GUINEA - Pooled-Fund for Basic Education

Abstract*

The development objectives of the Pooled-Fund for Basic Education (FoCEB) Project for Guinea are to: (i) improve access and learning in basic education and literacy of under-served populations, (ii) strengthen the ministry of pre-university education and literacy’s capacity in evidence-based management, and (iii) support the implementation of the education sector’s short-term Ebola strategic response plan. The project comprises of three components...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives are to (i) improve access and learning in basic education and literacy of under-served populations, (ii) strengthen the Ministry of Pre-University Education and Literacy's capacity in evidence-based management,and (iii) support the implementation of the Education sector's short-term Ebola strategic response plan.

Key Details

Project Details

  • P148127

  • Closed

  • Karine M. Pezzani , Assane Dieng

  • Republic of Guinea

  • Guinea

  • August 24, 2014

  • (as of board presentation)

    July 10, 2015

  • October 19, 2015

  • US$ 51.80 million

  • Ministry of National Education and Literacy

  • Western and Central Africa

  • 2016

  • US$ 51.80 million

  • B

  • July 17, 2024

  • August 31, 2019

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
UN Children's Fund 1.00
Education for All Supervising Entity 37.80
FRANCE: Govt. of [MOFA and AFD (C2D)] 12.00
Ebola Recovery and Reconstruction MPF 1.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 51.80
Total Project Cost** 51.80

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2019-06-13
Progress towards achievement of PDO Moderately Satisfactory 2019-06-13
Procurement Satisfactory 2019-06-13
Monitoring and Evaluation Moderately Satisfactory 2019-06-13
Overall Implementation Progress (IP) Moderately Satisfactory 2019-06-13
Project Management Moderately Satisfactory 2019-06-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-26-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-17-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Enrollment capacity of new classrooms (once completed and equipped) at the lower secondary level resulting from project interventionsValue0.0011520.005000.00
    DateApril 30, 2015August 31, 2019
    Comment
  • Number of words per minute measured in EGRA sub-test 8a in CP2 (experimental schools)Value7.0022.000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Analytical reports (using collected data) available and disclosedValue0.005.005.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Beneficiaries in NAFA centers (cumulative)Value0.0013054.0013000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Additional enrollment in Literacy campaign (project areas)Value0.0097000.0097000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Of which femaleValue0.009489.0010400.00
    DateApril 30, 2015August 31, 2019August 30, 2019
    Comment
  • Of which femaleValue0.0067900.0067900.00
    DateApril 30, 2015June 7, 2019August 31, 2019
    Comment
  • Primary schools in which the conditions of water points are below standardsValue77.0071.0066.00
    DateApril 1, 2015August 31, 2019August 31, 2019
    Comment
  • Gross enrollment rate at the primary levelValue83.7090.600.00
    DateApril 1, 2015August 31, 2019
    Comment
  • Gross enrollment rate at the primary level, girlsValue74.9082.300.00
    DateApril 1, 2015August 31, 2019
    Comment
  • Enrollment capacity of new classrooms (delivered and equipped) at the primary level resulting from project interventionsValue0.0017150.004200.00
    DateApril 30, 2015August 31, 2019
    Comment
  • Direct project beneficiariesValue0.002747514.002450000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Female beneficiariesValue0.0045.0045.00
    DateApril 30, 2015November 27, 2018
    Comment
  • Primary schools in which the conditions of latrines are below standardsValue30.0021.0020.00
    DateApril 1, 2015August 31, 2019August 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of additional classrooms built by project interventionsValue0.00582.00580.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Tools for statistical analysis of EMIS data designed and disseminatedValueNoYesYes
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Beneficiary of decentralized grantsValue0.007727.007580.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Staff affectation following proceduresValue91.0095.0095.00
    DateJanuary 1, 2017August 31, 2019August 31, 2019
    Comment
  • PrimaryValue0.00402.00400.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • SchoolsValue0.007256.007115.00
    DateApril 30, 2015June 7, 2019August 31, 2019
    Comment
  • DRH, DGSPDE and SNFPP database has been harmonizedValueNoYes
    DateApril 30, 2015August 31, 2019
    Comment
  • Lower secondaryValue0.00180.00180.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • DPE/DCE/IRE/DSEEValue0.00471.00465.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Number of standalone latrines built by project interventionsValue0.00233.00233.00
    DateApril 1, 2015August 31, 2019August 31, 2019
    Comment
  • MEN-A, Civil service Ministry, and Ministry of Finance teachers database has been harmonizedValueNoNo
    DateApril 30, 2015August 31, 2019
    Comment
  • Teaching and Learning Materials produced and distributedValue0.009069225.003520000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Number of standalone water points built by project interventionsValue0.00565.00403.00
    DateApril 1, 2015August 31, 2019August 31, 2019
    Comment
  • Renewed School Mapping usedValueNoYesYes
    DateApril 30, 2015August 31, 2019
    Comment
  • PreschoolValue0.0052000.0050000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • NAFA centers renewedValue0.00226.00121.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • A Skills Transfer Plan is established, being implemented, and regularly monitored.ValueNoYes
    DateApril 30, 2015August 31, 2019
    Comment
  • PrimaryValue0.008042240.003000000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Lower secondaryValue0.00974985.00470000.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Number of teachers trainedValue0.0017430.0010131.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Number of Primary school teachers trainedValue0.0011552.008424.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • Number of Lower secondary school teachers trainedValue0.001740.001740.00
    DateApril 30, 2015August 31, 2019August 31, 2019
    Comment
  • School performance appraisal system established and communicated to schools and deconcentrated levels of MEPU-A, and data collection for baseline completedValueNoYes
    DateMay 30, 2014August 31, 2019
    Comment