Financier | Commitments |
---|---|
Borrower/Recipient | 124.27 |
International Bank for Reconstruction and Development | 100.00 |
P148129
Closed
Hei Chiu , Yang Chen
People's Republic of China
August 10, 2014
(as of board presentation)
December 21, 2015
May 26, 2016
US$ 224.27 million
Tianjin PMO
2016
US$ 100.00 million
B
June 24, 2023
December 31, 2022
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 124.27 |
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 224.27 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 27, 2019 | IBRD-85650 | Loan Disb | 369,078.90 |
Dec 9, 2019 | IBRD-85650 | Loan Disb | 782,416.70 |
Jun 24, 2020 | IBRD-85650 | Loan Disb | 2,354,792.50 |
May 15, 2020 | IBRD-85650 | Loan Disb | 97,391.86 |
May 15, 2020 | IBRD-85650 | Int Charges | 97,391.86 |
May 15, 2020 | IBRD-85650 | Loan Disb | 297,496.53 |
May 15, 2020 | IBRD-85650 | Int Charges | 297,496.53 |
Sep 12, 2018 | IBRD-85650 | Loan Disb | 1,041,191.75 |
Nov 29, 2018 | IBRD-85650 | Loan Disb | 2,768,821.50 |
Nov 15, 2018 | IBRD-85650 | Loan Disb | 216,842.55 |
Nov 15, 2018 | IBRD-85650 | Int Charges | 216,842.55 |
May 15, 2018 | IBRD-85650 | Int Charges | 146,180.52 |
May 15, 2018 | IBRD-85650 | Loan Disb | 108,827.84 |
Dec 13, 2018 | IBRD-85650 | Loan Disb | 3,177,540.20 |
Nov 15, 2018 | IBRD-85650 | Loan Disb | 109,775.72 |
Nov 15, 2018 | IBRD-85650 | Int Charges | 109,775.72 |
May 15, 2019 | IBRD-85650 | Int Charges | 100,242.20 |
May 15, 2019 | IBRD-85650 | Loan Disb | 351,275.97 |
May 15, 2019 | IBRD-85650 | Loan Disb | 100,242.20 |
May 15, 2019 | IBRD-85650 | Int Charges | 351,275.97 |
Nov 15, 2019 | IBRD-85650 | Loan Disb | 351,712.10 |
Nov 15, 2019 | IBRD-85650 | Int Charges | 351,712.10 |
May 12, 2017 | IBRD-85650 | Loan Disb | 530,659.40 |
Nov 15, 2017 | IBRD-85650 | Loan Disb | 111,952.97 |
Nov 15, 2017 | IBRD-85650 | Int Charges | 111,952.97 |
Nov 15, 2017 | IBRD-85650 | Loan Disb | 125,004.34 |
Nov 15, 2017 | IBRD-85650 | Int Charges | 125,004.34 |
Oct 20, 2017 | IBRD-85650 | Loan Disb | 449,183.94 |
Dec 8, 2017 | IBRD-85650 | Loan Disb | 487,772.62 |
May 15, 2018 | IBRD-85650 | Int Charges | 108,827.84 |
May 15, 2018 | IBRD-85650 | Loan Disb | 146,180.52 |
Jan 18, 2017 | IBRD-85650 | Loan Disb | 10,000,000.00 |
Nov 15, 2016 | IBRD-85650 | Loan Disb | 138,365.78 |
Nov 15, 2016 | IBRD-85650 | Int Charges | 138,365.78 |
Nov 15, 2016 | IBRD-85650 | Loan Disb | 1,898.20 |
Nov 15, 2016 | IBRD-85650 | Int Charges | 1,898.20 |
May 26, 2016 | IBRD-85650 | Loan Disb | 250,000.00 |
May 26, 2016 | IBRD-85650 | Fee Charges | 250,000.00 |
May 15, 2017 | IBRD-85650 | Loan Disb | 115,376.56 |
May 15, 2017 | IBRD-85650 | Int Charges | 115,376.56 |
May 15, 2017 | IBRD-85650 | Loan Disb | 67,977.58 |
May 15, 2017 | IBRD-85650 | Int Charges | 67,977.58 |
Nov 15, 2022 | IBRD-85650 | Int Charges | 30,108.55 |
Nov 15, 2022 | IBRD-85650 | Int Charges | 1,166,049.20 |
Nov 15, 2022 | IBRD-85650 | Loan Repay | 2,819,774.80 |
Nov 8, 2022 | IBRD-85650 | Loan Disb | 18,935,552.00 |
Sep 14, 2022 | IBRD-85650 | Loan Disb | 8,559,472.00 |
Dec 6, 2022 | IBRD-85650 | Loan Disb | 521,430.38 |
May 15, 2023 | IBRD-85650 | Int Charges | 124,702.38 |
May 15, 2023 | IBRD-85650 | Int Charges | 50.00 |
May 15, 2023 | IBRD-85650 | Int Charges | 2,432,323.80 |
May 15, 2023 | IBRD-85650 | Loan Repay | 3,546,891.00 |
May 15, 2023 | IBRD-85650 | Int Charges | 907.87 |
Nov 15, 2023 | IBRD-85650 | Int Charges | 55,305.91 |
Nov 15, 2023 | IBRD-85650 | Int Charges | 2,803,609.50 |
Nov 15, 2023 | IBRD-85650 | Loan Repay | 3,546,891.00 |
May 15, 2024 | IBRD-85650 | Int Charges | 2,840,121.00 |
May 15, 2024 | IBRD-85650 | Loan Repay | 3,546,891.00 |
May 15, 2024 | IBRD-85650 | Int Charges | 17,505.40 |
Dec 21, 2015 | IBRD-85650 | Loan Commitment | 100,000,000.00 |
Nov 15, 2021 | IBRD-85650 | Loan Repay | 1,354,611.00 |
Nov 15, 2021 | IBRD-85650 | Int Charges | 76,984.72 |
Nov 15, 2021 | IBRD-85650 | Loan Disb | 197,634.62 |
Nov 15, 2021 | IBRD-85650 | Int Charges | 197,634.62 |
Nov 15, 2021 | IBRD-85650 | Loan Disb | 76,984.72 |
May 15, 2022 | IBRD-85650 | Int Charges | 153,263.80 |
May 15, 2022 | IBRD-85650 | Loan Repay | 2,494,946.00 |
May 15, 2022 | IBRD-85650 | Loan Disb | 44,689.24 |
May 15, 2022 | IBRD-85650 | Int Charges | 44,689.24 |
May 15, 2022 | IBRD-85650 | Loan Disb | 174,991.95 |
May 15, 2022 | IBRD-85650 | Int Charges | 174,991.95 |
Dec 9, 2021 | IBRD-85650 | Loan Disb | 7,122,450.00 |
Feb 28, 2022 | IBRD-85650 | Loan Disb | 5,378,290.00 |
Nov 22, 2022 | IBRD-85650 | Loan Disb | -521,430.38 |
Dec 17, 2021 | IBRD-85650 | Loan Disb | 9,797,803.00 |
Jan 3, 2022 | IBRD-85650 | Loan Disb | 9,368,998.00 |
Aug 12, 2020 | IBRD-85650 | Loan Disb | 2,950,912.20 |
Dec 14, 2020 | IBRD-85650 | Loan Disb | 520,325.94 |
Dec 23, 2020 | IBRD-85650 | Loan Disb | 642,964.10 |
Nov 15, 2020 | IBRD-85650 | Loan Disb | 192,821.30 |
Feb 23, 2021 | IBRD-85650 | Loan Disb | 1,122,690.50 |
May 15, 2021 | IBRD-85650 | Loan Disb | 155,227.52 |
May 15, 2021 | IBRD-85650 | Int Charges | 155,227.52 |
May 15, 2021 | IBRD-85650 | Loan Repay | 1,004,839.70 |
May 19, 2021 | IBRD-85650 | Loan Disb | 1,465,607.60 |
May 11, 2021 | IBRD-85650 | Loan Disb | 2,815,855.50 |
May 15, 2021 | IBRD-85650 | Int Charges | 87,456.82 |
Nov 15, 2020 | IBRD-85650 | Int Charges | 192,821.30 |
Nov 15, 2020 | IBRD-85650 | Loan Disb | 93,427.92 |
Nov 15, 2020 | IBRD-85650 | Int Charges | 93,427.92 |
Jul 1, 2021 | IBRD-85650 | Loan Disb | 5,469,032.00 |
May 10, 2021 | IBRD-85650 | Loan Disb | 174,590.45 |
May 15, 2021 | IBRD-85650 | Loan Disb | 87,456.82 |
Nov 15, 2019 | IBRD-85650 | Loan Disb | 100,445.24 |
Nov 15, 2019 | IBRD-85650 | Int Charges | 100,445.24 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2022-08-30 |
Procurement | Satisfactory | 2022-08-30 |
Financial Management | Satisfactory | 2022-08-30 |
Counterpart Funding | Satisfactory | 2022-08-30 |
Monitoring and Evaluation | Satisfactory | 2022-08-30 |
Overall Implementation Progress (IP) | Satisfactory | 2022-08-30 |
Project Management | Satisfactory | 2022-08-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2023 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-13-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | High | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
4. Number of reported accidents involving non-motorized vehicles or pedestrians in Heping, Hebei and Nankai pilot areas (accidents/year) | Value | 1201.00 | 1104.00 | 1144.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
1. Metro ridership generated from metro access improvement in the central city area (daily trips) | Value | 0.00 | 175750.00 | 95000.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
3. GHG emission reduction due to the project (tCO2e/year) | Value | 0.00 | 34281.00 | 7500.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
2. Walking and biking trips generated by the project in Heping, Hebei and Nankai pilot areas (daily trips) | Value | 0.00 | 153613.00 | 120000.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
5. Number of sites with citizen engagement system established | Value | 0.00 | 60.00 | 26.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
4.1 Number of reported accidents involving non-motorized vehicles or pedestrians in Heping and Nankai pilot areas (accidents/year) | Value | 206.00 | 255.00 | 260.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
2.1 Walking and biking trips generated by the project in Heping and Nankai pilot areas (daily trips) | Value | 0.00 | 98426.00 | 75000.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
5.1 Number of gender-informed (female) citizen engagement system established | Value | 0.00 | 60.00 | 23.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
6. Number of dissemination events promoting green transport strategies for large cities | Value | 0.00 | 15.00 | 10.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
4.2 Number of reported accidents involving non-motorized vehicles or pedestrians in Hebei pilot areas (accidents/year) | Value | 995.00 | 849.00 | 884.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
2.2 Walking and biking trips generated by the project in Hebei pilot areas (daily trips) | Value | 0.00 | 55187.00 | 45000.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1. Whether changes have been made to project activities as a result of consultation | Value | No | Yes | Yes |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
5. Number of metro station with access improved | Value | 0.00 | 96.00 | 96.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
6. Number of bus terminals completed under the project | Value | 0.00 | 1.00 | 1.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
7. Number of TA studies completed and endorsed by Tianjin government | Value | 0.00 | 6.00 | 6.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
2. NMT Space Ratio in Heping, Hebei and Nankai pilot areas | Value | 25.00 | 52.00 | 46.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
3. Kilometers of urban streets rehabilitated and open to traffic in Heping, Hebei and Nankai pilot areas | Value | 0.00 | 79.66 | 75.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |
4. Percentage of km with at least 3-star rating for pedestrians for project streets in Heping, Hebei and Nankai pilot areas | Value | 30.00 | 100.00 | 90.00 |
Date | September 1, 2015 | December 31, 2022 | December 31, 2022 | |
Comment |