RY: AF-Labor Intensive Public Works

Development Objective

The proposed Project’s development objectives are to assist the Recipient to: (i) provide needed infrastructure to improve access to basic public services; and (ii) create short term employment.

Key Details

Project Details

  • P148366

  • Closed

  • Sabine Beddies

  • N/A

  • Yemen, Republic of

  • March 11, 2014

  • (as of board presentation)

    July 3, 2014

  • N/A

  • US$ 50.00 million

  • B

  • October 31, 2022

  • January 17, 2017

  • Yes

  • BANK APPROVED

  • P122594

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 3.00
IDA Grant 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 53.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of female beneficiaries with improved access to water reclamation schemesValue0.0052.0050.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of female beneficiaries with access to improved streets and access to roads to villages/towns/informal settlementsValue0.0051.0050.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of annually enrolled female students benefiting from improved access to vocational trainingValue0.0080.0080.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of women with improved access to primary health care servicesValue0.0049.0050.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of female students with improved access to school enrollmentValue0.0046.0050.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of female beneficiaries with improved access to improved drinking waterValue0.0052.0050.00
    DateJune 30, 2012January 30, 2016
    Comment
  • Share of female beneficiaries with improved access to improved sanitationValue0.0045.0050.00
    DateJune 30, 2012January 30, 2016
    Comment
  • OLD Version of Indicator: People in project areas with access to Improved Water SourcesValue0.0030000.00213180.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • People provided with access to "improved sanitation facilities” under the proj.Value0.0071400.000.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    CommentRevised to be a Core Indicator
  • People provided with access to “improved sanitation facilities” - urbanValue0.000.000.00
    Date
    Comment
  • People provided with access to “improved sanitation facilities”- ruralValue0.000.000.00
    Date
    Comment
  • Number of annually enrolled students benefiting from improved access to vocational trainingValue0.001800.005984.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Number of people with improved access to primary health care servicesValue0.00163166.00485178.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Number of students with improved access to school enrollmentValue0.00167969.00230010.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Improved access to water (no. of beneficiaries)Value249700.000.00363700.00
    DateJune 30, 2012June 30, 2013January 30, 2016
    CommentNo results as yet.
  • Improved access to sewage network (no. of beneficiaries)Value730654.000.00979654.00
    DateJune 30, 2012June 30, 2013January 30, 2016
    CommentNo results as yet.
  • Number of people with improved access to water reclamation schemesValue0.00227000.00257456.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Number of beneficiaries with access to improved streets and access to roads to villages/towns/informal settlementsValue0.00321000.00253320.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Number of person-months of generated short-term employmentValue0.00151000.00240000.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Health facilities constructed, renovated, and/or equipped (number)Value0.0017.0038.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    CommentNew indicator to indicate this is a core indicator
  • Of which femaleValue0.0012.0020.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Number of households provided with access to improved water sources under the projectValue0.0011200.0077000.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Community contribution in the total project costs (percentage)Value0.009.009.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Stone Paving – New roads and streets constructedValue0.0032.00186.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    CommentRevised to reflect unit of measurement as square meters and not number of roads
  • Total community contribution (US$)Value0.000.000.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.000.0080.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Grievances related to delivery of project benefits that are addressed-(number)Value0.000.000.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Percentage of sub-project construction sites supervised by female engineersValue0.003.0012.00
    DateMay 6, 2014September 30, 2017
    Comment
  • Sustainability: Number of water supply schemes with sufficient O&M capacityValue0.0010.0030.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Sustainability: Number of rain water harvesting schemes with sufficient O&M capacityValue0.0092.00170.00
    DateJune 30, 2012September 30, 2017
    Comment
  • Share of Sub-projects for which short-term employment opportunities for women have been foundValue0.002.0012.00
    DateMay 6, 2014September 30, 2017
    Comment
  • Sustainability: Number of Sub-projects which received 2 follow-up visits to ensure Operation & Maintenance capacity within communityValue0.00382.00683.00
    DateMay 6, 2014September 30, 2017
    Comment
  • Sustainability: Number of Sub-projects which are fully functional 1 yr of completion and handoverValue0.000.00683.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Households with access to improved sanitation facilitiesValue0.007000.0039200.00
    DateJune 30, 2012May 6, 2014September 30, 2016
    Comment
  • Schools - Number of new classrooms rehabilitated/builtValue0.001314.002130.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Health-Number of units replaced, extended or rehabilitatedValue146.000.00171.00
    DateJune 30, 2012May 14, 2014January 30, 2016
    Commentdropped to switch from current custom indicator to new core indicator
  • Number of consultants given the opportunity to workValue0.00200.00400.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Number of sub-projects implementedValue0.00382.00683.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Water Supply - Number of new schemes builtValue0.008.0055.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Sanitation - Number of new schemes builtValue0.005.0028.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Water harvesting - Number of new water harvesting schemes (structures) builtValue0.0092.00185.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment
  • Stone paving - New roads and streets constructedValue130.000.00149.00
    DateJune 30, 2012June 30, 2013January 30, 2016
    CommentNo results as yet.
  • Training Centers - Number of new facilities built or rehabilitatedValue0.006.0021.00
    DateJune 30, 2012May 6, 2014September 30, 2017
    Comment