Financier | Commitments |
---|---|
Borrower/Recipient | 3.00 |
IDA Grant | 50.00 |
P148366
Closed
Sabine Beddies
N/A
Yemen, Republic of
March 11, 2014
(as of board presentation)
July 3, 2014
N/A
US$ 53.00 million
N/A
2015
US$ 50.00 million
B
October 31, 2022
January 17, 2017
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 3.00 |
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 53.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of female beneficiaries with improved access to water reclamation schemes | Value | 0.00 | 52.00 | 50.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of female beneficiaries with access to improved streets and access to roads to villages/towns/informal settlements | Value | 0.00 | 51.00 | 50.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of annually enrolled female students benefiting from improved access to vocational training | Value | 0.00 | 80.00 | 80.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of women with improved access to primary health care services | Value | 0.00 | 49.00 | 50.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of female students with improved access to school enrollment | Value | 0.00 | 46.00 | 50.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of female beneficiaries with improved access to improved drinking water | Value | 0.00 | 52.00 | 50.00 |
Date | June 30, 2012 | January 30, 2016 | ||
Comment |
Share of female beneficiaries with improved access to improved sanitation | Value | 0.00 | 45.00 | 50.00 |
Date | June 30, 2012 | January 30, 2016 | ||
Comment |
OLD Version of Indicator: People in project areas with access to Improved Water Sources | Value | 0.00 | 30000.00 | 213180.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 71400.00 | 0.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment | Revised to be a Core Indicator |
People provided with access to “improved sanitation facilities” - urban | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People provided with access to “improved sanitation facilities”- rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of annually enrolled students benefiting from improved access to vocational training | Value | 0.00 | 1800.00 | 5984.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Number of people with improved access to primary health care services | Value | 0.00 | 163166.00 | 485178.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Number of students with improved access to school enrollment | Value | 0.00 | 167969.00 | 230010.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Improved access to water (no. of beneficiaries) | Value | 249700.00 | 0.00 | 363700.00 |
Date | June 30, 2012 | June 30, 2013 | January 30, 2016 | |
Comment | No results as yet. |
Improved access to sewage network (no. of beneficiaries) | Value | 730654.00 | 0.00 | 979654.00 |
Date | June 30, 2012 | June 30, 2013 | January 30, 2016 | |
Comment | No results as yet. |
Number of people with improved access to water reclamation schemes | Value | 0.00 | 227000.00 | 257456.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Number of beneficiaries with access to improved streets and access to roads to villages/towns/informal settlements | Value | 0.00 | 321000.00 | 253320.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Number of person-months of generated short-term employment | Value | 0.00 | 151000.00 | 240000.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 17.00 | 38.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment | New indicator to indicate this is a core indicator |
Of which female | Value | 0.00 | 12.00 | 20.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Number of households provided with access to improved water sources under the project | Value | 0.00 | 11200.00 | 77000.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Community contribution in the total project costs (percentage) | Value | 0.00 | 9.00 | 9.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Stone Paving – New roads and streets constructed | Value | 0.00 | 32.00 | 186.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment | Revised to reflect unit of measurement as square meters and not number of roads |
Total community contribution (US$) | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 0.00 | 80.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Grievances related to delivery of project benefits that are addressed-(number) | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Percentage of sub-project construction sites supervised by female engineers | Value | 0.00 | 3.00 | 12.00 |
Date | May 6, 2014 | September 30, 2017 | ||
Comment |
Sustainability: Number of water supply schemes with sufficient O&M capacity | Value | 0.00 | 10.00 | 30.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Sustainability: Number of rain water harvesting schemes with sufficient O&M capacity | Value | 0.00 | 92.00 | 170.00 |
Date | June 30, 2012 | September 30, 2017 | ||
Comment |
Share of Sub-projects for which short-term employment opportunities for women have been found | Value | 0.00 | 2.00 | 12.00 |
Date | May 6, 2014 | September 30, 2017 | ||
Comment |
Sustainability: Number of Sub-projects which received 2 follow-up visits to ensure Operation & Maintenance capacity within community | Value | 0.00 | 382.00 | 683.00 |
Date | May 6, 2014 | September 30, 2017 | ||
Comment |
Sustainability: Number of Sub-projects which are fully functional 1 yr of completion and handover | Value | 0.00 | 0.00 | 683.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Households with access to improved sanitation facilities | Value | 0.00 | 7000.00 | 39200.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2016 | |
Comment |
Schools - Number of new classrooms rehabilitated/built | Value | 0.00 | 1314.00 | 2130.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Health-Number of units replaced, extended or rehabilitated | Value | 146.00 | 0.00 | 171.00 |
Date | June 30, 2012 | May 14, 2014 | January 30, 2016 | |
Comment | dropped to switch from current custom indicator to new core indicator |
Number of consultants given the opportunity to work | Value | 0.00 | 200.00 | 400.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Number of sub-projects implemented | Value | 0.00 | 382.00 | 683.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Water Supply - Number of new schemes built | Value | 0.00 | 8.00 | 55.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Sanitation - Number of new schemes built | Value | 0.00 | 5.00 | 28.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Water harvesting - Number of new water harvesting schemes (structures) built | Value | 0.00 | 92.00 | 185.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |
Stone paving - New roads and streets constructed | Value | 130.00 | 0.00 | 149.00 |
Date | June 30, 2012 | June 30, 2013 | January 30, 2016 | |
Comment | No results as yet. |
Training Centers - Number of new facilities built or rehabilitated | Value | 0.00 | 6.00 | 21.00 |
Date | June 30, 2012 | May 6, 2014 | September 30, 2017 | |
Comment |