ICT Sector Support in Somalia

Development Objective

The Project Development Objective (PDO) is “Create an enabling and trusted policy and regulatory environment to develop Somalia’s telecommunications infrastructure as a foundation for economic recovery and growth”. The outcomes are aligned with the a number of objectives with the Peace and State-building Trust Fund, including: 1.2 Partnerships are strengthened 1.4 Timely support provided for early confidence building 1.5 SPF programs are catalytic with the potential to be scaled up and/or replicated to ensure sustained support for institution building 1.6 Contributes to knowledge and learning that improves WB operations in FCS 2.1More effective, transparent and accountable collection, management and use of public resources that builds citizen confidence

Key Details

Project Details

  • P148588

  • Closed

  • Timothy Kelly

  • Ministry of Posts and Telecommunications

  • Somalia

  • April 24, 2014

  • (as of board presentation)

    April 24, 2014

  • May 30, 2014

  • US$ 2.00 million

  • C

  • December 15, 2020

  • March 31, 2016

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
State and Peace Building Fund 2.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.00
Total Project Cost** 2.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2016-01-26
Project Management Satisfactory 2016-01-26
Overall Implementation Progress (IP) Satisfactory 2016-01-26
Procurement Moderately Satisfactory 2016-01-26
Financial Management Moderately Satisfactory 2016-01-26
Overall Satisfactory 2016-01-26
Monitoring and Evaluation Moderately Satisfactory 2016-01-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Access to Internet Services (number of subscribers per 100 people)Value0.302.982.00
    DateDecember 31, 2012September 30, 2015December 31, 2016
    Comment
  • Establishing an effective ICT regulatory authorityValueNoNoYes
    DateDecember 31, 2012March 17, 2015March 31, 2016
    Comment
  • Access to Internet Services (number of subscribers per 100 people)Value23.0089.0030.00
    DateDecember 31, 2012September 30, 2015December 31, 2015
    Comment
  • Retail Price of Internet Services (per Mbit/s per Month, in US$)Value1400.00100.00500.00
    DateDecember 31, 2012September 30, 2015December 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Price per GB of mobile dataValue1000.0025.00250.00
    DateDecember 31, 2012June 30, 2015March 31, 2016
    Comment
  • Number of project beneficiaries femaleValue0.00850000.00770000.00
    DateDecember 31, 2012September 30, 2015December 31, 2016
    Comment