Financier | Commitments |
---|---|
IDA Grant | 68.22 |
IDA Credit | 6.77 |
P148617
Closed
Ivan Drabek
N/A
February 18, 2015
(as of board presentation)
March 26, 2015
N/A
US$ 74.99 million
N/A
2015
US$ 74.99 million
B
January 17, 2024
June 30, 2021
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 68.22 |
IDA Credit | 6.77 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 74.99 |
IBRD + IDA Commitment | 74.99 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 74.99 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries of Safety Nets programs - Female (number) | Value | 400000.00 | 0.00 | 600000.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) | Value | 30000.00 | 0.00 | 100000.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
Beneficiaries of Safety Nets programs (number) | Value | 600000.00 | 0.00 | 800000.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
Beneficiaries by gender | Value | 603679.00 | 0.00 | 1073140.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% HHs with asset value above critical threshold | Value | 0.00 | 0.00 | 0.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment | To be completed in first year | To be completed in first year |
Value | 0 | 1 | ||
Date | October 28, 2013 | December 31, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of beneficiaries that feel project investments/ PWP reflected their needs (core) | Value | 30.00 | 0.00 | 80.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of households who report improved access to social services- - (market- Health- education, - Irrigation- Potable water, - Road | Value | 0.00 | 0.00 | 70.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment | To be completed | To be completed |
% of people engaging in diversified IGAs (off-farm and on-farm) | Value | 4.00 | 0.00 | 50.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% Increase in household productive assets by type | Value | 0.00 | 0.00 | 25.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% increase in household level savings | Value | 84.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
Number of councils implementing targeting instruments to select beneficiaries | Value | 8.00 | 0.00 | 35.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of beneficiaries that are aware of project information and project supported investments (core) | Value | 0.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of grievances registered related to delivery of project benefits that are actually addressed (core) | Value | 0.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
Number of extension workers trained and supported with equipment | Value | 840.00 | 0.00 | 840.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of participants paid within the agreed time frame (2 weeks for PWP and within the month for SCT) | Value | 50.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 31, 2013 | ||
Comment |
% of beneficiaries receiving full entitlement (PWP, SCT) | Value | 0.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of beneficiaries staying in the program for a minimum of 3 years (PW, SCT) | Value | 0.00 | 0.00 | 80.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment | To be confirmed. |
% of subprojects screened for ESMF& implemented accordingly. | Value | 100.00 | 0.00 | 100.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment |
% of PW sub-projects selected and implemented following participatory community based planning approaches | Value | 0.00 | 0.00 | 100.00 |
Date | October 22, 2013 | December 31, 2018 | ||
Comment |
Areas restored or re-afforested | Value | 1122.00 | 0.00 | 1300.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment | This number will be greater than the baseline and 1300 is a placeholder. |
Number of Small scale irrigation schemes completed | Value | 319.00 | 0.00 | 400.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment | this will be a figure greater than 319 and for now 400 is a place holder. |
% of Sub-projects or investment for which arrangement for community engagement and or operation and maintenance are established | Value | 17.00 | 0.00 | 70.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment |
Type of IGAs implemented by the beneficiaries | Value | 25 | 40 | |
Date | October 23, 2013 | December 31, 2018 | ||
Comment | The number would be greater than 25 so at the moment 40 is a place holder. |
Number of training interventions on livelihood and skill development activities | Value | 2699.00 | 0.00 | 5000.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment | It is expected that COMSIP will form 6697 groups in total so the training would be a number >5000 |
Number of COMSIP and other livelihood groups | Value | 4457.00 | 0.00 | 6697.00 |
Date | October 23, 2013 | December 31, 2018 | ||
Comment |
% of Safety Net coordination meetings held as planned | Value | 100.00 | 0.00 | 100.00 |
Date | October 29, 2013 | December 20, 2018 | ||
Comment |
Operational M&E system | Value | 8 | 35 | |
Date | October 23, 2013 | December 31, 2018 | ||
Comment |
Number of Local Authorities with operational MIS | Value | 8 | 35 | |
Date | October 23, 2013 | December 31, 2018 | ||
Comment |
Number of Local Authorities with operational harmonized targeting mechanism | Value | 8 | 35 | |
Date | October 23, 2013 | December 29, 2018 | ||
Comment |
% of HH having at 3 meals per day by member, age gender | Value | 21.20 | 0.00 | 70.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |
% of HH reporting that asset depletion is prevented as a result of transfers (SCT, PWP) | Value | 0.00 | 0.00 | 40.00 |
Date | October 29, 2013 | December 31, 2018 | ||
Comment |