Development Objective

The Project Development Objective is to improve resilience among poor households and to strengthen Malawiâ??s social safety net delivery systems and coordination across programs.

Key Details

Project Details

  • P148617

  • Closed

  • Ivan Drabek

  • N/A

  • Malawi

  • February 18, 2015

  • (as of board presentation)

    March 26, 2015

  • N/A

  • US$ 74.99 million

  • B

  • January 17, 2024

  • June 30, 2021

  • TBD

  • BANK APPROVED

  • P133620

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 68.22
IDA Credit 6.77

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 74.99
IBRD + IDA Commitment 74.99
Lending Instrument
Grant Amount N/A
Total Project Cost** 74.99

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries of Safety Nets programs - Female (number)Value400000.000.00600000.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value30000.000.00100000.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • Beneficiaries of Safety Nets programs (number)Value600000.000.00800000.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • Beneficiaries by genderValue603679.000.001073140.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % HHs with asset value above critical thresholdValue0.000.000.00
    DateOctober 29, 2013December 31, 2018
    CommentTo be completed in first yearTo be completed in first year
  • Value01
    DateOctober 28, 2013December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of beneficiaries that feel project investments/ PWP reflected their needs (core)Value30.000.0080.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of households who report improved access to social services- - (market- Health- education, - Irrigation- Potable water, - RoadValue0.000.0070.00
    DateOctober 29, 2013December 31, 2018
    CommentTo be completedTo be completed
  • % of people engaging in diversified IGAs (off-farm and on-farm)Value4.000.0050.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % Increase in household productive assets by typeValue0.000.0025.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % increase in household level savingsValue84.000.00100.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • Number of councils implementing targeting instruments to select beneficiariesValue8.000.0035.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of beneficiaries that are aware of project information and project supported investments (core)Value0.000.00100.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of grievances registered related to delivery of project benefits that are actually addressed (core)Value0.000.00100.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • Number of extension workers trained and supported with equipmentValue840.000.00840.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of participants paid within the agreed time frame (2 weeks for PWP and within the month for SCT)Value50.000.00100.00
    DateOctober 29, 2013December 31, 2013
    Comment
  • % of beneficiaries receiving full entitlement (PWP, SCT)Value0.000.00100.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of beneficiaries staying in the program for a minimum of 3 years (PW, SCT)Value0.000.0080.00
    DateOctober 29, 2013December 31, 2018
    CommentTo be confirmed.
  • % of subprojects screened for ESMF& implemented accordingly.Value100.000.00100.00
    DateOctober 23, 2013December 31, 2018
    Comment
  • % of PW sub-projects selected and implemented following participatory community based planning approachesValue0.000.00100.00
    DateOctober 22, 2013December 31, 2018
    Comment
  • Areas restored or re-afforestedValue1122.000.001300.00
    DateOctober 23, 2013December 31, 2018
    CommentThis number will be greater than the baseline and 1300 is a placeholder.
  • Number of Small scale irrigation schemes completedValue319.000.00400.00
    DateOctober 23, 2013December 31, 2018
    Commentthis will be a figure greater than 319 and for now 400 is a place holder.
  • % of Sub-projects or investment for which arrangement for community engagement and or operation and maintenance are establishedValue17.000.0070.00
    DateOctober 23, 2013December 31, 2018
    Comment
  • Type of IGAs implemented by the beneficiariesValue2540
    DateOctober 23, 2013December 31, 2018
    CommentThe number would be greater than 25 so at the moment 40 is a place holder.
  • Number of training interventions on livelihood and skill development activitiesValue2699.000.005000.00
    DateOctober 23, 2013December 31, 2018
    CommentIt is expected that COMSIP will form 6697 groups in total so the training would be a number >5000
  • Number of COMSIP and other livelihood groupsValue4457.000.006697.00
    DateOctober 23, 2013December 31, 2018
    Comment
  • % of Safety Net coordination meetings held as plannedValue100.000.00100.00
    DateOctober 29, 2013December 20, 2018
    Comment
  • Operational M&E systemValue835
    DateOctober 23, 2013December 31, 2018
    Comment
  • Number of Local Authorities with operational MISValue835
    DateOctober 23, 2013December 31, 2018
    Comment
  • Number of Local Authorities with operational harmonized targeting mechanismValue835
    DateOctober 23, 2013December 29, 2018
    Comment
  • % of HH having at 3 meals per day by member, age genderValue21.200.0070.00
    DateOctober 29, 2013December 31, 2018
    Comment
  • % of HH reporting that asset depletion is prevented as a result of transfers (SCT, PWP)Value0.000.0040.00
    DateOctober 29, 2013December 31, 2018
    Comment