Skip to Main Navigation

Additional Financing to Second Northern Mountains Poverty Reduction Project

Development Objective

The AF focuses on institutionalizing and mainstreaming the socio-economic development planning approach in the broader planning and budget allocation processes in the project area. The PDO will, therefore, be revised to capture this important element of the AF. Project Development Objective for the AF is revised to read: The Project Development Objective (PDO) is to enhance the living standards of the Project Beneficiaries by improving: (i) their access to productive infrastructure; (ii) the productive and institutional capacity of local governments and communities; (iii) commune integrated investment planning and (iv) market linkages and business innovations.

Key Details

Project Details

  • P148733

  • Closed

  • Lan Nguyen

  • N/A

  • Viet Nam

  • November 26, 2014

  • (as of board presentation)

    February 27, 2015

  • N/A

  • US$ 100.00 million

  • B

  • June 26, 2024

  • June 30, 2018

  • TBD

  • BANK APPROVED

  • P113493

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 10.00
IDA Credit 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 110.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • At least 60% of the project beneficiaries report satisfaction on the selection, design, and implementation of project activities.Value0.0066.0060.00
    DateNovember 15, 2010December 28, 2012June 30, 2015
    CommentData from Light Survey for the Midterm review.
  • Project beneficiaries report an improvement of per capita income at least by 10%Value0.0011.0010.00
    DateNovember 15, 2010December 28, 2012June 30, 2015
    CommentData collection for baseline survey completed on November 15, 2010Data is from the Light Survey. This is a proxy measure for production and yield of rice only. Task team and client areconsideringassessment of the capacity to measure this before the EOP.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • At least 60% of households in the project areas report satisfaction of economic benefits due to productive infrastructure improvement in accessibility to basic infrastructureValue0.0048.0060.00
    DateNovember 15, 2010December 28, 2012June 30, 2015
    CommentData is from the Light Survey. 48% of improvement o access to roads.Citizens Report Card: Access to roads – 48% (96%), Access to irrigation – 37% (75%), Access to water supply– 45% (81%), Access tomarkets – 11% (52%)Community Report Card (all-women FGDs):Access to roads – 45% (95%), Access to irrigation – 28% (60%), Access towater supply– 20% (50%),Access to markets – 0% (14%)
  • At least60% of project beneficiaries report satisfaction with public services deliveryValue0.0077.0060.00
    DateNovember 15, 2010December 28, 2012June 30, 2015
    CommentData from the Light Survey for the MTR
  • Targeted clients satisfied with agricultural services (percentage)Value0.0030.0080.00
    DateSeptember 20, 2012October 2, 2013June 30, 2015
    CommentCore indicators are newly added under the retrofitted request from SDN on September 20, 2012. Hence, baseline isconsideredstartingon September 20, 2012.Data from MTR report.The baseline satisfaction rate was 20%, 2013 81%,
  • At least 60% of communes integrate the NMPRP-2 into their SEDPsValue0.000.0060.00
    DateNovember 15, 2010September 16, 2013June 30, 2015
    CommentIntegration of the project's activities to SEDP begins this year for 2014 planning so this remains to be updated. Not coveredbytheLight Survey.41%, (100%)
  • Number of households involved in non-farm income generating activity increase by at least 30%Value0.000.0030.00
    DateNovember 15, 2010September 16, 2013June 30, 2015
    CommentNot assessed in the Light Survey. End target is changed to 15% based on the advice from th Baseline survey. Changed is proposed atthe MTRIncome data was not collected by Limited Survey
  • At least 60% communes have undertaken risk assessment on their plan before submitting proposals for project interventionsValue0.000.0060.00
    DateNovember 15, 2010September 16, 2013June 30, 2015
    CommentNot covered by the Light Survey for the MTR. Data will be available to report for the planning for 2014.
  • Improvement in agricultural output at least by 10%Value0.0011.0010.00
    DateNovember 15, 2010December 28, 2012June 30, 2015
    CommentData is from the Light Survey. This is a proxy measure for production and yield of rice only. Task team and client are consideringassessment of the capacity to measure this before the EOP.
  • Over 60% of farmers in CIGs market their products beyond the farmgate to retailers, processors and other value chain membersValue0.0030.0060.00
    DateNovember 15, 2010January 7, 2013June 30, 2015
    CommentData reported at MTR. This is changed from the original indicator at the MTR.
  • At least 60% of women and ethnic minorities satisfied with their levelof participation in planning and decision making processValue0.0030.0060.00
    DateDecember 31, 2013June 30, 2015
    CommentData from the Light Survey for MTRCommunity Report Card:Public services delivery – 45%, (75%)Public representation and service delivery – 27% (NA)
  • Targeted clients satisfied with agricultural services - male (number)Value0.001800.0016000.00
    DateSeptember 20, 2012October 2, 2013June 30, 2015
    Comment
  • Targeted clients satisfied with agricultural services - female (number)Value0.005100.0044000.00
    DateSeptember 20, 2012October 2, 2013June 30, 2015
    Comment
  • Targeted clients- male (number)Value0.006000.0020000.00
    DateSeptember 20, 2012October 2, 2013June 30, 2015
    Comment
  • Targeted clients – female (number) Value0.0017000.0055000.00
    DateSeptember 20, 2012October 2, 2013June 30, 2015
    Comment
  • 30% of households report improved opportunities and public support to start or improve businessesValue0.0020.0030.00
    DateDecember 31, 2013June 30, 2015
    Comment
  • At least 80% of communes SEDPs include multiple sources of fundingValue0.000.0080.00
    DateJune 30, 2015
    Comment
  • At least 60% of commune women are satisfied with their level of participation in planning meetingsValue0.000.0060.00
    DateJune 30, 2015
    Comment