| Financier | Commitments | 
|---|---|
| IDA Grant | 70.00 | 
| IDA Grant | 70.00 | 
P148970
Closed
Veronique Verdeil
REPUBLIC OF HAITI,REPUBLIC OF HAITI
Haiti
July 17, 2014
(as of board presentation)
May 26, 2015
December 16, 2015
US$ 70.00 million
Ministry of Economy and Finance, MEF,DINEPA,Ministry of Economy and Finance, MEF,DINEPA
2015
US$ 70.00 million
B
Not Applicable
March 31, 2023
Bank Approved
October 2, 2023
| Financier | Commitments | 
|---|---|
| IDA Grant | 70.00 | 
| IDA Grant | 70.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 70.00 | 
| IBRD + IDA Commitment | 70.00 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 70.00 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Nov 4, 2022 | IDA-D0680 | Loan Disb | 272,519.16 | 
| Nov 10, 2022 | IDA-D0680 | Loan Disb | 235,494.00 | 
| Feb 2, 2023 | IDA-D0680 | Loan Disb | 500,000.00 | 
| Mar 30, 2023 | IDA-D0680 | Loan Cancel | 4,037,100.00 | 
| Dec 20, 2022 | IDA-D0680 | Loan Disb | 992,698.25 | 
| Apr 10, 2023 | IDA-D0680 | Loan Disb | 1,134,015.90 | 
| May 10, 2023 | IDA-D0680 | Loan Disb | 571,887.00 | 
| May 10, 2023 | IDA-D0680 | Loan Disb | 238,500.00 | 
| Mar 15, 2023 | IDA-D0680 | Loan Disb | 229,584.98 | 
| Apr 17, 2023 | IDA-D0680 | Loan Disb | 563,574.75 | 
| Aug 27, 2018 | IDA-D0680 | Loan Disb | 1,879,679.00 | 
| Jun 28, 2018 | IDA-D0680 | Loan Disb | 2,182,829.50 | 
| Jan 30, 2019 | IDA-D2010 | Loan Disb | 4,000,000.00 | 
| Jan 30, 2019 | IDA-D0680 | Loan Disb | 2,234,940.80 | 
| Jul 11, 2019 | IDA-D0680 | Loan Disb | 1,951,110.10 | 
| Dec 27, 2019 | IDA-D0680 | Loan Disb | 3,472,038.50 | 
| Jun 18, 2020 | IDA-D0680 | Loan Disb | 3,046,889.50 | 
| Mar 17, 2021 | IDA-D2010 | Loan Disb | 503,128.62 | 
| Dec 4, 2020 | IDA-D2010 | Loan Disb | 2,355,004.20 | 
| Dec 4, 2020 | IDA-D0680 | Loan Disb | 2,040,849.20 | 
| Dec 28, 2015 | IDA-D0680 | Loan Disb | 1,047,847.80 | 
| May 3, 2016 | IDA-D0680 | Loan Disb | 4,400,000.00 | 
| Nov 22, 2016 | IDA-D0680 | Loan Disb | 599,456.60 | 
| Jul 12, 2017 | IDA-D0680 | Loan Disb | 1,399,297.50 | 
| Jun 9, 2017 | IDA-D0680 | Loan Disb | 238,666.78 | 
| Mar 28, 2017 | IDA-D0680 | Loan Disb | 1,264,819.10 | 
| Nov 14, 2017 | IDA-D0680 | Loan Disb | 1,958,007.80 | 
| Dec 22, 2017 | IDA-D0680 | Loan Disb | 3,040,437.00 | 
| Apr 5, 2024 | IDA-D0680 | Loan Disb | -565,526.70 | 
| May 28, 2024 | IDA-D0680 | Loan Disb | 74,978.12 | 
| Jun 14, 2017 | IDA-D2010 | Loan Commitment | 20,000,000.00 | 
| May 26, 2015 | IDA-D0680 | Loan Commitment | 50,000,000.00 | 
| May 31, 2023 | IDA-D0680 | Loan Disb | 229,133.73 | 
| Jul 21, 2023 | IDA-D0680 | Loan Disb | 147,517.62 | 
| Jul 25, 2023 | IDA-D0680 | Loan Disb | 43,255.23 | 
| Nov 30, 2023 | IDA-D0680 | Loan Disb | -7,015.03 | 
| Jun 5, 2023 | IDA-D0680 | Loan Disb | 113,190.23 | 
| Jul 6, 2023 | IDA-D0680 | Loan Disb | 128,296.71 | 
| Oct 25, 2023 | IDA-D0680 | Loan Disb | 28,305.63 | 
| Oct 27, 2023 | IDA-D0680 | Loan Disb | 26,641.41 | 
| Oct 18, 2023 | IDA-D0680 | Loan Disb | 48,560.47 | 
| Oct 18, 2023 | IDA-D0680 | Loan Disb | 44,637.41 | 
| Oct 17, 2023 | IDA-D0680 | Loan Disb | 40,000.00 | 
| Apr 6, 2022 | IDA-D0680 | Loan Disb | 63,578.70 | 
| Jun 21, 2022 | IDA-D2010 | Loan Disb | 1,084,325.40 | 
| Dec 15, 2021 | IDA-D2010 | Loan Disb | 604,253.40 | 
| Dec 23, 2022 | IDA-D0680 | Loan Disb | 220,429.02 | 
| Dec 20, 2021 | IDA-D0680 | Loan Disb | 2,111,401.20 | 
| Dec 17, 2021 | IDA-D2010 | Loan Disb | 2,366,810.80 | 
| Sep 29, 2022 | IDA-D0680 | Loan Disb | 400,000.00 | 
| Nov 17, 2022 | IDA-D2010 | Loan Disb | 929,844.40 | 
| Sep 14, 2022 | IDA-D0680 | Loan Disb | 476,171.00 | 
| Sep 14, 2022 | IDA-D2010 | Loan Disb | 78,512.01 | 
| Nov 8, 2023 | IDA-D0680 | Loan Disb | 99,654.35 | 
| Nov 30, 2023 | IDA-D2010 | Loan Disb | -768.02 | 
| Nov 30, 2023 | IDA-D2010 | Loan Disb | -252.05 | 
| Nov 30, 2023 | IDA-D0680 | Loan Disb | -30,521.49 | 
| Oct 20, 2023 | IDA-D0680 | Loan Disb | 13,031.08 | 
| Oct 20, 2023 | IDA-D0680 | Loan Disb | 14,576.63 | 
| Oct 30, 2023 | IDA-D0680 | Loan Disb | 60,178.15 | 
| Oct 30, 2023 | IDA-D0680 | Loan Disb | 51,965.68 | 
| Nov 21, 2023 | IDA-D0680 | Loan Disb | 30,021.64 | 
| Nov 21, 2023 | IDA-D0680 | Loan Disb | 30,021.64 | 
| Nov 27, 2023 | IDA-D0680 | Loan Disb | 9,577.97 | 
| Nov 3, 2023 | IDA-D0680 | Loan Disb | 7,958.35 | 
| Nov 3, 2023 | IDA-D0680 | Loan Disb | 8,522.20 | 
| Oct 23, 2023 | IDA-D0680 | Loan Disb | 5,225.41 | 
| Oct 23, 2023 | IDA-D0680 | Loan Disb | 9,780.27 | 
| Oct 23, 2023 | IDA-D0680 | Loan Disb | 43,718.22 | 
| May 31, 2024 | IDA-D0680 | Loan Disb | 14,381.85 | 
| Apr 5, 2024 | IDA-D2010 | Loan Disb | -12,543.19 | 
| Apr 2, 2021 | IDA-D2010 | Loan Disb | 2,627,591.50 | 
| Apr 15, 2021 | IDA-D2010 | Loan Disb | 1,354,345.50 | 
| Apr 13, 2021 | IDA-D2010 | Loan Disb | 1,496,432.80 | 
| Mar 31, 2021 | IDA-D0680 | Loan Disb | 953,852.60 | 
| Jun 25, 2021 | IDA-D0680 | Loan Disb | 577,738.50 | 
| Jul 15, 2021 | IDA-D0680 | Loan Disb | 2,425,107.80 | 
| Jul 15, 2021 | IDA-D2010 | Loan Disb | 155,298.31 | 
| Sep 28, 2021 | IDA-D0680 | Loan Disb | 1,241,217.80 | 
| Sep 28, 2021 | IDA-D2010 | Loan Disb | 1,250,909.50 | 
| Mar 29, 2022 | IDA-D2010 | Loan Disb | 1,591,940.10 | 
| Name | Review | Date | 
|---|---|---|
| Monitoring and Evaluation | Moderately Satisfactory | 2023-03-30 | 
| Procurement | Moderately Unsatisfactory | 2023-03-30 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2023-03-30 | 
| Project Management | Moderately Unsatisfactory | 2023-03-30 | 
| Financial Management | Moderately Unsatisfactory | 2023-03-30 | 
| Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2023-03-30 | 
| Monitoring and Evaluation | Moderately Satisfactory | 2023-03-30 | 
| Procurement | Moderately Unsatisfactory | 2023-03-30 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2023-03-30 | 
| Project Management | Moderately Unsatisfactory | 2023-03-30 | 
| Financial Management | Moderately Unsatisfactory | 2023-03-30 | 
| Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2023-03-30 | 
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-02-2023 | 
|---|---|
| Outcomes | Moderately Satisfactory | 
| Risk to Development Outcome | |
| Bank Performance | Moderately Satisfactory | 
| Borrower Performance | |
| Government Performance | |
| Implementing Agency | 
| INDICATOR | ICR REVIEW: 02-06-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: 02-06-2024 | 
|---|---|---|
| Outcome Rating | Moderately Satisfactory | Moderately Satisfactory | 
| Risk To Development Outcome | ||
| Bank Performance | Moderately Satisfactory | Moderately Satisfactory | 
| Borrower Performance | ||
| Government Performance | ||
| Implementing Agency | ||
| Icr Quality | Substantial | Substantial | 
| M&e Quality | Substantial | Substantial | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Direct project beneficiaries | Value | 0.00 | 601518.00 | 618000.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| Female beneficiaries | Value | 0.00 | 50.00 | 0.00 | 
| Date | September 30, 2015 | May 17, 2018 | ||
| Comment | 
| Project beneficiaries in localities on the border with the DR including bi-national markets | Value | 0.00 | 39665.00 | 34000.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| Number of people in rural areas and small towns provided with access to Improved Water Sources under the project | Value | 0.00 | 570558.00 | 588000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Number of people provided with access to improved water sources under the project except in the areas affected by Hurricane Matthew | Value | 0.00 | 152319.00 | 197000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane Matthew | Value | 0.00 | 342339.00 | 320000.00 | 
| Date | June 14, 2017 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Project beneficiaries of small repairs of water systems in the context of COVID-19 emergency | Value | 0.00 | 75900.00 | 71000.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Piped water systems managed sustainably by a Professional Operator (PO) under the project | Value | 0.00 | 17.00 | 24.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Required functions deconcentrated to targeted OREPA | Value | 0.00 | 6.00 | 6.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 30960.00 | 30000.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People in rural areas provided with access to "improved sanitation facilities" - female | Value | 0.00 | 15000.00 | 15000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Priority cholera communes targeted under the project | Value | 0.00 | 7.00 | 7.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| DINEPA's system in place to respond to major emergencies | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Direct project beneficiaries | Value | 0.00 | 601518.00 | 618000.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| Female beneficiaries | Value | 0.00 | 50.00 | 0.00 | 
| Date | September 30, 2015 | May 17, 2018 | ||
| Comment | 
| Project beneficiaries in localities on the border with the DR including bi-national markets | Value | 0.00 | 39665.00 | 34000.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| Number of people in rural areas and small towns provided with access to Improved Water Sources under the project | Value | 0.00 | 570558.00 | 588000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Number of people provided with access to improved water sources under the project except in the areas affected by Hurricane Matthew | Value | 0.00 | 152319.00 | 197000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane Matthew | Value | 0.00 | 342339.00 | 320000.00 | 
| Date | June 14, 2017 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Project beneficiaries of small repairs of water systems in the context of COVID-19 emergency | Value | 0.00 | 75900.00 | 71000.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Piped water systems managed sustainably by a Professional Operator (PO) under the project | Value | 0.00 | 17.00 | 24.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Required functions deconcentrated to targeted OREPA | Value | 0.00 | 6.00 | 6.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 30960.00 | 30000.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People in rural areas provided with access to "improved sanitation facilities" - female | Value | 0.00 | 15000.00 | 15000.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Priority cholera communes targeted under the project | Value | 0.00 | 7.00 | 7.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| DINEPA's system in place to respond to major emergencies | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Departments covered by WSS baseline information | Value | 0.00 | 10.00 | 10.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placein zones affected by Hurricane Matthew | Value | 0.00 | 24.00 | 0.00 | 
| Date | June 14, 2017 | March 15, 2023 | ||
| Comment | 
| New piped household water connections that are resulting from the project intervention | Value | 0.00 | 6576.00 | 7750.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| DINEPA conducts an annual joint Government/ partners sector review | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane Matthew | Value | 0.00 | 270019.00 | 270000.00 | 
| Date | June 14, 2017 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 133.00 | 135.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in place | Value | 0.00 | 5.00 | 5.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People trained to improve hygiene behavior/sanitation practices under the project | Value | 0.00 | 981255.00 | 95000.00 | 
| Date | November 22, 2019 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Number of OREPAs among the 4 existing ones, using the baseline developed under the project to prioritize. | Value | 0.00 | 4.00 | 4.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion andsanitation themes and activities | Value | 0.00 | 23.00 | 23.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Students and teachers benefitting from improved sanitation facilities in public schools under the project | Value | 0.00 | 19351.00 | 30000.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of OREPAs among the 4 existing ones that have installed an accounting system which facilitates the consolidation of financial information at the central level. | Value | 0.00 | 1.00 | 2.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placeunder the project | Value | 0.00 | 51.00 | 70.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Households with latrine built during project implementation and of which use is verified | Value | 0.00 | 5449.00 | 1900.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of handwashing facilities built in the context of COVID-19 awareness campaign | Value | 0.00 | 1095.00 | 995.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| CAEPAs that include at least 20 percent female representation in project area | Value | 0.00 | 129.00 | 70.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of hospitals and health centers whose water supply system was repaired under the COVID-19 emergency | Value | 0.00 | 7.00 | 15.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| DINEPA acknowledged a gender action plan | Value | No | Yes | Yes | 
| Date | January 1, 2019 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| A fecal sludge management service chain for rural areas and small towns is defined | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 100.00 | 100.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Departments covered by WSS baseline information | Value | 0.00 | 10.00 | 10.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placein zones affected by Hurricane Matthew | Value | 0.00 | 24.00 | 0.00 | 
| Date | June 14, 2017 | March 15, 2023 | ||
| Comment | 
| New piped household water connections that are resulting from the project intervention | Value | 0.00 | 6576.00 | 7750.00 | 
| Date | September 30, 2015 | March 31, 2023 | September 30, 2021 | |
| Comment | 
| DINEPA conducts an annual joint Government/ partners sector review | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane Matthew | Value | 0.00 | 270019.00 | 270000.00 | 
| Date | June 14, 2017 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 133.00 | 135.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in place | Value | 0.00 | 5.00 | 5.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| People trained to improve hygiene behavior/sanitation practices under the project | Value | 0.00 | 981255.00 | 95000.00 | 
| Date | November 22, 2019 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Number of OREPAs among the 4 existing ones, using the baseline developed under the project to prioritize. | Value | 0.00 | 4.00 | 4.00 | 
| Date | September 30, 2015 | March 31, 2023 | March 31, 2023 | |
| Comment | 
| Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion andsanitation themes and activities | Value | 0.00 | 23.00 | 23.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Students and teachers benefitting from improved sanitation facilities in public schools under the project | Value | 0.00 | 19351.00 | 30000.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of OREPAs among the 4 existing ones that have installed an accounting system which facilitates the consolidation of financial information at the central level. | Value | 0.00 | 1.00 | 2.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment | 
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placeunder the project | Value | 0.00 | 51.00 | 70.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Households with latrine built during project implementation and of which use is verified | Value | 0.00 | 5449.00 | 1900.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of handwashing facilities built in the context of COVID-19 awareness campaign | Value | 0.00 | 1095.00 | 995.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| CAEPAs that include at least 20 percent female representation in project area | Value | 0.00 | 129.00 | 70.00 | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Number of hospitals and health centers whose water supply system was repaired under the COVID-19 emergency | Value | 0.00 | 7.00 | 15.00 | 
| Date | March 9, 2020 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| DINEPA acknowledged a gender action plan | Value | No | Yes | Yes | 
| Date | January 1, 2019 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| A fecal sludge management service chain for rural areas and small towns is defined | Value | No | Yes | Yes | 
| Date | September 30, 2015 | March 15, 2023 | March 31, 2023 | |
| Comment | 
| Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 100.00 | 100.00 | 
| Date | September 30, 2015 | March 15, 2023 | September 30, 2021 | |
| Comment |