Haiti Sustainable Rural and Small Towns Water and Sanitation Project

Abstract*

The Sustainable Rural and Small Towns Water and Sanitation Project for Haiti will: i) increase access to improved water supply and sanitation in targeted rural areas and small towns in zones affected by cholera; ii) strengthen water and sanitation service delivery mechanism at the deconcentrated level; and iii) improve capacity to respond promptly and effectively to an Eligible Emergency. Implementation of this project will involve the following three...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed objectives of the Project are to: (i) increase access to improved water supply and sanitation in targeted rural areas and small towns in zones affected by cholera; (ii) strengthen the Recipient’s water and sanitation service delivery mechanism at thedeconcentrated level; and (iii) improve the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency.

Key Details

Project Details

  • P148970

  • Closed

  • Veronique Verdeil

  • REPUBLIC OF HAITI

  • Haiti

  • July 17, 2014

  • (as of board presentation)

    May 26, 2015

  • December 16, 2015

  • US$ 70.00 million

  • DINEPA,Ministry of Economy and Finance, MEF

  • Latin America and Caribbean

  • 2015

  • US$ 70.00 million

  • B

  • October 2, 2023

  • March 31, 2023

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 70.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 70.00
IBRD + IDA Commitment 70.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 70.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 4, 2022 IDA-D0680 Loan Disb 272,519.16
Nov 10, 2022 IDA-D0680 Loan Disb 235,494.00
Feb 2, 2023 IDA-D0680 Loan Disb 500,000.00
Mar 30, 2023 IDA-D0680 Loan Cancel 4,037,100.00
Dec 20, 2022 IDA-D0680 Loan Disb 992,698.25
Apr 10, 2023 IDA-D0680 Loan Disb 1,134,015.90
May 10, 2023 IDA-D0680 Loan Disb 571,887.00
May 10, 2023 IDA-D0680 Loan Disb 238,500.00
Mar 15, 2023 IDA-D0680 Loan Disb 229,584.98
Apr 17, 2023 IDA-D0680 Loan Disb 563,574.75
Aug 27, 2018 IDA-D0680 Loan Disb 1,879,679.00
Jun 28, 2018 IDA-D0680 Loan Disb 2,182,829.50
Jan 30, 2019 IDA-D2010 Loan Disb 4,000,000.00
Jan 30, 2019 IDA-D0680 Loan Disb 2,234,940.80
Jul 11, 2019 IDA-D0680 Loan Disb 1,951,110.10
Dec 27, 2019 IDA-D0680 Loan Disb 3,472,038.50
Jun 18, 2020 IDA-D0680 Loan Disb 3,046,889.50
Mar 17, 2021 IDA-D2010 Loan Disb 503,128.62
Dec 4, 2020 IDA-D2010 Loan Disb 2,355,004.20
Dec 4, 2020 IDA-D0680 Loan Disb 2,040,849.20
Dec 28, 2015 IDA-D0680 Loan Disb 1,047,847.80
May 3, 2016 IDA-D0680 Loan Disb 4,400,000.00
Nov 22, 2016 IDA-D0680 Loan Disb 599,456.60
Jul 12, 2017 IDA-D0680 Loan Disb 1,399,297.50
Jun 9, 2017 IDA-D0680 Loan Disb 238,666.78
Mar 28, 2017 IDA-D0680 Loan Disb 1,264,819.10
Nov 14, 2017 IDA-D0680 Loan Disb 1,958,007.80
Dec 22, 2017 IDA-D0680 Loan Disb 3,040,437.00
Apr 5, 2024 IDA-D0680 Loan Disb -565,526.70
May 28, 2024 IDA-D0680 Loan Disb 74,978.12
Jun 14, 2017 IDA-D2010 Loan Commitment 20,000,000.00
May 26, 2015 IDA-D0680 Loan Commitment 50,000,000.00
May 31, 2023 IDA-D0680 Loan Disb 229,133.73
Jul 21, 2023 IDA-D0680 Loan Disb 147,517.62
Jul 25, 2023 IDA-D0680 Loan Disb 43,255.23
Nov 30, 2023 IDA-D0680 Loan Disb -7,015.03
Jun 5, 2023 IDA-D0680 Loan Disb 113,190.23
Jul 6, 2023 IDA-D0680 Loan Disb 128,296.71
Oct 25, 2023 IDA-D0680 Loan Disb 28,305.63
Oct 27, 2023 IDA-D0680 Loan Disb 26,641.41
Oct 18, 2023 IDA-D0680 Loan Disb 48,560.47
Oct 18, 2023 IDA-D0680 Loan Disb 44,637.41
Oct 17, 2023 IDA-D0680 Loan Disb 40,000.00
Apr 6, 2022 IDA-D0680 Loan Disb 63,578.70
Jun 21, 2022 IDA-D2010 Loan Disb 1,084,325.40
Dec 15, 2021 IDA-D2010 Loan Disb 604,253.40
Dec 23, 2022 IDA-D0680 Loan Disb 220,429.02
Dec 20, 2021 IDA-D0680 Loan Disb 2,111,401.20
Dec 17, 2021 IDA-D2010 Loan Disb 2,366,810.80
Sep 29, 2022 IDA-D0680 Loan Disb 400,000.00
Nov 17, 2022 IDA-D2010 Loan Disb 929,844.40
Sep 14, 2022 IDA-D0680 Loan Disb 476,171.00
Sep 14, 2022 IDA-D2010 Loan Disb 78,512.01
Nov 8, 2023 IDA-D0680 Loan Disb 99,654.35
Nov 30, 2023 IDA-D2010 Loan Disb -768.02
Nov 30, 2023 IDA-D2010 Loan Disb -252.05
Nov 30, 2023 IDA-D0680 Loan Disb -30,521.49
Oct 20, 2023 IDA-D0680 Loan Disb 13,031.08
Oct 20, 2023 IDA-D0680 Loan Disb 14,576.63
Oct 30, 2023 IDA-D0680 Loan Disb 60,178.15
Oct 30, 2023 IDA-D0680 Loan Disb 51,965.68
Nov 21, 2023 IDA-D0680 Loan Disb 30,021.64
Nov 21, 2023 IDA-D0680 Loan Disb 30,021.64
Nov 27, 2023 IDA-D0680 Loan Disb 9,577.97
Nov 3, 2023 IDA-D0680 Loan Disb 7,958.35
Nov 3, 2023 IDA-D0680 Loan Disb 8,522.20
Oct 23, 2023 IDA-D0680 Loan Disb 5,225.41
Oct 23, 2023 IDA-D0680 Loan Disb 9,780.27
Oct 23, 2023 IDA-D0680 Loan Disb 43,718.22
May 31, 2024 IDA-D0680 Loan Disb 14,381.85
Apr 5, 2024 IDA-D2010 Loan Disb -12,543.19
Apr 2, 2021 IDA-D2010 Loan Disb 2,627,591.50
Apr 15, 2021 IDA-D2010 Loan Disb 1,354,345.50
Apr 13, 2021 IDA-D2010 Loan Disb 1,496,432.80
Mar 31, 2021 IDA-D0680 Loan Disb 953,852.60
Jun 25, 2021 IDA-D0680 Loan Disb 577,738.50
Jul 15, 2021 IDA-D0680 Loan Disb 2,425,107.80
Jul 15, 2021 IDA-D2010 Loan Disb 155,298.31
Sep 28, 2021 IDA-D0680 Loan Disb 1,241,217.80
Sep 28, 2021 IDA-D2010 Loan Disb 1,250,909.50
Mar 29, 2022 IDA-D2010 Loan Disb 1,591,940.10

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Unsatisfactory 2023-03-30
Overall Implementation Progress (IP) Moderately Unsatisfactory 2023-03-30
Progress towards achievement of PDO Moderately Satisfactory 2023-03-30
Project Management Moderately Unsatisfactory 2023-03-30
Monitoring and Evaluation Moderately Satisfactory 2023-03-30
Procurement Moderately Unsatisfactory 2023-03-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-02-2023
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-06-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00601518.00618000.00
    DateSeptember 30, 2015March 31, 2023September 30, 2021
    Comment
  • Female beneficiariesValue0.0050.000.00
    DateSeptember 30, 2015May 17, 2018
    Comment
  • Project beneficiaries in localities on the border with the DR including bi-national marketsValue0.0039665.0034000.00
    DateSeptember 30, 2015March 31, 2023September 30, 2021
    Comment
  • Number of people in rural areas and small towns provided with access to Improved Water Sources under the projectValue0.00570558.00588000.00
    DateSeptember 30, 2015March 31, 2023March 31, 2023
    Comment
  • Number of people provided with access to improved water sources under the project except in the areas affected by Hurricane MatthewValue0.00152319.00197000.00
    DateSeptember 30, 2015March 31, 2023March 31, 2023
    Comment
  • Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane MatthewValue0.00342339.00320000.00
    DateJune 14, 2017March 31, 2023March 31, 2023
    Comment
  • Project beneficiaries of small repairs of water systems in the context of COVID-19 emergencyValue0.0075900.0071000.00
    DateMarch 9, 2020March 15, 2023March 31, 2023
    Comment
  • Piped water systems managed sustainably by a Professional Operator (PO) under the projectValue0.0017.0024.00
    DateSeptember 30, 2015March 15, 2023September 30, 2021
    Comment
  • Required functions deconcentrated to targeted OREPAValue0.006.006.00
    DateSeptember 30, 2015March 15, 2023September 30, 2021
    Comment
  • People provided with access to "improved sanitation facilities” under the proj.Value0.0030960.0030000.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • People in rural areas provided with access to "improved sanitation facilities" - femaleValue0.0015000.0015000.00
    DateSeptember 30, 2015March 31, 2023March 31, 2023
    Comment
  • Priority cholera communes targeted under the projectValue0.007.007.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • DINEPA's system in place to respond to major emergenciesValueNoYesYes
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Departments covered by WSS baseline informationValue0.0010.0010.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placein zones affected by Hurricane MatthewValue0.0024.000.00
    DateJune 14, 2017March 15, 2023
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.006576.007750.00
    DateSeptember 30, 2015March 31, 2023September 30, 2021
    Comment
  • DINEPA conducts an annual joint Government/ partners sector reviewValueNoYesYes
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane MatthewValue0.00270019.00270000.00
    DateJune 14, 2017March 15, 2023September 30, 2021
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.00133.00135.00
    DateSeptember 30, 2015March 31, 2023March 31, 2023
    Comment
  • A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in placeValue0.005.005.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • People trained to improve hygiene behavior/sanitation practices under the projectValue0.00981255.0095000.00
    DateNovember 22, 2019March 15, 2023September 30, 2021
    Comment
  • Number of OREPAs among the 4 existing ones, using the baseline developed under the project to prioritize.Value0.004.004.00
    DateSeptember 30, 2015March 31, 2023March 31, 2023
    Comment
  • Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion andsanitation themes and activitiesValue0.0023.0023.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Students and teachers benefitting from improved sanitation facilities in public schools under the projectValue0.0019351.0030000.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Number of OREPAs among the 4 existing ones that have installed an accounting system which facilitates the consolidation of financial information at the central level.Value0.001.002.00
    DateSeptember 30, 2015March 15, 2023September 30, 2021
    Comment
  • Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placeunder the projectValue0.0051.0070.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Households with latrine built during project implementation and of which use is verifiedValue0.005449.001900.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Number of handwashing facilities built in the context of COVID-19 awareness campaignValue0.001095.00995.00
    DateMarch 9, 2020March 15, 2023March 31, 2023
    Comment
  • CAEPAs that include at least 20 percent female representation in project areaValue0.00129.0070.00
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Number of hospitals and health centers whose water supply system was repaired under the COVID-19 emergencyValue0.007.0015.00
    DateMarch 9, 2020March 15, 2023March 31, 2023
    Comment
  • DINEPA acknowledged a gender action planValueNoYesYes
    DateJanuary 1, 2019March 15, 2023March 31, 2023
    Comment
  • A fecal sludge management service chain for rural areas and small towns is definedValueNoYesYes
    DateSeptember 30, 2015March 15, 2023March 31, 2023
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.00100.00100.00
    DateSeptember 30, 2015March 15, 2023September 30, 2021
    Comment