Abstract*

The development objective of Energy Resilience for Climate Adaptation Project for Belize is to demonstrate solutions that enhance the resilience of the energy system to adverse weather and climate change impacts. This project has three components. 1) The first component, Long-Term Planning and Capacity Building for Adaptation, has three subcomponents as follows: (i) Develop the capacity in Belize to carry out long-term energy and climate adaptation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the proposed Energy Resilience for Climate Adaptation Project is to demonstrate solutions that enhancethe resilience of the energy system to adverse weather and climate change impacts. This will be collectively achieved by implementing a wide-ranging and complementary set of activities that include pilot initiatives, infrastructure hardening, and analytical and planning efforts.

Key Details

Project Details

  • P149522

  • Closed

  • Nguyet Anh Pham

  • Government of Belize

  • Belize

  • January 24, 2014

  • (as of board presentation)

    September 12, 2016

  • December 6, 2016

  • US$ 8.00 million

  • B

  • January 19, 2024

  • November 30, 2024

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 3.98
Global Environment Facility (GEF) 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.00
Total Project Cost** 11.97

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-09-11
Procurement Moderately Satisfactory 2024-09-11
Overall Safeguards Rating Moderately Satisfactory 2024-09-11
Progress towards achievement of PDO Moderately Satisfactory 2024-09-11
Financial Management Moderately Satisfactory 2024-09-11
Monitoring and Evaluation Moderately Satisfactory 2024-09-11
Overall Implementation Progress (IP) Moderately Satisfactory 2024-09-11
Counterpart Funding Moderately Satisfactory 2024-09-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Methodologies and procedures to incorporate climate resilience in long-term planning of energy infrastructure and systems developedand adoptedValueNoNoYes
    DateNovember 1, 2016January 19, 2024May 31, 2024
    Comment
  • Transmission network segmented and protected against cascading line faultsValueNoNoYes
    DateNovember 1, 2016January 19, 2024November 30, 2024
    Comment
  • Generation sources available for dispatch despite line faultsValue5.005.007.00
    DateNovember 1, 2016July 31, 2020
    Comment
  • Consumers with enhanced security of electricity supply (reduced outages) due to weather eventsValue0.000.00274000.00
    DateNovember 1, 2016July 31, 2020
    Comment
  • Electricity consumers with enhanced security of electricity supply (reduced outages) despite weather events, of which, those are womenValue0.000.00139192.00
    DateNovember 1, 2016July 31, 2020
    Comment
  • Generation capacity available for dispatch despite line faultsValue82.5082.50110.00
    DateNovember 1, 2016July 31, 2020
    Comment
  • Weak transmission sections in the system reinforced to be more resilientValue0.000.00160.00
    DateNovember 1, 2016January 19, 2024November 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Training sessions on energy sector long-term planning conductedValue0.004.008.00
    DateNovember 1, 2016January 19, 2024September 29, 2023
    Comment
  • Appropriate technologies identified to be used for transmission line design for different terrain typesValueNoNoYes
    DateNovember 1, 2016January 19, 2024December 29, 2023
    Comment
  • Regional stakeholder and citizen engagement conferences held to evaluate and disseminate lessons learned and results achieved in project for enhancing energy resilienceValue0.001.001.00
    DateNovember 1, 2016January 19, 2024November 30, 2024
    Comment
  • Weather monitoring stations are installed and functioningValue0.0012.0025.00
    DateNovember 1, 2016January 19, 2024March 29, 2024
    Comment
  • Vegetable management plan for transmission and distribution lines informed with industry good practiceValueNoYesYes
    DateNovember 1, 2016January 19, 2024December 29, 2023
    Comment
  • Comprehensive emergency preparedness and recovery plan adoptedValueNoNoYes
    DateJuly 9, 2020January 19, 2024May 30, 2022