P149522
Closed
Nguyet Anh Pham
Government of Belize
January 24, 2014
(as of board presentation)
September 12, 2016
December 6, 2016
US$ 11.97 million
Belize Electricity Limited (BEL)
2017
US$ 8.00 million
B
January 19, 2024
November 30, 2024
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 3.98 |
Global Environment Facility (GEF) | 8.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.00 |
Total Project Cost** | 11.97 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-09-11 |
Procurement | Moderately Satisfactory | 2024-09-11 |
Overall Safeguards Rating | Moderately Satisfactory | 2024-09-11 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-11 |
Financial Management | Moderately Satisfactory | 2024-09-11 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-09-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-11 |
Counterpart Funding | Moderately Satisfactory | 2024-09-11 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Methodologies and procedures to incorporate climate resilience in long-term planning of energy infrastructure and systems developedand adopted | Value | No | No | Yes |
Date | November 1, 2016 | January 19, 2024 | May 31, 2024 | |
Comment |
Transmission network segmented and protected against cascading line faults | Value | No | No | Yes |
Date | November 1, 2016 | January 19, 2024 | November 30, 2024 | |
Comment |
Generation sources available for dispatch despite line faults | Value | 5.00 | 5.00 | 7.00 |
Date | November 1, 2016 | July 31, 2020 | ||
Comment |
Consumers with enhanced security of electricity supply (reduced outages) due to weather events | Value | 0.00 | 0.00 | 274000.00 |
Date | November 1, 2016 | July 31, 2020 | ||
Comment |
Electricity consumers with enhanced security of electricity supply (reduced outages) despite weather events, of which, those are women | Value | 0.00 | 0.00 | 139192.00 |
Date | November 1, 2016 | July 31, 2020 | ||
Comment |
Generation capacity available for dispatch despite line faults | Value | 82.50 | 82.50 | 110.00 |
Date | November 1, 2016 | July 31, 2020 | ||
Comment |
Weak transmission sections in the system reinforced to be more resilient | Value | 0.00 | 0.00 | 160.00 |
Date | November 1, 2016 | January 19, 2024 | November 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Training sessions on energy sector long-term planning conducted | Value | 0.00 | 4.00 | 8.00 |
Date | November 1, 2016 | January 19, 2024 | September 29, 2023 | |
Comment |
Appropriate technologies identified to be used for transmission line design for different terrain types | Value | No | No | Yes |
Date | November 1, 2016 | January 19, 2024 | December 29, 2023 | |
Comment |
Regional stakeholder and citizen engagement conferences held to evaluate and disseminate lessons learned and results achieved in project for enhancing energy resilience | Value | 0.00 | 1.00 | 1.00 |
Date | November 1, 2016 | January 19, 2024 | November 30, 2024 | |
Comment |
Weather monitoring stations are installed and functioning | Value | 0.00 | 12.00 | 25.00 |
Date | November 1, 2016 | January 19, 2024 | March 29, 2024 | |
Comment |
Vegetable management plan for transmission and distribution lines informed with industry good practice | Value | No | Yes | Yes |
Date | November 1, 2016 | January 19, 2024 | December 29, 2023 | |
Comment |
Comprehensive emergency preparedness and recovery plan adopted | Value | No | No | Yes |
Date | July 9, 2020 | January 19, 2024 | May 30, 2022 | |
Comment |