ROAD SAFETY SUPPORT PROJECT

Development Objective

To reduce the risk of roadway departure crashes on selected sections of the roads targeted under the RSDP and to strengthen the Government of Nepal’s capacity for improving road safety.

Key Details

Project Details

  • P149606

  • Closed

  • Luquan Tian , Dominic Patella

  • Government of Nepal represented by Ministry of Finance

  • Nepal

  • July 1, 2014

  • (as of board presentation)

    April 8, 2015

  • June 9, 2015

  • US$ 7.47 million

  • Department of Roads

  • South Asia

  • 2015

  • US$ 7.47 million

  • B

  • April 3, 2024

  • July 15, 2017

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Road Safety Program 7.47

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 7.47
Total Project Cost** 7.47

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2017-06-30
Project Management Moderately Satisfactory 2017-06-30
Financial Management Moderately Satisfactory 2017-06-30
Monitoring and Evaluation Moderately Satisfactory 2017-06-30
Procurement Satisfactory 2017-06-30
Overall Implementation Progress (IP) Moderately Satisfactory 2017-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-28-2017
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-20-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDO 1: Reduced risk of road departure crashes at dangerous locations along selected RSDP roads.Value0.0078.0076.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment
  • PDO 2: Strengthened capacity to implement the Nepal’s Road Safety Action Plan (2013)Value0.006.009.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component A: Capacity strengthening for RSAPValue0.002.002.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment
  • Component B: Improved physical safety of RSDP roadsValue0.0070000.0073000.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment
  • Dedicated unit for managing road safetyValue0.001.001.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment
  • Piloting road safety interventions for NepalValue0.002.002.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment
  • Prevention of road departure crashesValue0.0070000.0073000.00
    DateFebruary 15, 2015July 15, 2017July 15, 2017
    Comment