Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 6.54 |
P149629
Closed
Shelley Mcmillan
Government of Mozambique
June 5, 2014
(as of board presentation)
June 5, 2014
June 16, 2014
US$ 6.54 million
Direcção Nacional de Águas / National Director of Water,Instituto Nacional de Meteorologia / National Institute for Meteorlogy
2014
US$ 6.54 million
C
Not Applicable
December 31, 2016
TBD
BANK APPROVED
September 6, 2024
Financier | Commitments |
---|---|
Global Facility for Disaster Reduction and Recovery | 6.54 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.54 |
Total Project Cost** | 6.54 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2016-12-28 |
Progress towards achievement of PDO | Satisfactory | 2016-12-28 |
Project Management | Satisfactory | 2016-12-28 |
Financial Management | Satisfactory | 2016-12-28 |
Monitoring and Evaluation | Satisfactory | 2016-12-28 |
Overall Implementation Progress (IP) | Satisfactory | 2016-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2017 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 09-20-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Flood risk identification improved through the incorporation of new geospatial data in the Limpopo and Zambezi basin plans | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Improved accuracy of areas & pop. at risk of 100-year flood in the Limpopo and Zambezi with improvement to EWS | Value | 0.00 | 100.00 | 100.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 1035304.00 | 320800.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Staff trained in Lidar processing and data management from Limpopo | Value | 0.00 | 50.00 | 25.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Number of which are women | Value | 0.00 | 11.00 | 11.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Female Beneficiaries (Percentage, Core Supplement) | Value | 0.00 | 575066.00 | 192480.00 |
Date | June 20, 2014 | October 13, 2015 | June 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Airborne survey data collected for the Limpopo | Value | Limited Lidar data available | Pre and post processing of data complete | Pre and post processing of data complete |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Data transferred from contractor to client for the Limpopo | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Horizontal resolution of DEMs used for Limpopo | Value | 9000.00 | 1.00 | 15.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Geospatial data stored and managed for the Limpopo | Value | No storage & mgmt. system in place | System under installation | Data utilized through network across agencies |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
New geospatial Limpopo data available for public | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Multi-sector ‘uptake’ of Limpopo Lidar data for applications other than WRM and DRM | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Airborne survey data collected for the Zambezi | Value | No LiDAR data available | Pre and post | Pre and post processing of data complete |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Data transferred from contractor to client for the Zambezi | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Horizontal resolution of DEMs used for Zambezi | Value | 9000.00 | 1.00 | 15.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Geospatial data stored and managed for the Zambezi | Value | No storage & mgmt. system in place | Data storage system under installation | Data utilized through network across agencies |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
New geospatial Zambezi data available for public | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Multi-sector ‘uptake’ of Zambezi Lidar data for applications other than WRM and DRM | Value | No | Yes | Yes |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Staff trained in Lidar processing and data management for the Zambezi | Value | 0.00 | 50.00 | 25.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |
Number of which are women | Value | 0.00 | 11.00 | 11.00 |
Date | June 20, 2014 | December 14, 2016 | June 30, 2017 | |
Comment |