Financier | Commitments |
---|---|
Japan Social Development Fund | 2.75 |
P149690
Closed
Abderrahim Fraiji
Ministry of Planning, Statistics and Regional Integration
June 28, 2017
(as of board presentation)
June 28, 2017
September 10, 2018
US$ 2.75 million
Support for Promotion of Sustainable Livelihoods in the Pool Department Project Implementing Unit,Haut-Commissariat a la Reinsertion des Ex-Combattants
2017
US$ 2.75 million
B
Not Applicable
February 28, 2022
BANK APPROVED
August 11, 2023
Financier | Commitments |
---|---|
Japan Social Development Fund | 2.75 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.75 |
Total Project Cost** | 2.75 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2022-02-24 |
Overall | Moderable | 2022-02-24 |
Progress towards achievement of PDO | Satisfactory | 2022-02-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2023 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of household beneficiaries who received livelihood support, disaggregated by gender | Value | 0.00 | 1920.00 | 3014.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |
Increase of association memberâ??s monthly savings | Value | 0.00 | 30.00 | 37.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of beneficiary households using alternative sustainable sources of energy for productive use | Value | 0.00 | 35.00 | 15.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |
Share of business plans implemented as planned | Value | 0.00 | 35.00 | 35.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |
Pilot youth associations operational | Value | 0.00 | 12.00 | 72.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |
Percentage of grievances registered about the project that are resolved in a timely manner | Value | 0.00 | 70.00 | 75.00 |
Date | September 7, 2018 | February 28, 2022 | January 25, 2022 | |
Comment |