Transit Corridor Improvement Project

Abstract*

The objective of the Transit Corridor Improvement Project for Belarus is to improve transport connectivity, border crossing procedures and safety for domestic and international road users on selected sections of the M6 corridor. There are three components to the project, the first component being improvement of Sections of M6 'Minsk - Grodno' Transit Corridor. This component will finance widening works (from a two-lane road to a four-lane road) in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve transport connectivity, border crossing procedures and safety for domestic and international road users on selected sections of the M6 corridor.

Key Details

Project Details

  • P149697

  • Closed

  • Nijat Valiyev , Yevhen Bulakh

  • Republic of Belarus

  • Belarus

  • June 27, 2014

  • (as of board presentation)

    December 19, 2014

  • May 7, 2015

  • US$ 270.01 million

  • Ministry of Transportation and Communications

  • Europe and Central Asia

  • 2015

  • US$ 250.00 million

  • B

  • May 16, 2023

  • June 15, 2022

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 250.00
Borrower/Recipient 20.01

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 250.00
IDA Commitment N/A
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 270.01

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 25, 2017 IBRD-84590 Loan Disb 1,800,000.00
Sep 13, 2017 IBRD-84590 Loan Disb 1,785,500.00
Sep 28, 2017 IBRD-84590 Loan Disb 933,000.00
Oct 24, 2017 IBRD-84590 Loan Disb 1,300,000.00
Aug 16, 2017 IBRD-84590 Loan Disb 1,267,000.00
Dec 18, 2017 IBRD-84590 Loan Disb 5,790,000.00
Oct 12, 2017 IBRD-84590 Loan Disb 1,306,000.00
Jan 4, 2018 IBRD-84590 Loan Disb 250,000.00
Mar 12, 2018 IBRD-84590 Loan Disb 4,030,000.00
Apr 10, 2018 IBRD-84590 Loan Disb 4,650,000.00
Feb 26, 2018 IBRD-84590 Loan Disb 160,000.00
Apr 15, 2018 IBRD-84590 Int Charges 2,273.23
Feb 12, 2018 IBRD-84590 Loan Disb 4,800,000.00
Jan 16, 2018 IBRD-84590 Loan Disb 6,780,000.00
Apr 15, 2018 IBRD-84590 Int Charges 19,434.76
Apr 15, 2018 IBRD-84590 Int Charges 195,877.80
Apr 15, 2018 IBRD-84590 Int Charges 1,017,978.56
Jul 16, 2018 IBRD-84590 Loan Disb 4,960,000.00
Jul 6, 2018 IBRD-84590 Loan Disb 75,000.00
May 22, 2018 IBRD-84590 Loan Disb 7,080,000.00
Sep 14, 2018 IBRD-84590 Loan Disb 9,000,000.00
Sep 20, 2018 IBRD-84590 Loan Disb 120,000.00
Oct 15, 2015 IBRD-84590 Int Charges 376,023.12
Oct 15, 2015 IBRD-84590 Int Charges 2,627.41
Jan 13, 2016 IBRD-84590 Loan Disb 3,000.00
May 7, 2015 IBRD-84590 Loan Disb 625,000.00
May 7, 2015 IBRD-84590 Fee Charges 625,000.00
Apr 15, 2016 IBRD-84590 Int Charges 312,080.88
Apr 15, 2016 IBRD-84590 Int Charges 3,407.78
Oct 15, 2016 IBRD-84590 Int Charges 303,855.28
Oct 15, 2016 IBRD-84590 Int Charges 51,678.07
Jun 21, 2016 IBRD-84590 Loan Disb 7,000.00
Feb 9, 2017 IBRD-84590 Loan Disb 1,973,500.00
Aug 11, 2016 IBRD-84590 Loan Disb 17,690,000.00
Jan 23, 2017 IBRD-84590 Loan Disb 1,035,000.00
Jan 17, 2017 IBRD-84590 Loan Disb 940,000.00
Jan 23, 2017 IBRD-84590 Loan Disb 1,198,680.00
Dec 12, 2016 IBRD-84590 Loan Disb 1,965,000.00
Sep 10, 2019 IBRD-84590 Loan Disb 1,705,000.00
Jul 17, 2019 IBRD-84590 Loan Disb 10,000.00
Aug 26, 2019 IBRD-84590 Loan Disb 75,000.00
Sep 23, 2019 IBRD-84590 Loan Disb 390,000.00
Nov 13, 2019 IBRD-84590 Loan Disb 2,890,000.00
Oct 11, 2019 IBRD-84590 Loan Disb 2,850,000.00
Oct 15, 2019 IBRD-84590 Int Charges 3,404,568.00
Oct 15, 2019 IBRD-84590 Int Charges 745.68
Oct 16, 2019 IBRD-84590 Loan Disb -5,234,423.00
Oct 15, 2019 IBRD-84590 Int Charges 9,324.81
Oct 15, 2019 IBRD-84590 Int Charges 60,674.01
Sep 18, 2019 IBRD-84590 Loan Disb 25,000.00
Oct 15, 2019 IBRD-84590 Loan Disb 5,234,423.00
Mar 6, 2020 IBRD-84590 Loan Disb 126,000.00
Mar 31, 2020 IBRD-84590 Loan Disb 425,000.00
Jun 6, 2018 IBRD-84590 Loan Disb 245,000.00
Aug 24, 2018 IBRD-84590 Loan Disb 450,000.00
Aug 9, 2018 IBRD-84590 Loan Disb 7,020,000.00
Jul 11, 2018 IBRD-84590 Loan Disb 2,725,000.00
Jun 14, 2018 IBRD-84590 Loan Disb 8,600,000.00
Aug 27, 2018 IBRD-84590 Loan Disb 75,000.00
Oct 11, 2018 IBRD-84590 Loan Disb 6,200,000.00
Nov 5, 2018 IBRD-84590 Loan Disb 2,320,000.00
Dec 12, 2018 IBRD-84590 Loan Disb 5,890,000.00
Jan 18, 2019 IBRD-84590 Loan Disb 500,000.00
Feb 7, 2019 IBRD-84590 Loan Disb 3,910,000.00
Nov 8, 2018 IBRD-84590 Loan Disb 4,330,000.00
Jan 10, 2019 IBRD-84590 Loan Disb 4,115,000.00
Sep 25, 2018 IBRD-84590 Loan Disb 205,000.00
Oct 15, 2018 IBRD-84590 Int Charges 1,150.34
Oct 15, 2018 IBRD-84590 Int Charges 9,066.61
Oct 15, 2018 IBRD-84590 Int Charges 149,587.98
Oct 15, 2018 IBRD-84590 Int Charges 2,061,769.20
Oct 17, 2018 IBRD-84590 Loan Disb 680,000.00
Oct 2, 2018 IBRD-84590 Loan Disb 700,000.00
Oct 23, 2018 IBRD-84590 Loan Disb 256,000.00
May 10, 2019 IBRD-84590 Loan Disb 5,650,000.00
Dec 19, 2014 IBRD-84590 Loan Commitment 250,000,000.00
Jul 11, 2017 IBRD-84590 Loan Disb 2,220,000.00
Jun 20, 2017 IBRD-84590 Loan Disb 2,568,500.00
Jul 6, 2017 IBRD-84590 Loan Disb 3,550,000.00
May 18, 2017 IBRD-84590 Loan Disb 1,742,500.00
May 2, 2017 IBRD-84590 Loan Disb 1,760,000.00
Jun 1, 2017 IBRD-84590 Loan Disb 100,000.00
Mar 14, 2017 IBRD-84590 Loan Disb 1,342,000.00
Jun 15, 2017 IBRD-84590 Loan Disb 1,964,000.00
May 16, 2017 IBRD-84590 Loan Disb 1,485,000.00
Apr 15, 2017 IBRD-84590 Int Charges 281,414.28
Jul 10, 2019 IBRD-84590 Loan Disb 4,845,000.00
Apr 15, 2017 IBRD-84590 Int Charges 216,942.30
Oct 17, 2017 IBRD-84590 Loan Disb 1,090,000.00
Aug 9, 2017 IBRD-84590 Loan Disb 1,620,000.00
Sep 12, 2017 IBRD-84590 Loan Disb 1,233,590.00
Oct 15, 2017 IBRD-84590 Int Charges 8,477.43
Oct 15, 2017 IBRD-84590 Int Charges 244,101.45
Oct 15, 2017 IBRD-84590 Int Charges 556,876.80
Oct 15, 2017 IBRD-84590 Int Charges 1,287.61
Nov 14, 2017 IBRD-84590 Loan Disb 4,068,000.00
Nov 13, 2017 IBRD-84590 Loan Disb 1,515,000.00
Jul 24, 2017 IBRD-84590 Loan Disb 3,255,000.00
Aug 15, 2017 IBRD-84590 Loan Disb 988,224.00
Aug 18, 2017 IBRD-84590 Loan Disb 951,550.00
Sep 15, 2017 IBRD-84590 Loan Disb 759,190.00
Oct 27, 2016 IBRD-84590 Loan Disb 110,000.00
Nov 17, 2016 IBRD-84590 Loan Disb 1,240,000.00
Mar 24, 2017 IBRD-84590 Loan Disb 1,782,000.00
Mar 15, 2017 IBRD-84590 Loan Disb 1,370,000.00
Apr 26, 2017 IBRD-84590 Loan Disb 718,000.00
Apr 10, 2017 IBRD-84590 Loan Disb 1,290,000.00
May 17, 2017 IBRD-84590 Loan Disb 1,035,000.00
Apr 17, 2017 IBRD-84590 Loan Disb 1,320,000.00
Jun 19, 2017 IBRD-84590 Loan Disb 1,143,000.00
Feb 21, 2017 IBRD-84590 Loan Disb 1,074,000.00
Jul 10, 2017 IBRD-84590 Loan Disb 7,065,000.00
Jan 8, 2020 IBRD-84590 Loan Disb 1,375,000.00
Dec 13, 2019 IBRD-84590 Loan Disb 440,000.00
May 13, 2020 IBRD-84590 Loan Disb 311,000.00
Apr 22, 2020 IBRD-84590 Loan Disb 350,000.00
Apr 15, 2020 IBRD-84590 Int Charges 585.30
Apr 15, 2020 IBRD-84590 Loan Repay 10,410,366.00
Apr 15, 2020 IBRD-84590 Int Charges 7,319.28
Apr 15, 2020 IBRD-84590 Int Charges 40,450.10
Apr 15, 2020 IBRD-84590 Int Charges 2,951,325.00
Apr 15, 2020 IBRD-84590 Loan Repay 288.56
May 16, 2019 IBRD-84590 Loan Disb 360,000.00
Jun 10, 2019 IBRD-84590 Loan Disb 5,130,000.00
Apr 15, 2019 IBRD-84590 Loan Disb 15,000.00
Apr 23, 2019 IBRD-84590 Loan Disb 592,000.00
Apr 8, 2019 IBRD-84590 Loan Disb 3,060,000.00
May 23, 2019 IBRD-84590 Loan Disb 225,000.00
Jun 27, 2019 IBRD-84590 Loan Disb 490,000.00
Jun 19, 2019 IBRD-84590 Loan Disb 615,000.00
Aug 14, 2019 IBRD-84590 Loan Disb 2,840,000.00
Jul 24, 2019 IBRD-84590 Loan Disb 180,000.00
Aug 21, 2019 IBRD-84590 Loan Disb 25,000.00
Mar 13, 2019 IBRD-84590 Loan Disb 2,650,000.00
Jun 5, 2019 IBRD-84590 Loan Disb 2,090,000.00
Apr 15, 2019 IBRD-84590 Int Charges 27,991.83
Apr 15, 2019 IBRD-84590 Int Charges 95,650.56
Apr 15, 2019 IBRD-84590 Int Charges 2,906,918.80
Apr 15, 2019 IBRD-84590 Int Charges 2,377.23
Dec 17, 2021 IBRD-84590 Loan Disb 2,715,000.00
Oct 15, 2022 IBRD-84590 Loan Cancel 2,208,789.80
May 20, 2022 IBRD-84590 Loan Disb 111,612.71
Apr 15, 2022 IBRD-84590 Int Charges 560.01
Feb 17, 2022 IBRD-84590 Loan Disb 380,000.00
May 17, 2022 IBRD-84590 Loan Disb 270,921.62
May 11, 2022 IBRD-84590 Loan Disb 36,128.51
May 11, 2022 IBRD-84590 Loan Disb 168,052.64
May 11, 2022 IBRD-84590 Loan Disb 2,995,205.50
Aug 15, 2022 IBRD-84590 Loan Disb 31,200.00
Aug 15, 2022 IBRD-84590 Loan Disb 24,000.00
Jan 14, 2022 IBRD-84590 Loan Disb 275,000.00
Feb 9, 2022 IBRD-84590 Loan Disb 570,000.00
Nov 17, 2021 IBRD-84590 Loan Disb 1,900,000.00
Oct 29, 2021 IBRD-84590 Loan Disb 685,000.00
Oct 26, 2021 IBRD-84590 Loan Disb 810,000.00
Sep 14, 2021 IBRD-84590 Loan Disb 356,000.00
May 23, 2022 IBRD-84590 Loan Disb 55,710.72
May 26, 2022 IBRD-84590 Loan Disb 1,135,144.40
Apr 15, 2021 IBRD-84590 Loan Repay 9,997,240.00
Mar 26, 2021 IBRD-84590 Loan Disb 30,000.00
Apr 15, 2021 IBRD-84590 Loan Repay 1,035,190.06
Jul 12, 2021 IBRD-84590 Loan Disb 46,000.00
Apr 28, 2021 IBRD-84590 Loan Disb 45,000.00
Oct 8, 2021 IBRD-84590 Loan Disb 1,342,000.00
Jul 21, 2021 IBRD-84590 Loan Disb 615,500.00
Oct 15, 2021 IBRD-84590 Int Charges 22,343.60
Oct 15, 2021 IBRD-84590 Int Charges 964,473.80
Oct 15, 2021 IBRD-84590 Loan Repay 560.01
Oct 15, 2021 IBRD-84590 Int Charges 56.54
Oct 15, 2021 IBRD-84590 Loan Repay 11,131,575.00
Oct 15, 2021 IBRD-84590 Int Charges 161.30
Aug 11, 2021 IBRD-84590 Loan Disb 625,000.00
Sep 23, 2021 IBRD-84590 Loan Disb 630,000.00
Aug 18, 2021 IBRD-84590 Loan Disb 818,500.00
Feb 1, 2021 IBRD-84590 Loan Disb 820,000.00
Feb 3, 2021 IBRD-84590 Loan Disb 60,000.00
Apr 6, 2021 IBRD-84590 Loan Disb 325,000.00
Apr 15, 2021 IBRD-84590 Int Charges 1,141.53
Apr 15, 2021 IBRD-84590 Int Charges 7,771.54
Apr 15, 2021 IBRD-84590 Int Charges 25,306.31
Apr 15, 2021 IBRD-84590 Int Charges 1,002,112.25
Jul 8, 2020 IBRD-84590 Loan Disb 10,000.00
Jun 11, 2020 IBRD-84590 Loan Disb 506,000.00
Oct 15, 2020 IBRD-84590 Int Charges 2,844.62
Oct 15, 2020 IBRD-84590 Int Charges 34,958.65
Oct 15, 2020 IBRD-84590 Int Charges 2,056,521.80
Oct 15, 2020 IBRD-84590 Loan Repay 1,141.53
Oct 15, 2020 IBRD-84590 Loan Repay 10,564,463.00
Oct 15, 2020 IBRD-84590 Int Charges 288.56
Oct 13, 2020 IBRD-84590 Loan Disb 1,800,000.00
Nov 12, 2020 IBRD-84590 Loan Disb 810,000.00
Aug 18, 2020 IBRD-84590 Loan Disb 1,360,000.00
Sep 18, 2020 IBRD-84590 Loan Disb 100,000.00
Aug 7, 2020 IBRD-84590 Loan Disb 750,000.00
Sep 11, 2020 IBRD-84590 Loan Disb 2,410,000.00
Dec 15, 2020 IBRD-84590 Loan Disb 355,000.00
Mar 3, 2021 IBRD-84590 Loan Disb 110,000.00
Nov 25, 2020 IBRD-84590 Loan Disb 1,000,000.00
Dec 22, 2020 IBRD-84590 Loan Disb 160,000.00
Mar 26, 2020 IBRD-84590 Loan Disb 95,000.00
Feb 12, 2020 IBRD-84590 Loan Disb 80,000.00
Feb 20, 2020 IBRD-84590 Loan Disb 526,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2021-12-16
Financial Management Satisfactory 2021-12-16
Monitoring and Evaluation Satisfactory 2021-12-16
Overall Implementation Progress (IP) Moderately Satisfactory 2021-12-16
Project Management Satisfactory 2021-12-16
Counterpart Funding Satisfactory 2021-12-16
Procurement Moderately Satisfactory 2021-12-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-07-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-26-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in travel time between Minsk and GrodnoValue220.00172.00220.00
    DateJuly 29, 2014December 14, 2021
    Comment
  • Reduction in average time to complete inwards border clearance procedures (commercial vehicles) at Bruzgi BCPValue126.0082.300.00
    DateJuly 1, 2015December 14, 2021
    Comment
  • Reduction in severe injuries and fatalities on road sections under this projectValue42.0019.0042.00
    DateJuly 1, 2015December 14, 2021
    Comment
  • Vehicle operating costs for medium trucks, along the project road reducedValue0.550.500.55
    DateJuly 29, 2014December 14, 2021
    Comment
  • Percentage of project beneficiaries expressing satisfaction with improved travel experiences along the project roadsValue0.0085.000.00
    DateJuly 1, 2015December 14, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads constructed, non-ruralValue0.00154.000.00
    DateJuly 1, 2015December 14, 2021
    Comment
  • Development of a traffic and road safety co-ordination center (TRSCC)ValueNoNo
    DateJuly 1, 2015December 14, 2021
    Comment
  • Implementation of the “in – channel” clearance procedures policy by State Customs Committee.ValueNoYesSpecifications for infrastructure improvement prep
    DateDecember 14, 2015December 14, 2021
    Comment
  • Direct project beneficiaries (number), of which female (percentage)Valuesee belowsee below
    DateJuly 1, 2015December 14, 2021
    Comment
  • Improved climate for SME investment in road side servicesValueNoYes
    DateJuly 1, 2015December 14, 2021
    Comment
  • Development of a feasibility study for the rehabilitation and road safety improvement of the selected sections of M1 highwayValueNoYes
    DateFebruary 14, 2020December 14, 2021
    Comment
  • Short term construction jobsValue01203 (18%)
    Date
    Comment
  • Improved road safety framework for the management of road construction works and wild animal road crossingsValueNoYes
    DateFebruary 14, 2020December 14, 2021
    Comment
  • Long term maintenance/roadside services jobsValue0312 (36%)
    Date
    Comment
  • Daily road user and border crossing beneficiariesValue027823
    Date
    Comment
  • Annual road safety beneficiariesValue070 (41%)
    Date
    Comment
  • Roads rehabilitated/ repaired under the projectValue0.0025.000.00
    DateMay 15, 2015December 14, 2021
    Comment