2nd Fiscal Effectiveness and Growth DPL

Abstract*

The development objective of the Second Fiscal Effectiveness and Growth Development Policy Project for Romania is supports government reforms to: (a) strengthen fiscal management and the performance of state‐owned enterprises (SOEs) (b) improve the functioning of energy, property, and capital markets. This Fiscal Effectiveness and Growth Development Policy Loan (FEG‐DPL_ series was designed in close collaboration with the government, the European...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed Development Policy Loan (DPL) series supports government reforms to: (a) strengthen fiscal management and the performance of state-owned enterprises (SOEs) (b) improve the functioning of energy, property, and capital markets

Key Details

Project Details

  • P149776

  • Closed

  • Doerte Doemeland , Catalin Pauna

  • Ministry of Public Finance

  • Romania

  • August 31, 2015

  • (as of board presentation)

    December 15, 2016

  • May 31, 2017

  • US$ 558.27 million

  • Ministry of Public Finance

  • Europe and Central Asia

  • 2017

  • US$ 558.27 million

  • N/A

  • Not Applicable

  • December 31, 2017

  • BANK APPROVED

  • P148957

  • March 4, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 558.27

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 558.27
IDA Commitment N/A
IBRD + IDA Commitment 558.27
Lending Instrument
Grant Amount N/A
Total Project Cost** 558.27

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2022 IBRD-86650 Int Charges 7,471,612.50
Apr 15, 2023 IBRD-86650 Int Charges 8,487,399.00
Oct 15, 2023 IBRD-86650 Int Charges 8,072,565.00
Oct 15, 2020 IBRD-86650 Int Charges 8,993,565.00
Apr 15, 2021 IBRD-86650 Int Charges 9,182,754.00
Oct 15, 2021 IBRD-86650 Int Charges 8,911,826.00
Apr 15, 2022 IBRD-86650 Int Charges 8,295,907.50
Oct 15, 2018 IBRD-86650 Int Charges 8,901,465.00
Apr 15, 2018 IBRD-86650 Int Charges 1,208,509.80
Oct 15, 2019 IBRD-86650 Int Charges 8,454,780.00
Apr 15, 2020 IBRD-86650 Int Charges 8,371,890.00
Oct 15, 2017 IBRD-86650 Int Charges 785,700.00
Jul 28, 2017 IBRD-86650 Fee Charges 1,463,250.00
Sep 22, 2017 IBRD-86650 Loan Disb -598,275,010.00
Sep 22, 2017 IBRD-86650 Loan Disb 598,275,010.00
Aug 31, 2017 IBRD-86650 Loan Disb 593,049,980.00
Apr 15, 2018 IBRD-86650 Int Charges 9,457,902.00
Apr 15, 2018 IBRD-86650 Int Charges 189,909.27
Apr 15, 2018 IBRD-86650 Int Charges 284,526.25
Dec 15, 2016 IBRD-86650 Loan Commitment 558,270,020.00
Apr 15, 2024 IBRD-86650 Int Charges 8,179,247.50
Apr 15, 2019 IBRD-86650 Int Charges 8,681,192.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Unsatisfactory 2018-12-14
Progress towards achievement of PDO Moderately Unsatisfactory 2018-12-14
Program Management Moderately Satisfactory 2018-12-14
Monitoring and Evaluation Moderately Satisfactory 2018-12-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-14-2019
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-08-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityHighN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • The number of SOEs with professional Board and management appointedValue25.0032.0080.00
    DateDecember 31, 2013December 29, 2017December 29, 2017
    Comment
  • The average unit price for centrally procured drugs and devicesValue22.22020.0
    DateDecember 31, 2015December 29, 2017December 29, 2017
    Comment
  • Coverage of urban real state registrationValue39.0057.3057.00
    DateDecember 31, 2013December 29, 2017December 29, 2017
    Comment
  • International trade in electricity, exports plus imports (TWh)Value2.69.34
    DateDecember 31, 2012December 29, 2017December 29, 2017
    Comment
  • The number of the MOPF's liability management operationsValue0.000.003.00
    DateDecember 31, 2013June 29, 2018December 29, 2017
    Comment
  • The budget allocated to the portofolio of significant public investment projects monitored by MOPF (in billion RON)Value5.79.06.1
    DateDecember 31, 2014December 29, 2017December 29, 2017
    Comment
  • The budget allocated to means-tested social assistance programs (in billion RON)Value1.21.8
    DateDecember 31, 2014December 28, 2018December 31, 2018
    Comment
  • Number of benchmarks of the secondary emerging market indexValue4.008.008.00
    DateDecember 31, 2013December 29, 2017December 29, 2017
    Comment
  • Amount of natural gas traded at centralized platforms (billion cubic meter)Value05.92
    DateDecember 31, 2013December 29, 2017December 29, 2017
    Comment
  • Energy sector greenhouse gas (GHG) emissions (million tons)Value86.575.480
    DateDecember 31, 2012December 30, 2016December 29, 2017
    Comment