Financier | Commitments |
---|---|
Readiness Fund of the Forest Carbon Partnership Facility | 7.83 |
P149801
Closed
Salimata Follea
Ahoulou Kouame Ernest
September 8, 2014
(as of board presentation)
September 2, 2014
N/A
US$ 7.83 million
Ahoulou Kouame
2015
US$ 7.83 million
B
N/A
June 30, 2021
BANK APPROVED
June 4, 2024
Financier | Commitments |
---|---|
Readiness Fund of the Forest Carbon Partnership Facility | 7.83 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 7.83 |
Total Project Cost** | 7.83 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-12-04 |
Project Management | Satisfactory | 2020-12-04 |
Monitoring and Evaluation | Satisfactory | 2020-12-04 |
Overall Implementation Progress (IP) | Satisfactory | 2020-12-04 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
REDD+ National Infrastructure Finalized | Value | No | Yes | Yes |
Date | January 30, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |
Benefit sharing mechanism finalized | Value | No | No | Yes |
Date | January 30, 2015 | June 30, 2021 | June 30, 2021 | |
Comment |
Adoption of the REDD-plus Strategy | Value | No | Yes | Yes |
Date | January 30, 2015 | November 13, 2020 | June 30, 2021 | |
Comment |
All REDD+ management arrangements are operational | Value | No | Yes | Yes |
Date | January 30, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Adoption of the National REDD+ Strategy by all stakeholders at local and national levels | Value | No | Yes | Yes |
Date | January 30, 2015 | November 13, 2020 | June 30, 2021 | |
Comment |
Establishment and adoption of the national baseline for emissions | Value | No | Yes | Yes |
Date | January 30, 2015 | November 13, 2020 | June 30, 2021 | |
Comment |
Safeguards instruments finalized and published | Value | No | Yes | Yes |
Date | January 30, 2015 | November 13, 2020 | June 30, 2021 | |
Comment |
The REDD-plus strategy is prepared | Value | No | Yes | Yes |
Date | January 29, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |
National REDD-plus readiness management arrangements are in place | Value | No | Yes | Yes |
Date | January 29, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |
National REDD+ Commission, the REDD+ National Committee, the REDD+ Interministerial Technical Committee and the SEP-REDD+ are operational | Value | No | Yes | Yes |
Date | January 30, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |
Set up a Monitoring & Measurement, Reporting and Verification System (MRV) | Value | No | Yes | Yes |
Date | January 30, 2015 | November 19, 2020 | June 30, 2021 | |
Comment |
A Safeguard Information System (SIS) is set up | Value | No | No | Yes |
Date | January 30, 2015 | November 12, 2020 | June 30, 2021 | |
Comment |