Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
P149831
Closed
Diana Rubiano Vargas
Ministry of Economy and Finance
November 18, 2014
(as of board presentation)
March 12, 2015
June 22, 2015
US$ 400.00 million
Unidad de Coordinación de Cooperación Técnica y Financiera - UCCTF
2015
US$ 400.00 million
N/A
Not Applicable
March 12, 2018
BANK APPROVED
September 10, 2020
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 12, 2015 | IBRD-84780 | Loan Commitment | 400,000,000.00 |
Aug 20, 2015 | IBRD-84780 | Fee Charges | 2,000,000.00 |
May 15, 2023 | IBRD-84780 | Int Charges | 1,844,873.40 |
Nov 15, 2023 | IBRD-84780 | Int Charges | 2,210,576.80 |
Nov 15, 2023 | IBRD-84780 | Int Charges | 41,936.26 |
May 15, 2024 | IBRD-84780 | Int Charges | 13,802.57 |
May 15, 2024 | IBRD-84780 | Int Charges | 2,332,555.50 |
May 15, 2022 | IBRD-84780 | Int Charges | 373,061.12 |
Nov 15, 2022 | IBRD-84780 | Int Charges | 1,150,802.40 |
May 15, 2021 | IBRD-84780 | Int Charges | 369,541.66 |
Nov 15, 2020 | IBRD-84780 | Int Charges | 525,933.30 |
Nov 15, 2021 | IBRD-84780 | Int Charges | 364,933.34 |
Nov 15, 2019 | IBRD-84780 | Int Charges | 1,212,866.60 |
May 15, 2020 | IBRD-84780 | Int Charges | 959,038.90 |
May 15, 2018 | IBRD-84780 | Int Charges | 411,872.22 |
Nov 15, 2018 | IBRD-84780 | Int Charges | 1,177,088.90 |
May 15, 2019 | IBRD-84780 | Int Charges | 1,284,597.20 |
Feb 15, 2018 | IBRD-84780 | Loan Disb | -70,000,000.00 |
Feb 15, 2018 | IBRD-84780 | Loan Disb | 70,000,000.00 |
Mar 12, 2018 | IBRD-84780 | Loan Cancel | 330,000,000.00 |
Feb 15, 2018 | IBRD-84780 | Loan Disb | 70,000,000.00 |
May 15, 2023 | IBRD-84780 | Int Charges | 98,177.19 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2018-02-23 |
Program Management | Satisfactory | 2018-02-23 |
Progress towards achievement of PDO | Satisfactory | 2018-02-23 |
Monitoring and Evaluation | Satisfactory | 2018-02-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-27-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 05-03-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Annual budgetary performance report on PLANAGERD implementation under the results-based budgeting programs | Value | None | The 2017 annual report with budgetary performance | Annual budgetary performance reports published for |
Date | January 20, 2015 | February 13, 2018 | March 12, 2018 | |
Comment |
Number of regional governments that have approved regional plans for the prevention and reduction of disaster risk | Value | 0 | 19 | 15/25 |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |
Share of seismic risk reduction in school infrastructure in the Lima Metropolitan Area as a result of PRONIED implementation | Value | Risk Indicator (RI)=20.3 for a portfolio of 1,969 | There has been 10% risk reduction. | 10% reduction |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |
Policies and procedures for the financing of post-disaster rehabilitation and reconstruction processes | Value | None | D.S. 132-2017-EF approved the establishment of the | An Operation Manual approved |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |
Share of eligible low-income households covered by the Grant for Protection of Housing Vulnerable to Seismic Risk | Value | 0 | 61% | 80% of eligible households |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |
Number of approved studies for flood risk prevention and mitigation in watersheds | Value | 0.00 | 3.00 | 4.00 |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |
Number of National Government sectors that approve sector guidelines for the post-disaster reconstruction process | Value | 0.00 | 2.00 | 6.00 |
Date | January 20, 2015 | February 13, 2018 | March 12, 2018 | |
Comment |
Number of National Government agencies with approved operational continuity plans in the event of disasters | Value | 1.00 | 15.00 | 37.00 |
Date | January 20, 2015 | November 8, 2017 | March 12, 2018 | |
Comment |