Financier | Commitments |
---|---|
Borrower/Recipient | 0.24 |
Global Environment Facility (GEF) | 7.20 |
Cooperation in International Waters in Africa | 3.50 |
P149969
Closed
Sanjay Pahuja , Seydou Traore
Volta Basin Authority (VBA)
Western and Central Africa
November 4, 2014
(as of board presentation)
May 21, 2015
December 17, 2015
US$ 0.00 million
Volta Basin Authority (VBA)
2015
US$ 10.70 million
B
Not Applicable
August 31, 2019
TBD
BANK APPROVED
October 18, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 0.24 |
Global Environment Facility (GEF) | 7.20 |
Cooperation in International Waters in Africa | 3.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 10.70 |
Total Project Cost** | N/A |
Name | Review | Date |
---|---|---|
Procurement | Moderately Unsatisfactory | 2019-08-30 |
Summary Global Objective Rating | Moderately Unsatisfactory | 2019-08-30 |
Financial Management | Moderately Satisfactory | 2019-08-30 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2019-08-30 |
Project Management | Moderately Unsatisfactory | 2019-08-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2019-08-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-28-2020 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-29-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Action Plan to implement findings of Institutional Assessment developed and validated by member countries | Value | No | Yes | |
Date | September 15, 2015 | August 31, 2019 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 6000.00 |
Date | September 15, 2015 | August 28, 2019 | January 15, 2019 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | September 15, 2015 | |||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Communications Plan developed and validated by member countries | Value | No | Yes | |
Date | May 2, 2016 | August 28, 2019 | ||
Comment |
Area restored or re/afforested | Value | 0.00 | 0.00 | 200.00 |
Date | September 15, 2015 | August 31, 2019 | January 15, 2019 | |
Comment |
Water Charter drafted and validated by member states | Value | No | Yes | |
Date | September 15, 2015 | August 28, 2019 | ||
Comment |
Number of stakeholders consulted during development of Communications Plan | Value | 0.00 | 500.00 | 0.00 |
Date | September 15, 2015 | August 28, 2019 | ||
Comment |
Area re/afforested | Value | 0.00 | 0.00 | 200.00 |
Date | September 15, 2015 | August 31, 2019 | January 15, 2019 | |
Comment |
Number of priority actions implemented in Volta Basin transboundary zones. | Value | 0.00 | 0.00 | 0.00 |
Date | September 15, 2015 | August 28, 2019 | ||
Comment |