P149990
Active
Aditya Lukas , Rhedon Begolli
North Macedonia
March 27, 2019
(as of board presentation)
January 30, 2020
May 12, 2021
US$ 35.00 million
Ministry of Finance
2020
US$ 27.40 million
N/A
February 22, 2024
September 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 27.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 27.40 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 27.40 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 35.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 30, 2020 | IBRD-90380 | Loan Commitment | 27,400,000.00 |
Sep 15, 2023 | IBRD-90380 | Int Charges | 33,374.43 |
Jun 15, 2023 | IBRD-90380 | Loan Disb | 934,500.56 |
Nov 7, 2023 | IBRD-90380 | Loan Disb | 1,045,482.94 |
Apr 19, 2024 | IBRD-90380 | Loan Disb | 884,227.40 |
Mar 15, 2024 | IBRD-90380 | Loan Repay | 191,931.45 |
Mar 15, 2024 | IBRD-90380 | Int Charges | 30,228.86 |
Mar 15, 2024 | IBRD-90380 | Int Charges | 64,796.69 |
Jun 21, 2024 | IBRD-90380 | Loan Disb | 1,619,467.60 |
Jul 9, 2021 | IBRD-90380 | Loan Disb | 296,425.00 |
May 12, 2021 | IBRD-90380 | Loan Disb | 75,787.50 |
May 12, 2021 | IBRD-90380 | Fee Charges | 75,787.50 |
Sep 15, 2021 | IBRD-90380 | Int Charges | 16,225.84 |
Sep 15, 2021 | IBRD-90380 | Int Charges | 106.25 |
Mar 15, 2022 | IBRD-90380 | Int Charges | 33,628.88 |
Mar 15, 2022 | IBRD-90380 | Int Charges | 239.50 |
Aug 15, 2022 | IBRD-90380 | Loan Disb | 808,678.25 |
Dec 28, 2021 | IBRD-90380 | Loan Disb | 55,214.52 |
Sep 15, 2022 | IBRD-90380 | Int Charges | 30,821.56 |
Sep 15, 2022 | IBRD-90380 | Int Charges | 442.19 |
Mar 15, 2023 | IBRD-90380 | Int Charges | 31,410.20 |
Mar 15, 2023 | IBRD-90380 | Int Charges | 13,499.40 |
Mar 15, 2023 | IBRD-90380 | Loan Repay | 68,166.16 |
Mar 15, 2023 | IBRD-90380 | Int Charges | 174.05 |
Mar 15, 2023 | IBRD-90380 | Int Charges | 4.76 |
Sep 15, 2023 | IBRD-90380 | Int Charges | 31,445.55 |
Sep 15, 2023 | IBRD-90380 | Loan Repay | 122,453.20 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-09-10 |
Project Management | Satisfactory | 2024-09-10 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-10 |
Financial Management | Satisfactory | 2024-09-10 |
Monitoring and Evaluation | Satisfactory | 2024-09-10 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-10 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Projected lifetime energy savings from EE investments in the public sector | Value | 0.00 | 0.00 | 2454434000.00 |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Establishment and operationalization of an EE Fund | Value | No Energy Efficiency Fund for public sector | No Energy Efficiency Fund for public sector | EE Fund is established and operationalized |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Associated CO2 emissions reductions as a result of the energy savings | Value | 0.00 | 0.00 | 235896.00 |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Number of energy auditors, technical designers, constructors, supervisors trained | Value | 0.00 | 0.00 | 100.00 |
Date | October 31, 2019 | June 22, 2023 | December 31, 2025 | |
Comment |
Energy cost saving from EE measures (EURO) | Value | 0.00 | 0.00 | 3851705.00 |
Date | December 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Number of female technical staff trained | Value | 0.00 | 0.00 | 50.00 |
Date | October 31, 2019 | June 22, 2023 | December 31, 2025 | |
Comment |
Associated particulate matter (PM) emission reductions as a result of the investments | Value | 0.00 | 0.00 | 69997.00 |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Female staff hired under service contracts for technical and design work under the Project | Value | 20.00 | 20.00 | 30.00 |
Date | October 31, 2019 | June 22, 2023 | December 31, 2025 | |
Comment |
Number of subprojects completed | Value | 0.00 | 0.00 | 103.00 |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Users committee members satisfied with the renovation consultation processes | Value | 0.00 | 100.00 | 90.00 |
Date | October 31, 2019 | June 22, 2023 | December 31, 2025 | |
Comment |
Number of buildings renovated with energy performance certificates of class C or higher | Value | 0.00 | 0.00 | 101.00 |
Date | December 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 96892.00 |
Date | December 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | October 31, 2019 | January 1, 2024 | December 31, 2025 | |
Comment |
Increase in enduser satisfaction in renovated buildings | Value | 0.00 | 0.00 | 90.00 |
Date | October 31, 2019 | December 1, 2023 | December 31, 2025 | |
Comment |